Budget MOD009BOW From DB 39.5.0

Description for versions < DB 39.5.0


From DB 39.5.13

Access path

Up to DB 39.5.13

Access path

Information

  • In the Budget module, the budget of a project can be planned and edited.
  • The calculated effort and costs are visualized here and can be used to plan the budget.
  • Costs, budget, and budget planning are visualized in cost type groups.

Notes

  • The calculation of the effort and cost values is based on the load values of the resources assigned to the project or subproject (load level of the project).
    • The individual effort and cost values calculated on load level are summarized to the respective cost type groups per year. They are then summed-up across all years and finally they are summed-up as a total value across all cost type groups of the project.
      • For the summarization of effort and costs to cost type groups as well as for their visualization in the Budget module, the cost type of the cost type of the load records is applicable.
    • Additionally, cost values are summarized along the project structure, from the lowest subproject via further subprojects to main project level.
      • The (without SP) addition in the column headings (e.g. Budget (without SP), Total (without SP) implies that the values in the respective columns are the values of an individual project without consideration of its possibly existing subprojects. The values summarized via the project structure are visualized in the columns the headings of which contain no addition (e.g. Budget, Total, etc.).
        • From DB version 39.5.0 to 39.5.7, the current and total additions were used in the column headings.

Module Variants

From DB 39.5.15

Base Only the values of the selected project are displayed. The values of possibly existing subprojects ((without SP) values) are not considered.
With structure summarization The values summarized via the project structure (if the project structure exists) are displayed.
Overall view (with and without structure summarization) Values of individual projects and summarized values of the project structure

Up to DB 39.5.15

Base Only the values of the selected project are displayed. The values of possibly existing subprojects ((without SP) values) are not considered.
With structure summarization The values summarized via the project structure (if the project structure exists) are displayed.
Overall view (with and without structure summarization) Values of individual projects and summarized values of the project structure
Allocate approved budget (for "top down" model) Top down model cannot be used at the moment.

Header Area

From DB 39.5.14

Information
  • Apart from the project specifications, the following is illustrated in the header of the module:
    • Recalculate button. This button serves to update the calculation of all data used in the Budget module, e.g. if the data of the subprojects has changed, new subprojects have been created, or existing values have changed.
    • Line with the listbox and the button for inserting new yearly tranches as well as baseline specifications on the right hand side.
      • Empty yearly tranches are deleted automatically upon recalculation. If you do not want to carry out a recalculation, you can also delete the yearly tranches manually via the Delete yearly tranche context menu command.
    • Line with the arrows of the transfer function for adopting values from different sources. For this purpose, see the Transfer function.

From DB 39.5.13

Information
  • Apart from the project specifications, the following is illustrated in the header of the module:
    • Links to the Cost Reports and Effort Reports modules in which different evaluations of costs and cost budget or effort and effort budget can be found.
    • Recalculate button. This button serves to update the calculation of all data used in the Budget module, if, e.g., the data of the subprojects has changed, new subprojects have been created, or existing values have changed.
    • Line with the listbox and the button for inserting new yearly tranches as well as baseline specifications on the right hand side.
      • Empty yearly tranches are deleted automatically upon recalculation. If you do not want to carry out a recalculation, you can also delete the yearly tranches manually via the Delete yearly tranche context menu command.
    • Line with the arrows of the transfer function for adopting values from different sources. For this purpose, see the Transfer function.

From DB 39.5.10

Information
  • Apart from the project specifications, the following is illustrated in the header of the module:
    • three legend boxes with
      • specifications on the data source for costs and effort (in accordance with the settings of the manual cost input parameter).
      • specifications of input options in project budget fields (according to the settings of the p_project_budget_edit parameter in Global Settings).
      • specifications of input options in the Requested and Approved budget fields (according to the setting of the p_project_budget_approved_edit parameter in Global Settings).
    • Links to the Cost Reports and Effort Reports modules in which different evaluations of costs and cost budget or effort and effort budget can be found.
    • Recalculate button. This button serves to update the calculation of all data used in the Budget module, if, e.g., the data of the subprojects has changed, new subprojects have been created, or existing values have changed.
    • Line with the listbox and the button for inserting new yearly tranches as well as baseline specifications on the right hand side.
      • Empty yearly tranches are deleted automatically upon recalculation. If you do not want to carry out a recalculation, you can also delete the yearly tranches manually via the Delete yearly tranche context menu command.
    • Line with the arrows of the transfer function for adopting values from different sources. For this purpose, see the Transfer function.

