LegendFrom DB 39.5.14
Symbol Meaning Color Comment Requested dates Requested start and Requested end are defined in the Key dates area in the corresponding core data module (Project Core Data, Idea Core Data, Proposal Core Data, Program Core Data).
Calculated dates The color of the bar is determined by the code of the planning object.
Code A
Code B
Code C
Code D
Code ECalc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item.
In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.Actual dates The bar is shaded in white. The background color depends on the Project Code. Actual start and, if available Actual end, otherwise Latest time recording date of a project are calculated by clicking on the calculation button or by selecting the respective menu item. Float Float is available if the calculated end date (Calc. end) is earlier than the requested end date (Requested end).
Date delay A date delay occurs if the calculated end date (Calc. end) is later than the requested end date (Requested end).
The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades.
Master milestones Without date delay
With date delayTasks are defined as master milestones in the Schedule module. From DB 39.5.12
Symbol Meaning Color Comment Requested dates Requested start and Requested end are defined in the Key dates area in the corresponding core data module (Project Core Data, Idea Core Data, Proposal Core Data, Program Core Data).
Calculated dates The color of the bar is determined by the code of the planning object.
Code A
Code B
Code C
Code D
Code ECalc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item.
In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.Float Float is available if the calculated end date (Calc. end) is earlier than the requested end date (Requested end).
Date delay A date delay occurs if the calculated end date (Calc. end) is later than the requested end date (Requested end).
The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades.
Master milestones Without date delay
With date delayTasks are defined as master milestones in the Schedule module. Up to DB 39.5.12
Symbol Meaning Color Comment Requested dates Requested start and Requested end are defined in the Key dates area in the corresponding core data module (Project Core Data, Idea Core Data, Proposal Core Data, Program Core Data).
Calculated dates The color of the bar is determined by the code of the planning object.
Code A
Code B
Code C
Code D
Code ECalc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item.
In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.Actual dates Actual start and, if available, Actual end, in any other case the Latest time recording date of a project are calculated by clicking on the calculation button or by selecting the respective menu item. Float Float is available if the calculated end date (Calc. end) is earlier than the requested end date (Requested end).
Date delay A date delay occurs if the calculated end date (Calc. end) is later than the requested end date (Requested end).
The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades.
Master milestones With date delay
Without date delayTasks are defined as master milestones in the Schedule module.