DT823 Project/Report

DI008413 Project ID

Technical ID of the project

DI041520 Project

Functional ID of the project

DI008414 Parent project ID

Technical ID of the parent project

DI008416 Report

Code (ID) of the status report

DI008578 Main project ID

Technical ID of the main project

DI008586 Main project status

DI008588 Requested start

Requested start date of the project at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

DI008589 Requested end

Requested end date of the project at the time of creation of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

DI008590 Calc. start

Calculated start date of the project at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

DI008591 Calc. end

Calculated end date of the project at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

DI008592 Actual start

Actual start date of the project at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

DI008593 Actual end

Actual end date of the project at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

DI008594 Planned duration

Planned duration of the entire project at the time of creatiob/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

DI008595 Actual duration

Actual duration of the entire project at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

DI008596 Remaining duration

Remaining duration of the entire project at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

DI008597 Planned effort

From DB 39.5.0

Planned effort of the project at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the DI of the same name in the current planning (DT461 Project).

Up to DB 39.5.0

Planned total effort for the Internal and External resource type at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

DI008598 Actual effort

From DB 39.5.0

Actual effort of the project at the time of creation/update of the selected status report. The value is transferred from the DI of the same name in the current planning (DT461 Project) when creating/updating the status report.

Up to DB 39.5.0

Actual total effort for the Internal and External resource type at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

DI008599 Remaining effort

From DB 39.5.0

Remaining effort of the project at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the DI of the same name in the current planning (DT461 Project).

Up to DB 39.5.0

Remaining total effort for the Internal and External resource type at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

DI008602 Number of tasks

Number of tasks of the project

From DB 39.5.12

DI008604 Manager ID

Code (ID) of the person who was project manager at the time of creation/update of the selected status report

Up to DB 39.5.12

DI008604 Manager

Code (ID) of the person who was project manager at the time of creation/update of the selected status report

DI008605 Cost budget

From DB 39.5.0

Sum of all costs from all cost type groups at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the DI of the same name in the sum line of the cost report table (DT284 Project/Report/CTGr).

Up to DB 39.5.0

Sum of all costs from all cost type groups at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

DI008609 Total costs

From DB 39.5.0

Actual costs of the project at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the DI of the same name in the sum line of the cost report table (DT284 Project/Report/CTGr).

Up to DB 39.5.0

Actual total costs for the Internal and External resource type at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

DI008606 Planned costs

From DB 39.5.0

Planned costs of the project at the time of creation/update of the selected status report. The value is transferred from the DI of the same name in the current planning (DT461 Project) when creating/updating the status report.

Up to DB 39.5.0

Planned total costs for the Internal and External resource type at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

DI008607 Actual costs

From DB 39.5.0

Actual costs of the project at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the DI of the same name in the current planning (DT461 Project).

Up to DB 39.5.0

Actual total costs for the Internal and External resource type at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

DI008608 Rem. costs

From DB 39.5.0

Remaining costs of the project at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the DI of the same name in the current planning (DT461 Project).

Up to DB 39.5.0

Remaining total costs for the Internal and External resource type at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

.

DI008610 Total effort

From DB 39.5.0

Sum of all effort of the project at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the DI of the same name in the current planning (DT461 Project).

Up to DB 39.5.0

Sum of all total effort for the Internal and External resource type at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

DI008611 Project name

Name of the project

From DB 39.5.7

DI008612 Entire project estimate

Estimate of the status of the entire project (program) by the manager after capacity scheduling at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the DI of the same name in the current planning (DT461 Project).

From DB 39.5.7

DI008612 Manager estimate

Estimate of the status of the entire project by the manager at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the DI of the same name in the current planning (DT461 Project).

DI008613 Estimate date entire project

Date of the estimate of the status of the entire project by the manager at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the DI of the same name in the current planning (DT461 Project).

DI008615 Effort budget

Budget details for effort

DI008616 Cost center

Cost center (organizational unit) of the project at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the DI of the same name in the current planning (DT461 Project).

DI008668 Customer

Customer of the project at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the DI of the same name in the current planning (DT461 Project).

