Milestone Overview MOD009C8X New from DB 39.5.0

From DB 39.5.9

Access path

Up to DB 39.5.9

Access path

From DB 39.5.7

Information
  • The module provides an overview of all master milestones NEW and milestones of the selected program NEW and its projects.
  • You also have the option to define one of the program master milestones displayed here as a main milestone.
    • Main milestones are used as reference points for the interval calculation of the master milestones to the other master milestones.

Details

  • NEW The summary tasks (phases), milestones, and master milestones are displayed in the Gantt view, the master milestones are additionally displayed as gates on a horizontal axis.
  • On each master milestone symbol, the WBS code of the master milestone and the time interval to the main milestone date are specified (in weeks).
  • The calculated duration (Calc. start up to Calc. end) is visualized by
    • a dotted frame for the program
    • the bar in the color of the project code for projects.

Up to DB 39.5.7

Information
  • This module provides an overview of all master milestones (gates) of the program and the projects assigned to the program, which can be displayed on a horizontal axis directly below the scale.
  • You also have the option to define one of the program master milestones that are displayed here as a main milestone. Main milestones are used as reference points for the interval calculation of the master milestones to the main milestone.

Details

  • On each master milestone symbol, the WBS code of the master milestone and the time interval to the main milestone are specified.
  • The dotted frame informs about the program duration (Calc. start up to Calc. end).

Legend

From DB 39.5.14

Programs

Symbol Meaning Color Comment
DauerProjekt.PNG Calculated dates of the programs   Calc. start and Calc. end of a program are calculated by clicking on the calculation button or by selecting the respective menu item.
MMSbigDB14.png Gates MMSbigDB14.png Gate without date delay
MMSredbigDB14.png Gate with date delay
HMSDB14.png Main gate/main milestone
Gates are master milestones of planning objects.
Without date delay means: Total float 0
With date delay means: Total float < 0

Gates are only displayed in the schedule module if the Schedule with gates checkbox has been activated in the Project Core Data in the core data module of the respective planning object.

Project

KalkPRDB14.png Calculated dates The color of the bar is determined by the code of the planning object.
CodeADB14.png Code A
CodeBDB14.png Code B
CodeCDB14.png Code C
CodeDDB14.png Code D
CodeEDB14.png Code E
Calc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item.
In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.
MMSDB14.png Master milestones MMSDB14.png without date delay
MMSredDB14.png with date delay
Tasks are defined as master milestones in the Schedule module.
VGueberkrit.PNG Master milestone date delay   A master milestone date delay occurs if its Calc. end is later than its Latest end.

Task

SammelVGDB12.PNG Calculated dates of the summary tasks   A summary task is a task in the structured schedule which consists of subtasks and summarizes them. Information on the summary task, such as duration and dates, is determined automatically from the sub-tasks.
MMSDB14.png Master milestones MMSDB14.png without date delay
MMSredDB14.png with date delay
Tasks are defined as master milestones in the Schedule module.

From DB 39.5.12

Symbol Meaning Color Comment
Programs
Symbol Meaning Color Comment
DauerProjekt.PNG Calculated dates of the programs   Calc. start and Calc. end of a program are calculated by clicking on the calculation button or by selecting the respective menu item.
MMSbig.png Gates MMSbig.png Gate without date delay
MMSredbig.png Gate with date delay
HMS.png Main gate/main milestone
Gates are master milestones of planning objects.
Without date delay means: Total float 0
With date delay means: Total float < 0

Gates are only displayed in the schedule module if the Schedule with gates checkbox has been activated in the Project Core Data in the core data module of the respective planning object.

Project

KalkPRDB12.PNG Calculated dates The color of the bar is determined by the code of the planning object.
CodeADB12.PNG Code A
CodeBDB12.PNG Code B
CodeCDB12.PNG Code C
CodeDDB12.PNG Code D
CodeEDB12.PNG Code E
Calc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item.
In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.
MMSDB12.png Master milestones MMSDB12.png without date delay
MMSredDB12.png with date delay
Tasks are defined as master milestones in the Schedule module.
VGueberkrit.PNG Master milestone date delay   A master milestone date delay occurs if its Calc. end is later than its Latest end.

Task

SammelVGDB12.PNG Calculated dates of the summary tasks   A summary task is a task in the structured schedule which consists of subtasks and summarizes them. Information on the summary task, such as duration and dates, is determined automatically from the sub-tasks.
MMSDB12.png Master milestones MMSDB12.png without date delay
MMSredDB12.png with date delay
Tasks are defined as master milestones in the Schedule module.

Up to DB 39.5.12

Programs
Symbol Meaning Color Comment
DauerProjekt.PNG Calculated dates of the programs   Calc. start and Calc. end of a program are calculated by clicking on the calculation button or by selecting the respective menu item.
MMSbig.png Gates MMSbig.png Gate without date delay
MMSredbig.png Gate with date delay
HMS.png Main gate/main milestone
Gates are master milestones of planning objects.
Without date delay means: Total float 0
With date delay means: Total float < 0

Gates are only displayed in the schedule module if the Schedule with gates checkbox has been activated in the Project Core Data in the core data module of the respective planning object.

Project

Kalk.png Calculated dates The bar color is defined by the code of the planning object.
A.png Code A
B.png Code B
C.png Code C
D.png Code D
E.png Code E
Calc. start and Calc. end of a planning object are determined in the calculation of the schedule of the respective planning object.
In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.
MS.PNG Master milestones MMS_krit.PNG with date delay
MS.PNG without date delay
Tasks are defined as master milestones in the Schedule module.
VGueberkrit.PNG Master milestone date delay   A master milestone date delay occurs if its Calc. end is later than its Latest end.

Task

Sammel.PNG Calculated dates of the summary tasks   A summary task is a task in the structured schedule that consists of subtasks and summarizes them. Information on the summary task, such as duration and dates, is determined automatically from the sub-tasks.
MS.PNG Master milestones MMS_krit.PNG with date delay
MS.PNG without date delay
Tasks are defined as master milestones in the Schedule module.