DT593 Import Parameter Up to S 39.5.4

From server version 39.5.4, PLANTA provides the Universal Interface (PLANTA link) replacing the previous ERP interface. To learn more, please refer to the Universal Interface topic.

DI061503 Import ID

ID of the import parameter configuration

DI061532 Description

Name of the import parameter configuration

DI061528 Import path

Server path for import

DI061529 Import file name

Name of the file to be imported

DI061522 Reversal type

There are two types of reversals:

Details

  • Negative amount: The costs that are imported are negative.
  • Marking: The costs that are imported are marked with a code. E.g. R for reversal.

DI061578 Reversal type name

Name of the reversal type

DI061520 Import Type

Type of import

DI061577 Import type name

Name of the import type

DI061521 Automatically approve valid records

Code for the approval of valid records

Details

  • If data is imported from an external system, it must pass a check against existing cost centers, cost types, projects, tasks and resources.
    • If it already exists, the data is marked as valid and can be transferred directly to DT472.

DI061534 Book all incorrect records to

With this parameter you can define whether the records to be imported are booked to alternative objects (Project, Task, Resource, Cost Center, Cost Type), if the objects of the records to be imported do not exist in PLANTA

DI061536 Approval by PL required from

As of a certain amount, the project manager has to grant approval before the data is transferred to the DT472

DI061515 Project ID

Listbox field for selecting the project to which you want to book alternatively, if the importing project is not available in PLANTA

DI061519 Task ID

Listbox field for selecting the task to which you want to book alternatively, if the importing task is not available in PLANTA

DI061516 Resource from DT467

Listbox field for selecting the resource to which you want to book alternatively, if the importing resource is not available in PLANTA

DI061518 Cost center

Listbox field for selecting the cost center to which you want to book alternatively, if the importing cost center is not available in PLANTA project

DI061517 Cost type

Listbox field for selecting the cost type to which you want to book alternatively, if the importing cost type is not available in PLANTA project

DI061504 Header

For description, see Header

New from DB 39.5.0

DI062304 File header

This parameter determines whether the header of the import file is read or not.