The documentation from version 39.5.17 of PLANTA project can be found in the new PLANTA Online Help.

Check Reported Hours MOD009D2G New from DB 39.5.14

Access path

Information

  • In the Check Reported Hours module, the hours worked reported in the selected project can be checked.

Details

  • The time period is preset by default so that all reported hours of the current year are displayed. To restrict the time period, the entries in the from and to fields must be changed accordingly.
  • If there are canceled postings with their corresponding reverse postings in the required period, they are displayed as well.

Display hours

  • Set the required filter criteria.
  • Click on the Use changes button (next to the period fields).

See also: Check Reported Hours of all projects of the project manager