DI008670 Main project name

Name of the main project

DI008702 Report name

Name of the report

Note

From DB 39.5.6

* The name can only be changed in unreleased status reports and unreleased project applications. In released status reports as well as in released and unreleased NEW project applications, changing is not possible.

Up to DB 39.5.6

The name can only be changed in unreleased status reports and in unreleased project applications. Released status reports and project applications cannot be changed.

DI008706 Date

Date on which the report status was allocated to the respective report

From DB 39.5.7

DI008708 Deviation project end dates: calc. end - requested end

Absolute deviation (n days) of the project end dates (calc. end of requested end) at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the DI of the same name in the current planning (DT461 Project).

Up to DB 39.5.7

DI008708 Date deviation

Absolute deviation (n days) of the project end dates (calc. end of requested end) at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the DI of the same name in the current planning (DT461 Project).

From DB 39.5.7

DI008709 Deviation MMS end dates: calc. end - requested end

Absolute deviation of the master milestone end dates (calc. end of requested end) at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the DI of the same name in the current planning (DT461 Project). The highest value from all master milestones is visualized.

Up to DB 39.5.7

DI008709 Master milestone delay

Absolute deviation of the master milestone end dates (calc. end of requested end) at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the DI of the same name in the current planning (DT461 Project). The highest value from all master milestones is visualized.

DI008710 % deviation costs: total - budget

Percentage deviation of the total costs from the cost budget of the selected status report

Details

  • Deviation > 0 means: Budget overrun!

DI008711 % deviation effort: total - budget

Percentage deviation of total costs from the cost budget of the selected status report

Details

  • Deviation > 0 means: Budget overrun!

From DB 39.5.7

DI008722 OLE entire project estimate

Symbol for the visualization of the estimate of the status of the project by the manager in the selected status report. The symbol references the value of the Estimate entire project value of the selected status report.

Up to DB 39.5.7

DI008722 OLE manager estimate smiley

Symbol for the visualization of the estimate of the status of the project by the manager in the selected status report. The symbol references the value of the Estimate entire project value of the selected status report.

From DB 39.5.7

DI008725 OLE deviation project end dates: calc. end - requested end

Symbol (traffic light) for the visualization of the project end dates (calc. end from requested end) in the selected status report. The symbol references the value of the Deviation project end dates: calc. end - requested end parameter of the selected status report.

Up to DB 39.5.7

DI008725 OLE end date smiley

Symbol (traffic light) for the visualization of the project end dates (calc. end from requested end) in the selected status report. The symbol references the value of the Deviation project end dates: calc. end - requested end parameter of the selected status report.

From DB 39.5.7

DI008728 OLE effort deviation: total - budget

Symbol (traffic light) for the visualization of the deviation of the total effort from the effort budget in the selected status report. The symbol references the value of the % deviation effort: total - budget parameter of the selected status report.

Up to DB 39.5.7

DI008728 OLE effort smiley

Symbol (traffic light) for the visualization of the deviation of the total effort from the effort budget in the selected status report. The symbol references the value of the % deviation effort: total - budget parameter of the selected status report.

From DB 39.5.7

DI008731 OLE deviation costs: total - budget

Symbol (traffic light) for the visualization of the deviation of the total costs from the cost budget in the selected status report. The symbol references the value of the % deviation costs: total - budget parameter of the selected status report.

Up to DB 39.5.7

DI008731 OLE costs smiley

Symbol (traffic light) for the visualization of the deviation of the total costs from the cost budget in the selected status report. The symbol references the value of the % deviation costs: total - budget parameter of the selected status report.

From DB 39.5.7

DI008734 OLE deviation MMS end dates: calc. end - requested end

Symbol (traffic light) for the visualization of the master milestone end dates (calc. end from requested end) in the selected status report. The symbol references the value of the Deviation MMS end dates: calc. end - requested end parameter of the selected status report.

Up to DB 39.5.7

DI008734 OLE master milestones smiley

DI008734 OLE deviation MMS end dates: calc. end - requested end

Symbol (traffic light) for the visualization of the master milestone end dates (calc. end from requested end) in the selected status report. The symbol references the value of the Deviation MMS end dates: calc. end - requested end parameter of the selected status report.

