Check Reported Hours MOD009ALI

From DB 39.5.9

Access path

Up to DB 39.5.9

Access path

Information

  • In the Check Reported Hours module, the reported working hours of all projects in which the logged-on user is a manager can be checked.

Details

From DB 39.5.13

  • The time period is preset by default so that all reported hours of the current year are displayed. To restrict the time period, the entries in the from and to fields must be changed accordingly.
  • NEW If there are canceled postings with their corresponding reverse postings in the required period, they are displayed as well. Details on Reverse Postings

Up to DB 39.5.13

  • The time period is preset by default so that all reported hours of the current year are displayed. To restrict the time period, change values in the from and to fields as required.
  • Display hours

    • Set the required filter criteria.
      • The Project field is a mandatory field.
    • Click on the Use changes button (next to the period fields).


    See also: Check Reported Hours of the individual projects