DT282 Project/year/CTGr New from DB 39.5.0
Warning
- Between DB 39.5.0 and 39.5.7, the current addition was used for the values without structure summarization and the total addition for values with structure summarization. From DB 39.5.7, the values without structure summarization have the (without subprojects) addition and values with structure summarization do not have an addition.
DI061219 Effort budget not allocated
Difference between the budget assigned to the subprojects and the main project budget (model
top down)
DI063101 OLE costs deviation sum program
Traffic light for the visualization of the cost deviation:
Total costs from
Cost budget as a sum value of the selected yearly tranche
The traffic light is only displayed if the budget value is available (i.e. > 0).
DI062977 % effort deviation sum
Percentage deviation of the effort:
Total effort from
Effort budget as a sum value of the yearly tranche
DI061216 Cost budget not distributed
Difference between the budget assigned to the subproject (sum of the approved (o. TP = withoutsubprojects) and the main project budget (approved value) in the selected yearly tranche
It is only used in the "Top-down" model in structured projects.
DI060640 Effort deviation
Deviation of the effort values:
Total effort from
Effort budget
DI060583 Rem. costs (without subprojects)
Remaining costs of the project without considering its subprojects for the selected year
DI060495 Cost budget approved (without subprojects)
Approved cost budget of the project without considering its subprojects for the selected year
DI060649 % cost deviation (without subprojects) sum
Percentage deviation of the costs:
Total costs (without subprojects) from
Cost budget (without subprojects) as a sum value of the yearly tranche
DI060658 OLE effort deviation (without subprojects) sum
Traffic light for the visualization of the effort deviation:
Total effort (without subprojects) from
Budget (without subprojects)
The traffic light is only displayed if the budget value is available (i.e. > 0).
DI061242 Total costs active SR
DI060651 OLE cost deviation
Traffic light for the visualization of the cost deviation:
Total costs from
Cost budget
DI060639 Cost deviation
Deviation of the cost values:
Total costs from
Cost budget
DI060645 Cost deviation (without subprojects)
Deviation of the cost values:
Total costs (without subprojects) from
Cost budget (without subprojects) in the selected yearly tranche
DI060648 % effort deviation (without subprojects)
Percentage deviation of the effort values:
Total effort (without subprojects) from
Effort budget (without subprojects) in the selected yearly tranche
DI060509 Remaining effort
For projects: Remaining effort of the project and all of its subprojects (sum of the
Remaining effort (without subprojects) values of the projects and all of its subprojects) for the selected year
For programs: Remaining effort of all projects assigned to the program (sum of the
Remaining effort values of the projects) for the selected year
DI060773 Cost budget requested
For projects: Requested cost budget of the project and all of its subprojects (sum of the
Remaining effort (without subprojects) values of the projects and all of its subprojects) for the selected year
For programs: Requested cost budget of all projects assigned to the program (sum of the
Cost budget requested values of the projects) for the selected year
DI060650 % effort deviation (without subprojects) sum
DI060508 Total effort
For projects: Total effort of the project and all of its subprojects (sum of the
Total effort (without subprojects) values of the projects and all of its subprojects) for the selected year
For programs: Total effort of the of the program (sum of the
Total effort values of all projects assigned to the program) for the selected year
DI060513 Effort budget requested (without subprojects)
Requested effort budget of the project without considering its subprojects for the selected year
DI060504 Effort budget (without subprojects)
Effort budget of the project without considering its subprojects for the selected year
DI060498 Actual costs
For projects: Actual costs of the project and all of its subprojects (sum of the
Actual costs (without subprojects) values of the projects and all of its subprojects) for the selected year
For programs: Actual costs of all projects assigned to the program (sum of the
Actual costs values of all projects assigned to the program) for the selected year
DI060502 Total costs baseline
For projects: Total cost budget from the baselines of the project and all of its subprojects (sum of the
Cost budget baseline (without subprojects) values from the baselines of the project and all of its subprojects for the selected year
For programs: Total costs from the baselines of all projects assigned to the program (sum of the
Cost budget baseline values of all projects assigned to the program) for the selected year
DI060771 Effort budget requested
For projects: Requested effort budget of the project and all of its subprojects (sum of the
Effort budget requested (without subprojects) values of the projects and all of its subprojects) for the selected year
For programs: Requested effort budget of all projects assigned to the program (sum of the
Effort budget requested values of the projects) for the selected year
DI060656 OLE effort deviation sum
Traffic light for the visualization of the effort deviation (
Total effort from
Effort budget) in the sum line of the selected yearly tranche
The traffic light is only displayed if the budget value is available (i.e. > 0).
DI060642 % effort deviation
Percentage deviation of the effort values (
Total effort from
Effort budget) in the selected cost type group of the selected yearly tranche
DI060510 Actual effort
For projects: Actual effort of the project and all of its subprojects (sum of the
Actual effort (without subprojects) values of the projects and all of its subprojects) for the selected year
For programs: Actual effort of all projects assigned to the program (sum of the
Actual effort values of the projects) for the selected year
DI060492 Cost budget subprojects
Cost budget of all subprojects without the project itself (sum of the
Cost budget (without subprojects) values of the subprojects) for the selected year
DI060491 Cost budget (without subprojects)
Cost budget of the project without considering its subprojects for the selected year
DI060655 OLE effort deviation
Traffic light for the visualization of the effort deviation (
Total effort from
Effort budget) in the selected cost type group of the selected yearly tranche
The traffic light is only displayed if the budget value is available (i.e. > 0).
