The documentation from version 39.5.17 of PLANTA project can be found in the new PLANTA Online Help.

Status Report MOD009A52

Access path

From DB 39.5.0

  • Project panel (Proposal panel) NEW Status Click on the link in the ID field of the required status report Status Report (the existing status report is opened)
  • Project panel (Proposal panel) NEW Status Click on the Create baseline report or Create status report or Create final report buttton Status Report (a new status report is created)

Up to DB 39.5.0

  • Project panel (Proposal panel) Status Click on the link in the ID field of the required status report Status Report (the existing status report is opened)
  • Project panel (Proposal panel) Status Click on the Create baseline report or Create final report buttton Status Report (a new status report is created)
  • Information

    • In this module, the data which was which was transferred from the Status module and frozen at a specific time is displayed. Here, no data can be changed or edited. All fields are set to "output".

    From DB 39.5.9

    Details
    • In the status report, the fixed data is split in several areas depending on the Costs, Effort, Dates, etc. factors.
    • In each area, the following data is displayed in the header:
      • the manager’s estimate on the respective factor
        • The estimate is visualized by a thumb symbol.
          • For factors for which no estimate has been entered yet, no thumb symbol is displayed here.
      • Comments
    • In the Costs, Effort, and Dates subareas, the following data is displayed additionally:
      • the frozen calculated status of the deviation values of the respective factor: Total vs. budget for costs and effort, and requested vs. calculated for dates
        • This is visualized by traffic light triangles with a specification of the percentage deviation of costs and effort, and the deviation of dates in days.
          • red: costs/effort overrun by more than 5%, date delay of more than 5 days
          • yellow: costs/effort overrun by up to 5%, date delay of up to 5 days
          • green: costs/effort not overrun, no delay
          • For dates, both the project end date deviation value as well as the master milestone end date are indeed instanced, the respective traffic light, however, refers to the worst of both values.
      • the project trend compared to the report that was active at the time of creation of the current report.
        • This is visualized by trend arrows specifying the percentage deviation of costs and effort and the deviation of dates in days.
          • Arrow up = negative trend, arrow down = positive trend.
    • In some areas, details can be viewed by expanding the tree structure.
      • When you expand the
        • Costs area, details on the cost budget, two cost trend graphics as well as the Earned Value Analysis are displayed.
          • Graphic 1: cumulated total costs from the selected status report (provided that the report has been released) and from the baseline (if it exists)
          • Graphic 2: total costs per month from the selected status report (provided that the report has been released) and from the baseline (if it exists)
        • Effort area, details on the effort budget and two effort trend graphics are displayed.
          • Graphic 1: cumulated total effort from the selected status report (provided that the report has been released) and from the baseline (if it exists)
          • Graphic 2: total effort per month from the selected status report (provided that the report has been released) and from the baseline (if it exists)
        • Dates area, the dates and the duration of the project, milestone and master milestone dates, as well as milestone/master milestone trend graphics are displayed.
        • Risks/opportunities area,
          • the damage and gross profit values of the project/program resulting from the risks or opportunities as well as
          • the individual risks and opportunities are listed including their measures in the respective Risks and Opportunities subareas.

    From DB 39.5.7

    Details
    • In the status report, the fixed data is split in several areas depending on the Costs, Effort, Dates, etc. factors.
    • In each area, the following data is displayed in the header:
      • the manager’s estimate on the respective factor
        • The estimate is visualized by a thumb symbol.
          • For factors for which no estimate has been entered yet, no thumb symbol is displayed here.
      • Comments
    • In the Costs, Effort, and Dates subareas, the following data is displayed additionally:
      • the frozen calculated status of the deviation values of the respective factor: Total vs. budget for costs and effort, and requested vs. calculated for dates
        • This is visualized by traffic light triangles with a specification of the percentage deviation of costs and effort, and the deviation of dates in days.
          • red: costs/effort overrun by more than 5%, date delay of more than 5 days
          • yellow: costs/effort overrun by up to 5%, date delay of up to 5 days
          • green: costs/effort not overrun, no delay
          • For dates, both the project end date deviation value as well as the master milestone end date are indeed instanced, the respective traffic light, however, refers to the worst of both values.
      • the project trend compared to the report that was active at the time of creation of the current report.
        • This is visualized by trend arrows specifying the percentage deviation of costs and effort and the deviation of dates in days.
          • Arrow up = negative trend, arrow down = positive trend.
    • In some areas, details can be viewed by expanding the tree structure.
      • When you expand the
        • Costs area, details on the cost budget, two cost trend graphics as well as the Earned Value Analysis are displayed.
          • Graphic 1: cumulated total costs from the selected status report (provided that the report has been released) and from the baseline (if it exists)
          • Graphic 2: total costs per month from the selected status report (provided that the report has been released) and from the baseline (if it exists)
        • Effort area, details on the effort budget and two effort trend graphics are displayed.
          • Graphic 1: cumulated total effort from the selected status report (provided that the report has been released) and from the baseline (if it exists)
          • Graphic 2: total effort per month from the selected status report (provided that the report has been released) and from the baseline (if it exists)
        • Dates area, the dates and the duration of the project, milestone and master milestone dates, as well as milestone/master milestone trend graphics are displayed.
        • Risks/opportunities area,
          • the damage and gross profit values of the project/program resulting from the risks or opportunities as well as
          • the individual risks and opportunities are listed including their measures in the respective Risks and Opportunities subareas.
            • NEW In the Risks subarea, a matrix diagram which displays the number of risks measured from their Damage extent and its Probability of occurrence in the high, medium and low categories is additionally visualized.

