External Tasks

Information

  • In PLANTA project, external tasks are one of the three options for illustrating dependencies between projects.
  • This function allows you to display tasks of another project in the schedule of a project/program.
  • Milestones that are decisive for your own project can therefore be displayed and ensure clarity within the project.

From DB 39.5.15

Details
  • In the schedule in window 1, external tasks are marked with the symbol before the respective record.
  • The date bar of the external task is also displayed below the scale.

From DB 39.5.12

Details
  • In window 1 of the schedule, external tasks are marked with the VorgangExtern.png symbol in front of the respective record.
  • The date bar of the external task is displayed below the scale.

Up to DB 39.5.12

Details
  • In window 1 of the schedule, external tasks are marked with the PfeilGruen.png symbol in front of the respective record.
  • The date bar of the external task is displayed below the scale.

Notes

The procedure for displaying an external task is identical in project and program schedules.

  • Right-click on the required task.
  • Select Insert External task from the context menu.
  • Select the required project/program and the required task from the respective listbox.
    • The selected external task is displayed in the schedule of your own project/program.

Bar legends: external tasks

From DB 39.5.12

Symbol Meaning Color Comment
KalkExtDB12.PNG Calculated dates of the external tasks KalkExtDB12.PNG Uncritical
KalkExtredDB12.png Critical
Calc. start and Calc end of the external tasks are calculated by clicking on the calculation button or by selecting the respective menu item.
Uncritical means: Total float > 0
Critical means: Total float 0
Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can be critical as well.
SammelExtVGDB14.png Calculated dates of the external summary tasks    
MSextDB12.png / MMSExtDB12.PNG Milestones/master milestones of the external summary tasks MSextDB12.png / MMSExtDB12.PNG Without delay
MSextRedDB12.png / MMSextRedDB12.png With delay
Without delay means: Total float 0
With delay means: Total float < 0

Up to DB 39.5.12

Symbol Meaning Color Comment
ExtTAUncrit.PNG Calculated dates of the external tasks ExtTA.PNG Critical
ExtTAUncrit.PNG Uncritical
Calc. start and Calc. end of the external tasks are calculated by clicking on the calculation button or by selecting the respective menu item.
Uncritical means: Total float > 0
Critical means: Total float 0
Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical.
ExtSum.PNG Calculated dates of the external summary tasks    
MSExternal.PNG Milstones/master milestones of the external tasks    


See also: Schedule, Links
Topic attachments
I Attachment History Size Date Comment
Pngpng PfeilGruen.png r1 0.6 K 2019-09-11 - 10:32  
Pngpng VorgangExtern.png r1 0.4 K 2019-09-11 - 10:32  

         PLANTA project









 
  • Suche in Topic-Namen

  • Suche in Topic-Inhalten
This site is powered by the TWiki collaboration platform Powered by Perl