DT826 TAR/Report
DI008497 Project ID
Technical ID of the project. It is generated automatically upon creation of the project and cannot be changed afterwards, unlike the functional ID. It is usually invisible in the modules.
DI008498 Task ID
Technical ID of the task. It is generated automatically upon creation of the task and cannot be changed afterwards unlike the functional ID. This ID is not visible in modules, but can be displayed if necessary.
DI008502 Resource
Code (ID) of the task resource
DI008514 Report
ID of the status report
DI008652 Planned costs
Planned costs of the task resource at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT466
Resource assignment).
DI008653 Actual costs
Actual costs of the task resource at the time of creation/update of the selected status report Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT466
Resource assignment).
DI008654 Rem. costs
Remaining costs of the task resource at the time of creation/update of the selected status report Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT466
Resource assignment).
DI008655 Total costs
Total (actual+remaining) costs of the task resource at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT466
Resource assignment).
DI029141 Task name
Name of the task
DI029157 Project name
Name of the project
DI034508 Main project
ID of the main project
DI034515 Resource name
Name of the resource
DI057791 Project
Functional ID of the project. It is generated automatically (copied from the
technical project ID). Unlike the technical
Project ID, the functional ID can be changed manually.
DI058232 WBS code
Project structure plan code
DI058234 Parent task name
Name of the parent task
DI058235 Task
ID of the task
DI008499 Resource
ID of the resource
DI008657 Requested start
Requested start date of the task resource at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT466
Resource assignment).
Note
- This field is hidden by default but can be displayed by the user if necessary.
DI008658 Req. end
Requested end date of the task resource at the time of creation/update of the selected status report Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT466
Resource assignment).
Note
- This field is hidden by default but can be displayed by the user if necessary.
DI008645 Actual start
Actual start date of the task resource at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT466
Resource assignment).
Note
- This field is hidden by default but can be displayed by the user if necessary.
DI008647 Actual end
Actual end date of the task resource at the time of creation/update of the selected status report Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT466
Resource assignment).
Note
- This field is hidden by default but can be displayed by the user if necessary.
DI008649 Calc. start
Calculated start date of the task resource at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT466
Resource assignment).
Note
- This field is hidden by default but can be displayed by the user if necessary.
DI008650 Calc. end
Calculated end date of the task resource at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT466
Resource assignment).
Note
- This field is hidden by default but can be displayed by the user if necessary.
DI059641 Calc. start (baseline)
Calculated start date of the task resource in the baseline report
Note
- This field is hidden by default but can be displayed by the user if necessary.
DI059642 Calc. end (baseline)
Calculated end date of the task resource in the baseline report
Note
- This field is hidden by default but can be displayed by the user if necessary.
DI034545 Resource type
Type of task resource in the status report
Note
- This field is hidden by default but can be displayed by the user if necessary.
DIs no longer used from DB 39.5.0
The DIs listed below are no longer used from DB version 39.5.0.
DI028765 Total costs: int. personnel
Total costs of the
Internal personnel cost type group
DI028769 Total costs: ext. personnel
Total costs of the
External personnel cost type group
DI028773 Total costs: material costs
Total costs of the
Material costs cost type group
DI028777 Total costs: investments
Total costs of the
Investments cost type group
DI028781 Total costs: miscellaneous
Total costs of the
Miscellaneous cost type group