an overview of an SAP project structure imported from SAP or created manually, or an alternative structure as well as
an option to change this structure by creating new elements or deleting or moving existing ones
an option to link the SAP project structure to the PLANTA project structure by assigning PLANTA tasks to the SAP WBS elements in order to
enable comparison of the cost/effort values imported from SAP or created manually and those from PLANTA project, which is done on the basis of the link of both structures.
In addition, a column with deviation value is displayed for each column pair.
NEW Since both import of the SAP values to PLANTA project and export of PLANTA project values to SAP are done via account assignment elements, PLANTA project values are summarized via the account assignment to the SAP WBS elements. ID of the account assignment elements equates to the ID of the cost type or cost center from which the costs or effort stem. If no account assignment elements exist on costs/effort, it is not summarized to the SAP WBS elements accordingly.
The sum line only sums up the values of all SAP WBS elements on top level. As a result of structure summarization, the values of the elements which lie below in the structure are taken into account in the sum.
From DB 39.5.10
The linkage of the structures is done by assigning elements of a structure to those of others
In addition, a column with deviation value is displayed for each column pair.
NEW The sum line only sums up the values of all SAP WBS elements on top level. As a result of structure summarization, the values of the elements which lie below in the structure are taken into account in the sum.
Up to DB 39.5.10
The linkage of the structures is done by assigning elements of a structure to those of others
In addition, a column with deviation value is displayed for each column pair.
Notes
PLANTA project values
All PLANTA project costs/effort values displayed in the SAP WBS module are based on the status of the last scheduling run.
Costs and effort on task level are displayed summarized from the resource costs or resource effort directly assigned to the task.
After changes were made and saved in the Budget module, budgets are immediately updated and displayed in the header area of the SAP WBS module.
SAP values
The SAP budget values changed in the Create SAP WBS Elements module are only updated in the SAP WBS module after you have clicked on the Recalculate button.
SAP costs/effort values which have been imported or changed in the Create SAP WBS Elements module are immediately updated on the SAP WBS elements.
Right-click on the required SAP WBS element and select InsertSAP WBS Elements from the context menu.
A new (empty) SAP WBS record is inserted.
Enter the required data.
Save.
New from DB 39.5.11
Create and Assign Account Assignment Elements Manually
Procedure
Right-click on the SAP WBS element to which an account assignment element is to be subordinated and select InsertAccount assignment element from the context menu.
Enter the ID or the cost type or cost center from which costs/effort are to be summarized in the Account assignment element field.
Save.
New from DB 39.5.11
Delete SAP WBS Elements/Account Assignment Elements
Procedure
Mark the lines to be deleted.
Click on the Delete button in the toolbar to delete the required line.
Notes
SAP WBS elements can only be deleted if
it is located on the lowest structure level, i.e. if no other SAP WBS element is assigned to it.
no effort or cost data from SAP is available on this SAP WBS element.
no PLANTA project tasks are assigned to this SAP WBS element.
Assign Tasks to SAP WBS Elements
Procedure
From DB 39.5.12
The assignment of tasks to SAP WBS elements in the SAP WBS module can be done in two ways: