The documentation from version 39.5.17 of PLANTA project can be found in the new PLANTA Online Help.

My Watchlist MOD009AG3

From DB 39.5.13

Access path

From DB 39.5.9

Access path

Up to DB 39.5.9

Access path

Information

  • In this module, the employee can display planning objects he or she wants to monitor. He or she does not necessarily have to be planned as a resource in these planning objects.
    • In order to be allowed to use the watchlist function, the logged-on user must be defined in the system as a Stakeholder.

Assign planning objects to the watchlist/remove planning objects from the watchlist

From DB 39.5.12

  • To include the planning objects in the watchlist, click on the Assign planning objects button (at the right upper margin of the left module window).
  • NEW To remove the required planning objects from the watchlist, mark them and click on the Deletion button in the toolbar.

Up to DB 39.5.12

  • This module is a pure overview module in which planning objects which have already been included in the watchlist are displayed.
  • The watchlist can be edited (addition, deletion of planning objects, etc.) in the Edit Watchlist module which can be opened via the button of the same name.
  • Details

    • The projects to be displayed in this module can be filtered using object filters.
      • If there already is an object filter, it can be selected from the listbox on the Filter field. After you have clicked on the Use changes button, only projects which correspond to the filter will be displayed.
      • You can edit existing object filters or create new ones in the Object Filter module which is opened via the Edit filter button.
      • If a grouping criterion is selected in one of the modules which use object filters, it automatically takes effect in all other modules with object filters.
    • By By clicking on the ID of the required project, you can switch to the corresponding Project panel in which you can edit or view the program data depending on your user rights.

    Legend

    From DB 39.5.15

    Symbol Meaning Color Comment
    WunschDB14.png Requested dates   Requested start and Requested end are defined in the Key dates area in the corresponding core data module (Project Core Data, Idea Core Data, Proposal Core Data, Program Core Data).
    KalkPRDB14.png Calculated dates The color of the bar is determined by the code of the planning object.
    CodeADB14.png Code A
    CodeBDB14.png Code B
    CodeCDB14.png Code C
    CodeDDB14.png Code D
    CodeEDB14.png Code E
    Calc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item.
    In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.
    ActDB14.png Actual dates The bar is white hatched. The background color depends on the Code of the planning object. Actual start and Actual end (if there is any, otherwise Latest time recording date) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) when calculating the schedule of the respective planning object.
    Puffer.png Float   Float is available if the calculated end date (Calc. end) is earlier than the requested end date (Requested end).
    Verzug.png Date delay   A date delay occurs if the calculated end date (Calc. end) is later than the requested end date (Requested end).
    The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades.
    MMSDB14.png Master milestones MMSDB14.png Without date delay
    MMSredDB14.png With date delay
    Tasks are defined as master milestones in the Schedule module.
    AOBAus.png external links AOBAus.png outgoing
    AOBEin.png incoming
     

    From DB 39.5.14

    Symbol Meaning Color Comment
    WunschDB14.png Requested dates   Requested start and Requested end are defined in the Key dates area in the corresponding core data module (Project Core Data, Idea Core Data, Proposal Core Data, Program Core Data).
    KalkPRDB14.png Calculated dates The color of the bar is determined by the code of the planning object.
    CodeADB14.png Code A
    CodeBDB14.png Code B
    CodeCDB14.png Code C
    CodeDDB14.png Code D
    CodeEDB14.png Code E
    Calc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item.
    In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.
    ActDB14.png Actual dates The bar is white hatched. The background color depends on the Code of the planning object. Actual start and Actual end (if there is any, otherwise Latest time recording date) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) in the calculation of the schedule of the respective planning object.
    Puffer.png Float   Float is available if the calculated end date (Calc. end) is earlier than the requested end date (Requested end).
    Verzug.png Date delay   A date delay occurs if the calculated end date (Calc. end) is later than the requested end date (Requested end).
    The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades.
    MMSDB14.png Master milestones MMSDB14.png Without date delay
    MMSredDB14.png With date delay
    Tasks are defined as master milestones in the Schedule module.

    From DB 39.5.12

    Symbol Meaning Color Comment
    Wunsch.png Requested dates   Requested start and Requested end are defined in the Key dates area in the corresponding core data module (Project Core Data, Idea Core Data, Proposal Core Data, Program Core Data).
    KalkPRDB12.PNG Calculated dates The color of the bar is determined by the code of the planning object.
    CodeADB12.PNG Code A
    CodeBDB12.PNG Code B
    CodeCDB12.PNG Code C
    CodeDDB12.PNG Code D
    CodeEDB12.PNG Code E
    Calc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item.
    In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.
    ActDB12.png Actual dates   Actual start and Actual end (if there is any, otherwise Latest time recording date) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) when calculating the schedule of the respective planning object.
    Puffer.png Float   Float is available if the calculated end date (Calc. end) is earlier than the requested end date (Requested end).
    Verzug.png Date delay   A date delay occurs if the calculated end date (Calc. end) is later than the requested end date (Requested end).
    The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades.
    MMSDB12.png Master milestones MMSDB12.png Without date delay
    MMSredDB12.png With date delay
    Tasks are defined as master milestones in the Schedule module.

    Up to DB 39.5.12

    Symbol Meaning Color Comment
    Wunsch.png Requested dates   Requested start and Requested end are defined in the Key dates area in the corresponding core data module (Project Core Data, Idea Core Data, Proposal Core Data, Program Core Data).
    Kalk.png Calculated dates The color of the bar is determined by the code of the planning object.
    A.png Code A
    B.png Code B
    C.png Code C
    D.png Code D
    E.png Code E
    Calc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item.
    In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.
    Act.png Actual dates   Actual start and Actual end (if there is any, otherwise Latest time recording date) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) when calculating the schedule of the respective planning object.
    Puffer.png Float   Float is available if the calculated end date (Calc. end) is earlier than the requested end date (Requested end).
    Verzug.png Date delay   A date delay occurs if the calculated end date (Calc. end) is later than the requested end date (Requested end).
    The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades.
    MS.PNG Master milestones MMS_krit.PNG With date delay
    MS.PNG Without date delay
    Tasks are defined as master milestones in the Schedule module.

             PLANTA project









     