DI060653 OLE cost deviation (without subprojects)
Traffic light for the visualization of the cost deviation (
Total costs from
Cost budget) in the selected cost type group of the selected yearly tranche
The traffic light is only displayed if the budget value is available (i.e. > 0).
DI060586 Effort costs (without subprojects)
Total costs (actual + remaining) of the project without considering its subprojects for the selected year
DI060589 Total effort (without subprojects)
Total effort (actual + remaining) of the project without considering its subprojects for the selected year
DI060512 Total effort baseline (without subprojects)
Total effort (actual + remaining) from the baseline of the project without considering its subprojects
DI060505 Effort budget subprojects
Sum of the
Effort budget (without subprojects) values of all subprojects of the project without the project itself for the selected year
DI060501 Total costs
For projects: Total costs of the project and all of its subprojects (sum of the
Total costs (without subprojects) values of the project and all of its subprojects) for the selected year
For programs: Total costs of all projects assigned to the program (sum of the
Total costs values of all projects assigned to the program) for the selected year
DI060494 Cost budget requested (without subprojects)
Requested cost budget of the project without considering its subprojects for the selected year
DI060493 Cost budget
For projects: Cost budget of the project and all of its subprojects (sum of the
Cost budget (without subprojects) values of the project and all of its subprojects) for the selected year
For programs: Cost budget of all projects assigned to the program (sum of the
Cost budget values of the projects) for the selected year
DI060646 Effort deviation (without subprojects)
Deviation of the effort:
Total effort (without subprojects) from
Effort budget (without subprojects)
DI060657 OLE effort deviation (without subprojects)
Traffic light for the visualization of the effort deviation (
Total effort from
Effort budget) in the selected cost type group of the selected yearly tranche
The traffic light is only displayed if the budget value is available (i.e. > 0).
DI060584 Actual costs (without subprojects)
Actual costs of the project without considering its subprojects for the selected year
DI060587 Actual effort (without subprojects)
Actual effort of the project without considering its subprojects for the selected year
DI060503 Liability
Liability value of the current yearly tranche.
A liability is a contractual or optional liability leading to actual costs due to business transactions like goods input or invoice receipt.
In finance, the term liability is used for the payment obligations of a company.
Liability does not only include the liabilities already gathered in terms of bookkeeping (e.g. through received but not yet payed bills), but also all future payment obligations (e.g. due to contractual agreements). Source:
Wikipedia
DI060754 Cost budget relevant
DI060647 % cost deviation (without subprojects)
Percentage deviation of the costs:
Total costs (without subprojects) from
Cost budget (without subprojects) in the selected yearly tranche
DI060588 Remaining effort (without subprojects)
Remaining effort of the project without considering its subprojects for the selected year
DI060514 Effort budget
For projects: Effort budget of the project and all of its subprojects (sum of the
Effort budget (without subprojects) values of the project and all of its subprojects) for the selected year
For programs: Effort budget of all projects assigned to the program (sum of the
Cost budget values of the assigned projects) for the selected year
DI060506 Effort budget approved (without subprojects)
Approved effort budget of the project without considering its subprojects for the selected year
DI060500 Remaining costs
For projects: Remaining costs of the project and all of its subprojects (sum of the
Remaining costs (without subprojects) values of the project and all of its subprojects) for the selected year
For programs: Remaining costs of all projects assigned to the program (sum of the
Remaining costs values of the assigned projects) for the selected year
DI060774 Cost budget approved
For projects: Approved cost budget of the project and all of its subprojects (sum of the
Cost budget approved (without subprojects) values of the projects and all of its subprojects) for the selected year
For programs: Approved cost budget of all projects assigned to the program (sum of the
Cost budget requested values of the projects) for the selected year
DI060755 Effort budget relevant
DI060772 Effort budget approved
For projects: Approved effort budget of the project and all of its subprojects (sum of the
Effort budget approved (without subprojects) values of the projects and all of its subprojects) for the selected year
For programs: Approved effort budget of all projects of the program (sum of the
Effort budget approved values of all projects assigned to the program) for the selected year
DI060641 % cost deviation
Percentage deviation of the costs:
Total costs from
Cost budget
DI060496 Total costs baseline (without subprojects)
Total costs from the baseline of the project without considering its subprojects for the selected year
DI060507 Total effort baseline
For projects: Baseline total costs of the project and all of its subprojects (sum of the
Effort total baseline (without subprojects) values of the project and all of its subprojects) for the selected year
For programs: Baseline total costs of all projects assigned to the program (sum of the
Effort budget baseline values of the projects) for the selected year
DI060761 Text: Sum effort per year
Virtual data item which is used for displaying the heading of the
Effort subarea
DI060638 Text: Sum costs per year
Virtual data item which is used for displaying the heading of the
Costs subarea
DI063100 % cost deviation sum program
Percentage deviation of the costs:
Total costs from
Cost budget as a sum value of the selected yearly tranche
DI063104 % effort deviation sum program
Percentage deviation of the effort:
Total effort from
Effort budget as a sum value of the selected yearly tranche
DI060496 Total costs baseline (without subprojects)
Total costs from the baseline of the project without considering its subprojects for the selected year
DI060515 Project ID
DI060470 Project ID
DI060631 Project
DI060632 Main project ID
DI060633 Main project
DI060484 Cost type group
DI060473 Cost type group ID
DI060485 Cost type group name
Name of the cost type group
DI060490 Cost type group class name
DI060488 Cost type group class code
DI060630 Cost type group active?
DI060472 Year
DI060516 Year
DI060585 Planned effort (without subprojects)
DI060568 Planned costs (without subprojects)
DI060511 Planned effort
DI060497 Planned costs
DI060487 Sorting number