Resource Utilization by Code MOD0099G0

From DB 39.5.13

Access path

From DB 39.5.11

Access path

From DB 39.5.9

Access path

Up to DB 39.5.9

Access path

Information

From DB 39.5.0

  • In this module, the utilization of a resource selected (from the listbox) is displayed by the code of projects in which this resource is scheduled. The utilization display is done in the form of a histogram.
    • If a department resource has been selected, their child resources are not displayed automatically NEW but can be displayed by clicking on the Display child resources button.

Up to DB 39.5.0

  • In this module, the utilization of a resource selected (from the listbox) is displayed by the code of projects in which this resource is scheduled.
  • Details

    • The causes of utilization (projects and tasks for which the resource is planned or for which he or she has already worked) can be displayed by opening the tree structure.
    • On project and task level, the Remaining effort, Overload, Calculated start date, and Calculated end date of the respective resource are displayed.
    • Remaining effort and Overload are additionally summarized on resource level.
    • In the scale area, resource dates per project and task are additionally represented in a Gantt chart.

    New from DB 39.5.11

    Notes
    • Only the utilization in
      • projects with Status = "1" (active projects) is displayed.
      • projects which have scheduling data in the period from today - 30 d up to today + 365 d is displayed.
    • tasks for which the resource in question is planned and which already have an Actual end are displayed grayed out.

    Note

    • PLANTA recommends to carry out a replanning of all projects before viewing the utilization diagram, especially if changes have been made to the resource structure.

    Legend: Histogram

    From DB 39.5.15

    Symbol Meaning Color Comment
    CodeADB14.png Planned load (remaining load) of the resource(s) in projects The color of the bar is determined by the code of the projects.
    CodeADB14.png Code A
    CodeBDB14.png Code B
    CodeCDB14.png Code C
    CodeDDB14.png Code D
    CodeEDB14.png Code E
    The code is defined in the Project Core Data module of the respective project.
    The values for the histogram bars are each calculated from the Planned code 1 to Planned code 5 columns.
    ActDB12.png Actual load of the resource(s)   The values for the histogram bar are taken from the Used column from the period records of the resource(s) (DT468). The values in the period records, in turn stem from the working time recording of the resources (DT472).
    KapLinieDB15.png Available capacity of resource(s)   The values for histogram bars are calculated from the Available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
    The limiting line at the top of the bar will be visible despite of overlapping by utilization bars.
    GrundlastLinieDB15.png Basic load of resource(s)   The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, again, comes from the general basic load defined for the resource in the Resource Data Sheet.
    The limiting line at the top margin of the bar will be visible despite overlapping by utilization bars.

    From DB 39.5.14

    Symbol Meaning Color Comment
    CodeADB14.png Planned load (remaining load) of the resource(s) in projects The color of the bar is determined by the code of the projects.
    CodeADB14.png Code A
    CodeBDB14.png Code B
    CodeCDB14.png Code C
    CodeDDB14.png Code D
    CodeEDB14.png Code E
    The code is defined in the Project Core Data module of the respective project.
    The values for the histogram bars are each calculated from the Planned code 1 to Planned code 5 columns.
    ActDB12.png Actual load of the resource(s)   The values for the histogram bar are taken from the Used column from the period records of the resource(s) (DT468). The values in the period records, in turn stem from the working time recording of the resources (DT472).
    KapLinieDB14.png Available capacity of resource(s)   The values for histogram bars are calculated from the Available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
    The limiting line at the top of the bar will be visible despite of overlapping by utilization bars.
    GrundlastLinieDB14.png Basic load of resource(s)   The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, again, comes from the general basic load defined for the resource in the Resource Data Sheet.
    The limiting line at the top margin of the bar will be visible despite overlapping by utilization bars.

    From DB 39.5.12

    Symbol Meaning Color Comment
    CodeADB12.PNG Planned load (remaining load) of the resource(s) in projects The color of the bar is determined by the code of the projects.
    CodeADB12.PNG Code A
    CodeBDB12.PNG Code B
    CodeCDB12.PNG Code C
    CodeDDB12.PNG Code D
    CodeEDB12.PNG Code E
    The code is defined in the Project Core Data module of the respective project.
    The values for the histogram bars are each calculated from the Planned code 1 to Planned code 5 columns.
    IstHisto.png Actually incurring load (actual load) of the resource(s)   The values for the histogram bar are taken from the Used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472).
    KapLinie.png Available capacity of the resource(s)   The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
    NEWThe limiting line at the top of the bar will be visible despite of overlapping by utilization bars.
    GrundlastLinie.png Basic load of resource(s)   The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, again, comes from the general basic load defined for the resource in the Resource Data Sheet.
    NEWThe limiting line at the top margin of the bar will be visible despite overlapping by utilization bars.
    Faktor4.png Factor 4 of resource(s)   The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet.
    Faktor5.png Factor 5 of resource(s)   The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, again, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet.

