DT804 Open Items Up to DB 39.5.0
Note
- From DB 39.5.0 Open items was renamed Todo items. Hence, the name of DT805 as well as the names of the corresponding DIs have changed. If you are using a DB version 39.5.0, please go to the DT804TodoItem topic.
DI006450 Project ID
Technical ID of the project. Is generated automatically upon creation of the project and cannot be changed afterwards unlike the functional ID. It is usually invisible in the modules.
DI006451 Project ID
Technical ID of the project. Is generated automatically upon creation of the project and cannot be changed afterwards unlike the functional ID. It is usually invisible in the modules.
DI006452 Task ID
Technical ID of the task. Is generated automatically upon creation of the task and cannot be changed afterwards unlike the functional ID. It is usually invisible in the modules.
DI006453 Resource
ID of the
Resource parameter. For description, see
Resource name.
DI006454 Open Item
ID of the open item. Upon creation of a open item, it is automatically generated after saving.
Details
DI006474 Created On
When you create a record, the creation date is automatically entered in this field.
DI006477 Created by
When you create a record, the ID (code) of the logged-on user is automatically entered in this field.
The creating user is also the
owner of a record.
DI006501 Item
DI006503 Start from
Date on which the completion of the open item is supposed to start
DI006504 Date
Date by which the open item is to be completed
Details
- In the Open Items and Schedule modules, the following traffic lights are set in the Date field:
- Red: requested end date is in the past.
- Yellow: requested end date is today.
- Green: requested end date is in the future
DI006505 % completed
Here, the percentage to which the open item is completed is entered.
DI006506 Linked File
DI006507 Category
Open item category
Details
DI006508 Priority
Priority of the open item
Values
- 1: high
- 2: Medium:
- 3: low
DI006509 Open Item Name
Name of the open item
DI006669 Calculation Start
Calculated start date of the task to which the open item is assigned
DI006670 Calculation End
Calculated end date of the task to which the open item is assigned
DI006671 Actual Start
Actual start date of the task to which the open item is assigned
DI006672 Actual End
Actual end date of the task to which the todo item is assigned
DI006674 Task Name
Name of the task to which the todo item is assigned
DI006676 Remaining Duration
Remaining duration of the task to which the todo item is assigned
DI006687 Project Name
Name of the project to which the todo item is assigned
DI006840 Type
DI006841 Project ID
ID of the project
DI009625 Bar Open Item Start from-Date
Bar for todo dates of the todo item (
Start from,
Date)
DI023367 TDI: Counter (WB 1)
Technical data item: Counter (WB 1) shows the number of open items with a particular status. For description, see
TDI:Past/Current/Future.
DI023375 TDI:Past/Present/Future
Technical data item controlling the status of open items
Values
- Without date
- Late
- Today
- Future
DI024603 Outlook Export
DI024867 Resource Structure Code
DI026060 Comments
You can enter comments on the todo item here.
DI040536 Resource Name
Incarnation field of the
Resource parameter. Here a resource for the completion of the open item is selected from the listbox.
DI041375 Project
ID of the project to which the todo item is assigned
DI041594 Task
ID of the task to which the todo item is assigned
DI051838 Created by
When you create a record, the ID (code) of the logged-on user is automatically entered in this field.
The creating user is also the
owner of a record.
DI056993 804: OLAP
DI057578 Own/Other Items
Grouping parameters for todo items
DI058227 Parent Task Name
Name of the parent task
Note
- This field is hidden by default and can be displayed by the user if necessary.
DI058228 WBS Code
WBS code of the task to which the todo item is assigned
Note
- This field is hidden by default and can be displayed by the user if necessary