DI008744 HT: Dates

DI008811 HT: planned/actual costs

DI008813 Main project = project

DI008816 Cost deviation: total - budget

Absolute deviation of the total costs from the cost budget of the selected status report

From DB 39.5.12

DI008819 Manager

Name of the person who was project manager at the time of creation/update of the selected status report

Up to DB 39.5.12

DI008819 Manager name

Name of the person who was project manager at the time of creation/update of the selected status report

DI008821 Released on

Date on which the selected status report was released

From DB 39.5.12

DI008822 Released by: ID:

Code (ID) of the user who released the selected status report

Up to DB 39.5.12

DI008822 Released by

Code (ID) of the user who released the selected status report

From DB 39.5.12

DI008823 Released by

Name of the user who released the selected status report

Up to DB 39.5.12

DI008823 Released by: name

Name of the user who released the selected status report

From DB 39.5.12

DI008824 Created by

Name of the user who created the record

From DB 39.5.12

DI008824 Created by: name

Name of the user who created the record

DI008420 Created on

When you create a record, the creation date is automatically entered in this field.

DI008423 Created by

When you create a record, the ID (code) of the logged-on user is automatically entered in this field.

The creating user is also the owner of a record.

DI022285 Milestone trend analysis

Via this checkbox it is controlled whether the respective status report is considered in the master milestone trend analysis or not, or whether the status report is to be compared to the current status of the project in the Delta View module.

Values

  • Checked - the respective status report is considered in the milestone or master milestone trend analysis, or, the respective status report is compared to the current status of the project.
  • Unchecked - the respective status report is not considered in the milestone or master milestone trend analysis, or, the respective status report is compared to the current status of the project.

DI023333 Last scheduling date

Date on which the last calculation of the schedule was carried out before the creation/update of the selected status report

DI028505 Baseline from

Date on which the status report was defined as a baseline

DI028506 Final report

Parameter which marks the status report as a final report

DI028538 Planned revenues

Planned revenues at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

DI028539 Actual revenues

Actual revenues at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

DI028540 Remaining revenues

Remaining revenues at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

DI028541 Total revenues

Total revenues at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

DI028547 Revenues - costs

Deviation of the Total revenues frozen in the status report from the Total costs

DI029162 823: OLAP 1 - txt

DI029163 Cost center name

Name for the cost center parameter

DI034525 Active baseline

Parameter that marks a baseline as active. If several baselines have been created, the last created baseline is always marked as an Active baseline.

Values

  • Checked: The status report is an active baseline
  • Unchecked: The status report is no active baseline

Note

  • The checkbox is always activated for one status report only.

DI029177 Previous baseline

Parameter that marks, which status reports have been baselines before the latest baseline was created. The new baseline is marked with the Active baseline parameter.

Values

  • Checked: The status report is a previous baseline
  • Unchecked: The status report is no previous baseline

Note

  • The checkbox is activated for all existing baselines except the Active baseline.

DI029178 Previous status report

Parameter which marks a status report that was active before the currently active status report. The active status report is the last released status report.

Values

  • Checked: The status report is a previous status report
  • Unchecked: The status report is no previous status report

Note

  • The checkbox is always activated for one status report only.

DI029179 Active status report

Parameter that marks a baseline as an active status report. The active status report is the last released status report.

Values

  • Checked: The status report is an active status report
  • Unchecked: The status report is no active status report

Note

  • The checkbox is always activated for one status report only.

DI029180 Estimate project end date

Numeric estimate value for the end date of the project/program, according to which the display of the respective estimate symbol is done. The value is transferred from the DI of the same name in the current planning (DT461 Project) and is invisible in the user modules.

DI029181 Cost estimate

Numeric estimate value for the costs of the project/program, according to which the display of the respective estimate symbol is done. The value is transferred from the DI of the same name in the current planning (DT461 Project) and is invisible in the user modules.

DI029182 Effort estimate

Numeric estimate value for the effort of the project/program, according to which the display of the respective estimate symbol is done. The value is transferred from the DI of the same name in the current planning (DT461 Project) and is invisible in the user modules.

