Workflow: Create Portfolio Status Report From DB 39.5.10

Please note
  • The following workflow applies to database versions starting from 39.5.10.
  • The following table contains links to the other versions:

DB 39.5.10 go to the tutorial
DB 39.5.9 go to the tutorial
< DB 39.5.9 go to the tutorial
  go to further tutorials

Access

Procedure
  • Open the PLANTA project Client.
  • Enter the demo user as portfolio manager R70 in the upper input field.
    • Demo users do not possess passwords, so no input is necessary in the second field.
  • Confirm with OK.
  • Select Portfolio Management Planning and Reports Multi-Portfolio Board in the User Menu.
  • Click on the ID of the required portfolio in the Portfolios module.
    • The Portfolio panel is opened, the Dashboard module is focused.
    • Click on the Status module tab.
      • The Status module is activated.
        • If there already are status reports for the selected portfolio, they are listed at the bottom module margin of the Portfolio status reports area.

Configure Status Report

Procedure
  • Enter the name for the report in the header in the Report field and select the month for which the status report is to apply from the for* listbox.
  • Make estimates on factors like costs, dates, etc.
    • by clicking on the » Change estimate button in the Estimate area (EinschaetzungDB10_1.png, EinschaetzungDB10_2.png, or EinschaetzungDB10_3.png).
      • If no thumb symbol is displayed, this means that no estimate is available.
    • Enter or edit comments on the required factors if necessary.
  • Assign a released status report to the respective planning object assigned to the portfolio in the Planning objects with status report selection area.
    • To do so, click on the ButtonStatusberichtZuordnenDB10.png Assign a status report to the planning object button. If the planning object has no released status reports, a message indicating this is displayed.
      • The Assign Status Report selection module is opened.
      • Click on the required status report.
        • The status report is assigned to the selected planning object.
    • Define whether the data (from the selected status report) of the respective planning object is considered and displayed in the Time&Budget matrix by setting or removing the checkmark in the TBM display checkbox.
    • The configuration of the new portfolio status report is thus completed.
    • The portfolio status report can now be created (frozen).

Freeze Status Report

Procedure
  • After the required configurations have been made, click on the Create status report button.
  • Confirm the Are all entries (estimates/comments) and assignments (status reports to planning objects) complete and up-to-date? message with Yes.
  • The Portfolio Status Reports module is opened.
    • The status report is now created.

Details

  • In the Portfolio Status Report module, the created status report can be released, printed as a PDF, or deleted by clicking on the respective buttons.

Note

  • Released status reports cannot be deleted. In order to delete them, the status of the status reports must be set back to “created” by canceling the release.
Topic attachments
ISorted ascending Attachment History Size Date Comment
Pngpng ButtonStatusberichtZuordnenDB10.png r1 0.5 K 2020-03-05 - 15:01  
Pngpng EinschaetzungDB10_1.png r3 r2 r1 0.6 K 2020-03-05 - 14:39  
Pngpng EinschaetzungDB10_2.png r3 r2 r1 0.6 K 2020-03-05 - 14:39  
Pngpng EinschaetzungDB10_3.png r3 r2 r1 0.6 K 2020-03-05 - 14:39  

         PLANTA project









 
  • Suche in Topic-Namen

  • Suche in Topic-Inhalten
This site is powered by the TWiki collaboration platform Powered by Perl