Base | Only tasks the deviation values of which are > 0 (indicated by red or yellow traffic lights) are displayed. Tasks are displayed grouped by three criteria: dates, costs, and effort. In every grouping area, only data of the respective grouping criterion is displayed for each task. |
All end dates | All tasks of the project are displayed with end date values. |
All effort data | All tasks of the project are displayed with effort values. |
All cost data | All tasks of the project are displayed with cost values. |
Legend: Project
Symbol Meaning Color Comment
![]()
Actual dates Actual start and Actual end (if there is any, otherwise Latest time recording date) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) when calculating the schedule of the respective planning object. ![]()
Calculated dates from status report Calc. start and Calc. end of the planning object from the selected status report. Legend: Task
Symbol Meaning Color Comment ![]()
Task requested dates Requested start and Requested end of a task can be defined in the corresponding data fields in the Schedule module or they can be entered directly and graphically in the Gantt chart. ![]()
Calculated dates of the tasks Uncritical
Critical
Calc. start and Calc. end are calculated by clicking on the calculation button or by selecting the respective menu item.
Uncritical means: Total float > 0
Critical means: Total float 0
Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical.![]()
Calculated dates of the summary tasks A summary task is a task in the structured schedule that consists of subtasks and summarizes them. Information on the summary task, such as duration and dates, is determined automatically from the sub-tasks. ![]()
Calculated dates of the tasks from status report Calc. start and Calc. end of the tasks, the milestones, and the master milestones from the selected status report. ![]()
Calculated dates of summary tasks from status report Calc. start and Calc. end of the summary tasks from the selected status report