DI029183 Estimate project/MMS end date

Numeric estimate value for the end dates of the project/program, according to which the display of the respective estimate symbol is done. The value is transferred from the DI of the same name in the current planning (DT461 Project) and is invisible in the user modules.

DI029184 Quality estimate

Numeric estimate value for the end dates of the project/program, according to which the display of the respective estimate symbol is done. The value is transferred from the DI of the same name in the current planning (DT461 Project) and is invisible in the user modules.

DI029185 Estimate date project end date

Date on which the estimate of the project/program end date was done. The value is transferred from the DI of the same name in the current planning (DT461 Project) and is invisible in the user modules.

DI029186 Cost estimate date

Date on which the estimate of the costs of the project/program was done. The value is transferred from the DI of the same name in the current planning (DT461 Project) and is invisible in the user modules.

DI029187 Effort estimate date

Date on which the estimate of the project/program effort was done. The value is transferred from the DI of the same name in the current planning (DT461 Project) and is invisible in the user modules.

From DB 39.5.7

DI029188 Estimate date project/MMS end dates

The date on which the estimate of the end dates of the project/program and the master milestones was done. The value is transferred from the DI of the same name in the current planning (DT461 Project) and is invisible in the user modules.

Up to DB 39.5.7

DI029188 Milestones estimate date

Date on which the estimate of the costs of the master milestones was done. The value is transferred from the DI of the same name in the current planning (DT461 Project) and is invisible in the user modules.

DI029189 Estimate date for quality

The date on which the estimate of the costs of the project/program was done. The value is transferred from the DI of the same name in the current planning (DT461 Project) and is invisible in the user modules.

DI029196 Comment entire project

Comment on the quality of the project/program at the time of creation/update of the selected status report. The value is transferred from the DI of the same name in the current planning (DT461 Project).

DI029197 Comment project end date

Comment on the end date of the project/program at the time of creation/update of the selected status report. The value is transferred from the DI of the same name in the current planning (DT461 Project).

DI029198 Comment costs

Comment on the costs of the project/program at the time of creation/update of the selected status report. The value is transferred from the DI of the same name in the current planning (DT461 Project).

DI029199 Comment effort

Comment on the effort of the project/program at the time of creation/update of the selected status report. The value is transferred from the DI of the same name in the current planning (DT461 Project).

From DB 39.5.7

DI029200 Comment project/MMS end dates

Comment on the end dates of the project/program and the master milestones at the time of creation/update of the selected status report. The value is transferred from the DI of the same name in the current planning (DT461 Project).

Up to DB 39.5.7

DI029200 Comment milestones

Comment on the master milestone dates of the project at the time of creation/update of the selected status report. The value is transferred from the DI of the same name in the current planning (DT461 Project).

DI029201 Comment quality

Comment on the total status of the project/program at the time of creation/update of the selected status report. The value is transferred from the DI of the same name in the current planning (DT461 Project).

DI061349 Comment risks/opportunities

Comment on the risks/opportunities of the project/program at the time of creation/update of the selected status report. The value is transferred from the DI of the same name in the current planning (DT461 Project).

DI029208 OLE cost estimate

Symbol visualizing the estimate of the project/program costs by the project/program manager at the time of creation/update of the selected status report. The symbol references the value of the Cost estimate parameter.

DI029209 OLE effort estimate

Symbol visualizing the estimate of the project/program effort by the project/program manager at the time of creation/update of the selected status report. The symbol references the value of the Effort estimate parameter.

DI029210 OLE estimate project end date

Symbol visualizing the estimate of the project/program end date by the project/program manager at the time of creation/update of the selected status report. The symbol references the value of the Project end date estimate parameter.

From DB 39.5.7

DI029211 OLE estimate project/MMS end dates

Symbol visualizing the estimate of the project/program end dates and master milestones by the project/program manager at the time of creation/update of the selected status report. The symbol references the value of the Project/MMS end date estimate parameter.

Up to DB 39.5.7

DI029211 OLE milestones estimate

Symbol visualizing the estimate of the master milestones by the project manager at the time of creation/update of the selected status report. The symbol references the value of the Milestone estimate parameter.