Up to DB 39.5.10

Information
  • Apart from the project specifications, the following is illustrated in the header of the module:
    • Three legend boxes with
      • specifications on the data source for costs and effort (in accordance with the settings of the manual cost input parameter).
      • specifications of input options in project budget fields (according to the settings of the p_project_budget_edit parameter in Global Settings).
      • specifications of input options in the Requested and Approved budget fields (according to the setting of the p_project_budget_approved_edit parameter in Global Settings).
    • Links to the Cost Reports and Effort Reports modules in which different evaluations of costs and cost budget or effort and effort budget can be found.
    • Recalculate button. This button serves to update the calculation of all data used in the Budget module, if, e.g., the data of the subprojects has changed, new subprojects have been created, or existing values have changed.
    • Line with the listbox and the button for inserting new yearly tranches as well as baseline specifications on the right hand side.
      • Empty yearly tranches are deleted automatically upon recalculation. If you do not want to carry out a recalculation, you can also delete the yearly tranches manually via the Delete yearly tranche context menu command.
    • Line with the arrows of the transfer function for adopting values from different sources. For this purpose, see the Transfer function.

Costs Block

Data Display

Vertical Display

Costs block consisting of

Summarization
  • The lowest level is formed by cost type group lines of the yearly tranche. From here,
    • the values of all cost type groups of a yearly tranche are summarized in the sum line of this yearly tranche (summed up) on one hand,
    • the values of individual cost type groups of all yearly tranches are summarized (summed up) to project total level on the other hand.
  • The top level forms the sum line on project total level. It displays the summarized values from all cost type group lines of all yearly tranches.
  • If the selected project is also a structured project, all subprojects of the project are displayed with the same yearly tranches and cost type groups as displayed in the Budget module in the main project, and their data is summarized to main project level.

From DB 39.5.14

Details
  • The yearly tranches are
    • either created automatically according to the time scheduling of the resources in the Schedule module
    • NEW or manually by clicking on the plus button on the header bar and selecting one or more years in the Create Yearly Tranche dialog module and clicking on the Assign selected button.
  • If particular yearly tranches are emptied retrospectively due to the replannings in the Schedule module (for the respective year, no plannings and hence no costs and/or budgets exist), they are not deleted automatically in the Budget module. If you do not want to see them any longer, you have to delete them manually. To do so, right-click on the top line of the yearly tranche and select the Delete yearly tranche command from the context menu.

Up to DB 39.5.14

Details
  • The yearly tranches are
    • either created automatically according to the time scheduling of the resources in the Schedule module
    • or manually by selecting a year from the listbox in the header and clicking on the Insert yearly tranche button.
  • If particular yearly tranches are emptied retrospectively due to the replannings in the Schedule module (for the respective year, no plannings and hence no costs and/or budgets exist), they are not deleted automatically in the Budget module. If you do not want to see them any longer, you have to delete them manually. To do so, right-click on the top line of the yearly tranche and select the Delete yearly tranche command from the context menu.

Horizontal Display

In the Costs block, the following columns and column groups are to be distinguished according to their function:

  • Budget column groups (columns Budget (without SP), Budget (SP), Budget, Baseline (without SP) , Baseline)
  • Cost column group (Actual (without SP), Remaining (without SP), Total (without SP) and Actual, Remaining, Total)
  • Obligo column

Summarization
  • The column heading with (without SP) addition is used for the columns in which only the values of the selected project are displayed without considering its subprojects (if available).
  • The column heading without addition is used for the columns in which the value summarized via the project structure (sum value from the respective project and all of its subprojects) is displayed.