    From DB 39.5.8

    Symbol Meaning Color Comment
    CodeHisto.png Planned load of the resource(s) in projects The color of the bar is determined by the code of the projects.
    A.png Code A
    B.png Code B
    C.png Code C
    D.png Code D
    E.png Code E
    The code is defined in the Project Core Data module of the respective project.
    The values for the histogram bars are each calculated from the Planned code 1 to Planned code 5 columns.
    IstHisto.png Actually incurring load (actual load) of the resource(s)   The values for the histogram bar are taken from the Used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472).
    KapLinie.png Available capacity of the resource(s)   The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
    NEWThe limiting line at the top of the bar will be visible despite of overlapping by utilization bars.
    GrundlastLinie.png Basic load of resource(s)   The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, again, comes from the general basic load defined for the resource in the Resource Data Sheet.
    NEWThe limiting line at the top margin of the bar will be visible despite overlapping by utilization bars.
    Faktor4.png Factor 4 of resource(s)   The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet.
    Faktor5.png Factor 5 of resource(s)   The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, again, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet.

    Up to DB 39.5.8

    Symbol Meaning Color Comment
    CodeHisto.png Planned load of the resource(s) in projects The color of the bar is determined by the code of the projects.
    A.png Code A
    B.png Code B
    C.png Code C
    D.png Code D
    E.png Code E
    The code is defined in the Project Core Data module of the respective project.
    The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns.
    IstHisto.png Actually incurring load (actual load) of the resource(s)   The values for the histogram bar are taken from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472).
    Kap.png Available capacity of resource(s)   The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
    GrundlastAbDb8.png Basic load of resource(s)   The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load value defined for the resource in the Resource Data Sheet.
    Faktor4.png Factor 4 of resource(s)   The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet.
    Faktor5.png Factor 5 of resource(s)   The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, again, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet.

    Legend: Bar diagram (project/proposal/resource)

    From DB 39.5.14

    Symbol Meaning Color Comment
    WunschDB14.png Task requested dates   Requested start and Requested end of a task are defined in the Schedule module.
    KalkPRDB14.png Calculated dates of the selected resource for the selected task in the selected project The color of the bar is determined by the code of the respective project. For the meaning of the individual code colors, see the histogram scale. Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.
    ActDB12.png Calculated dates of the selected resource for the selected task in the selected project The bar is white hatched. Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the reported hours worked of the corresponding resource (DT472) or are edited manually.
    Puffer.png Latest task dates   Latest start and Latest end of a task are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.

    From DB 39.5.12

    Symbol Meaning Color Comment
    Wunsch.png Task requested dates   Requested start and Requested end of a task are defined in the Schedule module.
    KalkPRDB12.PNG Calculated dates of the selected resource for the selected task in the selected project The color of the bar is determined by the code of the respective project. For the meaning of the individual code colors, see the histogram scale. Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.
    ActDB12.png Actual dates of the selected resource for the selected task in the selected project   Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from working time recording of the corresponding resource (DT472) or are edited manually.
    Puffer.png Latest task dates   Latest start and Latest end of a task are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.

    Up to DB 39.5.12

    Symbol Meaning Color Comment
    Wunsch.png Task requested dates   Requested start and Requested end of a task are defined in the Schedule module.
    Kalk.png Calculated dates of the selected resource for the selected task in the selected project The color of the bar is determined by the code of the respective project. For the meaning of the individual code colors, see the histogram scale. Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.
    Ist.png Actual dates of the selected resource for the selected task in the selected project   Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the working time recording of the corresponding resource (DT472) or are edited manually.
    Puffer.png Latest task dates   Latest start and Latest end of a task are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.

    Topic attachments
    I Attachment History Size Date Comment
    Pngpng Ist.png r1 0.3 K 2011-07-20 - 12:36  
    Pngpng Kalk.png r1 0.4 K 2011-07-20 - 12:37  

             PLANTA project









     
    • Suche in Topic-Namen

    • Suche in Topic-Inhalten
    This site is powered by the TWiki collaboration platform Powered by Perl