Send Forecast MOD009D2B From DB 39.5.14

Access path

Information

  • In case an employee notices upon completion of a task planned for him/her that the effort is higher than planned, he/she has the option to report them to the project manager responsible in the form of a remaining effort forecast.

Procedure

  • Click on the Send forecast button in the header area of the Time Recording module.
  • The Send Forecast module is opened.
  • Enter the estimated remaining effort in the Forecast field and save.
  • Click on the Send forecast button in the project line (button with envelope symbol).
  • The Send Info module is opened including an automatically created message.
  • The message contains the following data: sender, actual values of the current week, remaining and forecast values as well as the expected completion date, in case it is filled.
    • The project manager of the project is automatically entered as the recipient.
  • Click on the Send button. The message is automatically sent to the recipient via e-mail.