Edit the Data

Budget Column Group

Procedure

  • Budget (without SP) / Budget / Budget (SP)
    • The values of these columns represent the actual, final budget of the project.
    • The Budget (without SP) column only contains the values of the selected project without considering its possibly existing subprojects. On which level (project or yearly tranche) input and editing are possible depends on the settings of the p_project_budget_edit parameter in Global Settings.
    • The Budget column contains the values of the selected project and of all of its subprojects. The values are automatically calculated as a sum of Budget (without SP) of the project and of individual subprojects. Manual input is not possible.
    • The Budget (SP) column contains values of all subprojects of the selected project without considering the project itself. The values are automatically calculated as a sum of Budget (without SP) of the subprojects. Manual input is not possible.

  • Requested (without SP) / Requested
    • The values of these columns represent the requested budget of the project.
    • The Requested (without SP) column contains the values of the selected project without considering its subprojects. Input and editing are only possible on project level. After input, the annual values are summarized to the project level immediately.
    • The Requested column contains the values of the selected project and of all of its subprojects. Editing of values not possible. The column is automatically filled with the sum value from Requested (without SP) of the project and Requested (without SP) of all of its subprojects.

  • Approved (without SP) / Approved
    • The values of the Approved (without SP) and Approved columns represent the approved budget or the budget to be approved (in Approved (without SP)), depending on whether the Budget approved checkbox is activated or deactivated in the respective yearly tranche. * Input and editing are only possible on annual level. Only the approved annual values are copied to project level (output fields) and summarized.
Approve budget function
  • Activate the Budget approved checkbox in the yearly tranche sum line: The Approved (without SP) column of this yearly tranche is set to "Output" and can no longer be edited. The values of the yearly tranche are summarized to project total level and are considered in the calculation of the sum value.
  • Activate the Budget approved checkbox in the yearly tranche sum line: The Approved (without SP) column of this yearly tranche is set to "Input" and can be edited. The values of the yearly tranche are not summarized to the project total level and not considered in the calculation of the sum value.
  • The Approved column only contains actually approved values of the selected project and of all of its subprojects. Editing of values not possible. The column is automatically filled with the sum value from Requested (without SP) of the project and Requested (without SP) of all of its subprojects and only from approved years.

Approved (without SP) Approved
Project   Automatically: Sum X + Y [year 1 + 2 ] Project Automatically: (X + Y project) + (X + Y + Z subproject 1) + (X + Y subproject 1.1)
  Year 1 approved Manual X Automatically: X project + X subproject 1 + X subproject 1.1
  Year 2 approved Manual X Automatically: Y project + Y subproject 1 + Y subproject 1.1
  Year 3 not approved Manually Z Automatically: Z subproject 1
subproject 1   Automatically: Sum X +Y +Z [year 1 + 2 + 3] subproject 1 Automatically: (X + Y + Z subproject 1) + (X + Y subproject 1.1)
  Year 1 approved Manual X Automatically: X subproject 1 + X subproject 1.1
  Year 2 approved Manual X Automatically: Y subproject 1 + Y subproject 1.1
  Year 3 approved Manually X Automatically: Z subproject 1
Subproject 1.1   Automatically: Sum X +Y [year 1 + 2] subproject 1.1 Automatically: X + Y
  Year 1 approved Manual X Automatically: X
  Year 2 approved Manual X Automatically: Y
  Year 3 not approved Manually Z Automatically: -

  • The Baseline (without subprojects)/Baseline serves for information purposes and as a source for transfer to other columns. This column cannot be edited. See also Transfer functions.

Costs Column Group

Columns in question
  • Actual (without SP) / Actual
  • Remaining (without SP) / Remaining
  • Total (without SP) / Total
  • Deviation (without SP) / Deviation
  • % deviation (without SP) / % deviation

Procedure

  • Whether the data in the Cost columns can be entered and edited manually (input fields) with the (without SP) addition of the individual projects, or represent calculated values (output fields), depends on the settings of the manual cost input parameter in the Model and Model Parameters module.