    From DB 39.5.5

    Details
    • In the status report, the fixed data is split in several areas depending on the Costs, Effort, Dates, etc. factors.
    • In each area, the following data is displayed in the header:
      • the manager’s estimate on the respective factor
        • The estimate is visualized by a thumb symbol.
          • For factors for which no estimate has been entered yet, no thumb symbol is displayed here.
      • Comments
    • In the Costs, Effort, and Dates subareas, the following data is displayed additionally:
      • the frozen calculated status of the deviation values of the respective factor: Total vs. budget for costs and effort, and requested vs. calculated for dates
        • This is visualized by traffic light triangles with a specification of the percentage deviation of costs and effort, and the deviation of dates in days.
          • red: costs/effort overrun by more than 5%, date delay of more than 5 days
          • yellow: costs/effort overrun by up to 5%, date delay of up to 5 days
          • green: costs/effort not overrun, no delay
      • the project/program trend compared to the report that was active at the time of creation of the current report.
        • This is visualized by trend arrows specifying the percentage deviation of costs and effort and the deviation of dates in days.
          • Arrow up = negative trend, arrow down = positive trend.
    • In some areas, details can be viewed by expanding the tree structure.
      • When you expand the
        • Costs area, details on the cost budget, two cost trend graphics as well as the Earned Value Analysis NEW are displayed.
          • Graphic 1: cumulated total costs from the selected status report (provided that the report has been released) and from the baseline (if it exists)
          • Graphic 2: total costs per month from the selected status report (provided that the report has been released) and from the baseline (if it exists)
        • Effort area, details on the effort budget and two graphics on the effort trend are displayed.
          • Graphic 1: cumulated total effort from the selected status report (provided that the report has been released) and from the baseline (if it exists)
          • Graphic 2: total effort per month from the selected status report (provided that the report has been released) and from the baseline (if it exists)
        • Dates factor, dates and duration of the project as well as milestone and master milestone dates are displayed.
        • Risks/opportunities area,
          • the damage and gross profit values of the project/program resulting from the risks or opportunities as well as
          • the individual risks and opportunities are listed including their measures in the respective Risks and Opportunities subareas.

    From DB 39.5.0

    Details
    • In the status report, the fixed data is split in several areas depending on the Costs, Effort, Dates, etc. factors.
    • In each area, the following data is displayed in the header:
      • the manager’s estimate on the respective factor
        • The estimate is visualized by a thumb symbol.
          • For projects/programs for which no estimate has been entered yet, no thumb symbol is displayed here.
      • Comments
    • In the Costs, Effort, Dates, and Milestones subareas, the following data is displayed additionally:
      • the frozen calculated status of the deviation values of the respective factor: Total vs. budget for costs and effort, and requested vs. calculated for dates
        • This is visualized by traffic light triangles with a specification of the percentage deviation of costs and effort, and the deviation of dates in days.
          • red: costs/effort overrun by more than 5%, date delay of more than 5 days
          • yellow: costs/effort overrun by up to 5%, date delay of up to 5 days
          • green: costs/effort not overrun, no delay
      • the project trend compared to the report that was active at the time of creation of the current report.
        • This is visualized by trend arrows specifying the percentage deviation of costs and effort and the deviation of dates in days.
          • Arrow up = negative trend, arrow down = positive trend.
    • In some subareas, details can be viewed by expanding the tree structure.
      • When you expand the
        • Costs area, details on the cost budget and two graphics on the cost trend are displayed.
          • Graphic 1: cumulated total costs from the selected status report (provided that the report has been released) and from the baseline (if it exists)
          • Graphic 2: total costs per month from the selected status report (provided that the report has been released) and from the baseline (if it exists)
        • Effort area, details on the effort budget and two graphics on the effort trend are displayed.
          • Graphic 1: cumulated total effort from the selected status report (provided that the report has been released) and from the baseline (if it exists)
          • Graphic 2: total effort per month from the selected status report (provided that the report has been released) and from the baseline (if it exists)
        • Dates area, dates and duration of the project as well as milestone and master milestone dates NEW are displayed.
        • Milestones area, milestone and master milestone dates are displayed.
        • Risks/Opportunities area NEW, damage and gross profit numbers of the project are displayed.
    • For newly created or non released status reports, you can edit the Measures and Decisions fields (depending on the user's rights).

