DT430 Basic Calendar Periods

DI022725 Dominance symbol 1st month

DI000796 Company day

This parameter is hidden in the Standard but can be displayed and filled in if a factory calendar based on it is used.

DI000797 Company week

This parameter is hidden in the Standard but can be displayed and filled in if a factory calendar based on it is used.

Details

  • If start and end dates are entered in company week date formats, they are converted to day dates as follows.
    • Start date:
      • First working day of the company week. In case none is available, the next working day of the following week is taken, etc. The conversion is only possible if the data item possesses the summarization type "3".
    • End date.
      • Last working day of the week. In case none is available, the next working day of the previous week is taken. The conversion is only possible if the data item possesses the summarization type "2".
    • A value range check (e.g. SD < = ED) operates dominantly.

DI000987 Calendar

Code (ID) of the calendar

Note

  • The corresponding data field is hidden by default but can be displayed by the user if necessary.

DI000997 Period

Date according to the gregorian calendar

DI000999 Work

Here you can define if it is a working period. When copying to the resource calendars, this value is adopted.

Values

  • Checked - Period is defined as working day
  • Unchecked - Period is defined as holiday

The parameter can be edited by users with modification rights in the following module:

DI001470 Company year

This parameter is hidden in the Standard but can be displayed and filled in if a factory calendar based on it is used.

DI001672 Day

The corresponding weekday (e.g., 1=Monday, 2=Tuesday)

DI002368 Calendar week

The respective calendar week

DI002369 Month

DI022726 1. Month vs day

DI022757 Weekday

The respective weekday

DI022759 CW next to monday

DI022814 Last day month+1J

DI040928 Month (period)

DI040929 Calendar week (period)

Calendar week name including week number and year specification