Manual cost input parameter Actual (without SP) Remaining (without SP) Total (without SP) Deviation (without SP) % deviation. (without SP)
Checked = Manual cost input Manual input both on project level and in the yearly tranches. The inputs on yearly level overwrite project values. Manual input both on project level and in the yearly tranches. The inputs on yearly level overwrite project values Automatic calculation of the sum of Actual and Remaining Automatic calculation of the Total costs and Budget balance Automatic calculation of the Total costs and Project budget percentage balance
Unchecked = Automatic summarization Automatic summarization from load table (DT472) to the cost type groups of the corresponding project yearly tranches and from there to the cost type group of the project.
Actual values result from work reportings.
Summarization from DT472 or automatic calculation of the difference between Planned and Actual.
Planned values are not displayed in the Standard but are calculated and can be included and displayed in the module.
Automatic calculation of the sum of Actual and Remaining Automatic calculation of the Total costs and Project budget balance Automatic calculation of the Total costs and Project budget percentage balance

  • The data in the Actual, Remaining, Total cost columns (i.e. columns without without SP addition) are independent of the setting of the Manual cost input parameter and are always output values which result from the summarization of the values of the project and of all of its subprojects.

Liability Column

Procedure
  • Liability values are independent of the manual cost input parameter and can either be entered and edited on yearly tranche or project level.
  • The values are summarized from the yearly tranches to project level.
    • As soon as values exist on yearly tranche level, the sum values of the yearly tranches overwrite the values on project level in case they have been entered manually before.
  • The values only apply to the current project. The existing child subprojects are not considered (no summarization via project structure).

Transfer Functions

Information
  • There is an option to automatically copy the values of particular columns to the other columns.
    • For this purpose, click on the required arrow above the required column.
  • If you move the cursor to the required arrow, a tooltip specifying the source and target column is displayed.

From DB 39.5.7

Note
  • In structured projects, the transfer arrows take effect for the project level on which they were approved and all child project levels.

Up to DB 39.5.7

Note
  • In structured projects, the transfer arrows only take effect on main project level.

Traffic Lights

Information
  • To the left of the heading column, traffic light triangles visualize the deviation between budget values and the calculated cost or effort values for each line.
  • The traffic lights are only displayed if budget values are available.
  • The reference field for the traffic light is the % deviation field in the respective line.
    • Green traffic light: Total costs are lower than budget
    • Yellow traffic light: Costs/effort overrun of up to 5%
    • Red traffic light: Costs/effort overrun of up to 5%
  • The % deviation values reference the absolute values in the Deviation column.

Effort Block

Information
  • The construction and the editing options are identical to those in the Costs block.

Benefit and Revenues Block

On vertical level, the following levels are to be distinguished in the Benefit and revenues block:
  • Project total level
  • Yearly tranche level

Summarization
  • The values of the separate yearly tranches are summed up to program total level.

Note

  • If neither revenues nor benefit have been entered in the project yet, the yearly tranche level is not displayed.

On horizontal level, the following levels are to be distinguished in the Benefit and revenues block:

Budget Data Migration when Updating to Venus Versions

Attention
  • The editing of cost and budget data in versions up to DB 39.5.0 and from DB 39.5.0 (Venus) is based on different data models. Therefore you have to note the following when updating to DB 39.5.x:
    • Since there is no division into cost type groups but only a total value for project effort budget values in versions up to DB 39.5.0, it is migrated in the Budget (without SP) column of the Internal effort cost type group in versions from 39.5.0.
    • During migration, only approved annual values are transferred and summarized to the project. Annual values which are not approved are not considered.
    • Since in versions up to 39.5.0 benefit and revenue values in structured projects only exist per project and are not summarized, they are copied to the respective fields (without SP fields) in 39.5.x and are subsequently summarized to the structure fields (in versions from 39.5.0).
    • From DB 39.5.0, the current project structure is displayed in the status reports. The displayed data, however, is that of the structure which has been active at the time of creation of the status report. This means: if a project has been detached from the structure afterwards, it will not be displayed in any of the status reports created up to this date, its values, however, will be displayed.


See also: Tutorial: Budgeting with PLANTA project , Budget and Cost Planning
Topic attachments
I Attachment History Size Date Comment
Pngpng Portfoliozuordnung.PNG r1 0.7 K 2015-10-09 - 18:19  

         PLANTA project









 
  • Suche in Topic-Namen

  • Suche in Topic-Inhalten
This site is powered by the TWiki collaboration platform Powered by Perl