Project (Idea, Proposals) panel Schedule Select the Assign resources context menu command on the task Resource List
Project (Idea, Proposals) panel Schedule Select the Assign revenue and cost resources context menu command on a task Resource List
From DB 39.5.0
Project (Idea, Proposals) panel Schedule Select the Assign resources context menu command on a task Resource List
Information
This module is an auxiliary module and therefore it has no stand-alone function. It is used to assign several resources to a task in the Schedule module at once.
Procedure
From DB 39.5.1
When opening the module via the Assign resources context menu command, person, department, and skill resources are loaded automatically.
Mark the required resources in the list by
clicking or
CTRL + clicking (can be used to mark a parent resource (e.g. a department resource) and its child resources at once).
Subsequently click on the Copy marked button.
To have the revenue and cost resources displayed, click on the button of the same name and proceed as described above.
When opening the module via the Assign revenue and cost resources context menu command, person, department, and skill resources are loaded automatically.
The procedure here equates to that of the department, employee, and skill resources.
To have the department, employee, and skill resources displayed, click on the Person resources button.
Up to DB 39.5.1
To select the required resources, mark them with CTRL + click.