Change Person ID MOD000365 New from DB 39.5.12
From DB Version 39.5.12, the 000365
Resource ID Change module has been renamed
Change Person ID. If you use a DB version < 39.5.12, please go to
ResourceIDChangeMOD000365.
Access path
- PM Administration Special Functions Change Person ID
Information
- In this module, person IDs can be changed system wide.
Procedure
- Select the required person ID from the listbox on the Person ID field.
- Enter the new person ID in the New ID field.
- Now, you have the option to
- either carry out the ID change immediately
- To do so, click on the Assign Stakeholder button.
- or have a preview displayed first and then carry out the change.
- To do so, click on the Preview button.
- All data tables of the PLANTA project database are displayed, and the number of records to be changed in the respective table is displayed opposite of each table.
- After you have checked the preview in the preview field, click on the Start ID change button.
- Subsequently, the list of data tables is displayed again with a specification of the number of changed records per table.
Details
- The ID (code) of the person is changed in both the master data and all person assignments of the entire PLANTA project database.
- The auto commit to the database is automatically switched on and off during the change process.
Adjustment
- In order to include further data tables/data items in the person ID change, you have to make the following adjustments:
- Open the current module 000365 Change Person ID in the customizer.
- Open data area 000468.
- Open data field configuration of data field 101039.
- Extend the existing data field configuration by the required data tables/data items
- They must be created as a new line according to the <DT-ID> <DI-IDs> schema (see existing entries)
- Here you have to make sure not to insert unnecessary line breaks and to stay within the triple quotation marks.