    Up to DB 39.5.0

    Details
    • In the status report, the fixed data is split in several areas depending on the Costs, Effort, Dates, etc. factors.
    • In each area, the following data is displayed in the header:
      • the manager’s estimate on the respective factor
        • The estimate is visualized by a thumb symbol.
          • For factors for which no estimate has been entered yet, no thumb symbol is displayed here.
      • Comments
    • In the Costs, Effort, Dates, and Milestones subareas, the following data is displayed additionally:
      • the frozen calculated status of the deviation values of the respective factor: Total vs. budget for costs and effort, and requested vs. calculated for dates
        • This is visualized by traffic light triangles with a specification of the percentage deviation of costs and effort, and the deviation of dates in days.
          • red: costs/effort overrun by more than 5%, date delay of more than 5 days
          • yellow: costs/effort overrun by up to 5%, date delay of up to 5 days
          • green: costs/effort not overrun, no delay
      • the project trend compared to the report that was active at the time of creation of the current report.
        • This is visualized by trend arrows specifying the percentage deviation of costs and effort and the deviation of dates in days.
          • Arrow up = negative trend, arrow down = positive trend.
    • In some areas, details can be viewed by expanding the tree structure.
      • When you expand the
        • Costs area, details on the cost budget and two graphics on the cost trend are displayed.
          • Graphic 1: cumulated total costs from the selected status report (provided that the report has been released) and from the baseline (if it exists)
          • Graphic 2: total costs per month from the selected status report (provided that the report has been released) and from the baseline (if it exists)
        • Effort area, details on the effort budget and two graphics on the effort trend are displayed.
          • Graphic 1: cumulated total effort from the selected status report (provided that the report has been released) and from the baseline (if it exists)
          • Graphic 2: total effort per month from the selected status report (provided that the report has been released) and from the baseline (if it exists)
        • Dates area, project dates and duration are displayed.
        • Milestones area, milestone and master milestone dates are displayed.
    • For newly created or non released status reports, you can edit the Measures and Decisions fields (depending on the user's rights).

    Notes and technical details

    From DB 39.5.0

    • All values that are to be displayed and fixed in status reports are values summarized via the project structure, i.e. for each selected project it is the sum of the values of the project itself and all of its subprojects.
    • The values of the status reports are saved in particular data tables.
      • General project data and dates in DT823
      • NEW Costs and effort of the project level in DT284
      • NEW Costs and effort of the yearly tranches in DT285
      • NEW Benefit and revenues in DT835
      • NEW Opportunities in DT872
      • NEW Risks in DT831
      • Risk measures in DT823
      • Opportunity measures in DT873

    Up to DB 39.5.0

  • The values of the status reports are saved in particular data tables.
    • General project data and dates in DT823
    • Costs, effort, revenues and benefit of the project level in DT823
    • Costs, effort, revenues and benefit of the project level in DT835
    • Risks and Opportunities in DT823
    • Measures in DT823
  • Module Variants

    From DB 39.5.0

    Base The frozen status of project costs, effort, dates, quality as well as risks/opportunities NEW is displayed.
    complete The frozen status of the descriptive data, evaluation data, todo items, risks/opportunities, and process steps is displayed.

    Up to DB 39.5.0

    Base The frozen status of project costs, effort, dates, and quality is displayed.
    complete The frozen status of the descriptive data, evaluation data, todo items, risks/opportunities, and process steps is displayed.

    See also: Module Variants

    Release Status Report

    Procedure

    From DB 39.5.0

    • Click on the Approve button.
    • Confirm the Status report cannot be changed after it has been released. Continue? dialog message with Yes.

    Up to DB 39.5.0

  • Click on the Submit button.
  • Confirm the Status report cannot be changed after it has been released. Continue? dialog message with Yes.
  • Notes

    Refresh Status Report

    Information
    • If changes are made to the project between report creation and release that are to be included in the report, the status report must be refreshed before the release.

    Procedure

    From DB 39.5.5

    • Click on the Refresh button.
    • Confirm the Do you really want to refresh this data? dialog message with Yes.
      • As a result, dates, costs, and budgets of the affected project are calculated anew (NEW). These and other possibly updated data are transferred to the status report.
      • If comments, measures, and decisions have been changed in the Status module in the meantime, the new data is included in the status report as well when it is refreshed.

    Up to DB 39.5.5

  • Click on the Refresh button.
  • Confirm the Do you really want to refresh this data? dialog message with Yes.
    • As a result, the data updated in the project is included in the status report.
  • Delete Status Report

    Procedure
    • Click on the Delete button.
    • Confirm the Do you really want to delete this data? message with Yes.
    • The status report is deleted.

    Notes

    New from DB 39.5.14

    Export Status Report to PowerPoint

    Information
    • Via the PowerPoint symbol in the header area of the module, the data displayed in the module can be exported to a PowerPoint file. The PowerPoint template file must therefore be stored in the client.
      • In the PLANTA standard delivery, a standard PowerPoint template is already contained in the client and can be adjusted individually if desired. For more information, see the PowerPointExport topic.

             PLANTA project









     
    • Suche in Topic-Namen

    • Suche in Topic-Inhalten
    This site is powered by the TWiki collaboration platform Powered by Perl