DI029212 OLE quality estimate

Symbol visualizing the estimate of the quality of the project/program costs by the project/program manager at the time of creation/update of the selected status report. The symbol references the value of the Estimate quality parameter.

DI061352 OLE risks/opportunities estimate

Symbol visualizing the estimate of the risks/opportunities of the project/program by the project/program manager at the time of creation/update of the selected status report. The symbol references the value of the Estimate risks/opportunities parameter.

From DB 39.5.7

DI029828 Deviation project end dates: calc. end - requested end (active SR)

Deviation of the calculated end date from the requested end date of the project (program) from the status report that was active at the time of creation of the selected status report. Upon creation/update of the status report, the value is copied from the Deviation project end dates: calc. end - requested end parameter of the status report active at that time.

Up to DB 39.5.7

DI029828 End deviation (previous report)

Deviation of the calculated end date from the requested end date of the project (program) from the status report that was active at the time of creation of the selected status report. Upon creation/update of the status report, the value is copied from the 008711 parameter of the status report active at that time.

From DB 39.5.7

DI029829 Deviation MMS end dates: calc. end - requested end (active SR)

Deviation of the calculated end date from the requested end date of the master milestones (the highest value from all master milestones) from the status report that was active at the time of creation of the selected status report. Upon creation/update of the status report, the value is copied from the Deviation MMS end dates: calc. end - requested end parameter of the status report active at that time.

Up to DB 39.5.7

DI029829 Milestones deviation (previous report)

Deviation of the calculated end date from the requested end date of the master milestones (the highest value from all master milestones) from the status report that was active at the time of creation of the selected status report. Upon creation/update of the status report, the value is copied from the Deviation MMS end dates: calc. end - requested end parameter of the status report that was active at that time.

From DB 39.5.7

DI029830 % deviation effort: total - budget (active SR)

Percentage deviation of the total effort from the effort budget from the status report that was active at the time of creation of this status report. Upon creation/update of the status report, the value is copied from the % deviation effort: total - budget parameter of the status report that was active at that time.

Up to DB 39.5.7

DI029830 Effort deviation (previous report)

Percentage deviation of the total effort from the effort budget from the status report that was active at the time of creation of this status report. Upon creation/update of the status report, the value is copied from the % deviation effort: total - budget parameter of the status report that was active at that time.

From DB 39.5.7

DI029836 % deviation costs: total - budget (active SR)

Percentage deviation of the total costs from the cost budget from the status report that was active at the time of creation of this status report. Upon creation/update of the status report, the value is copied from the % deviation costs: total - budget parameter of the status report that was active at that time.

Up to DB 39.5.7

DI029836 Total costs deviation (previous report)

Percentage deviation of the total costs from the cost budget from the status report that was active at the time of creation of this status report. Upon creation/update of the status report, the value is copied from the % deviation costs: total - budget parameter of the status report that was active at that time.

From DB 39.5.7

DI029843 OLE trend deviation Project end date (SR vs. active SR)

Symbol for the visualization of the trend of the project end date deviation of the selected status report (Deviation project end dates: calc. end - requested end) in comparison to the deviation value from the status report that was active at the time of creation of the selected status report (Deviation project end dates: calc. end - requested end (active SR)).

Details

  • Arrow up: negative trend
  • Arrow down: positive trend
  • Arrow to the right: no change to the values

Up to DB 39.5.7

DI029843 OLE end dates compared

Symbol for the visualization of the trend of the deviation of the project end dates (calc. end from requested end) of the selected status report (Deviation project end dates: calc. end - requested end) in comparison to the deviation value from the status report that was active at the time of creation of the selected status report (Deviation project end dates: calc. end - requested end (active SR)).

Details

  • Arrow up: negative trend
  • Arrow down: positive trend
  • Arrow to the right, no change to the values

From DB 39.5.7

DI029844 OLE trend effort deviation (SR vs. active SR)

Symbol for the visualization of the trend of the effort deviation values (Total effort from Effort budget) of the selected status report (% deviation total effort budget) compared to the status report that was active at the time of creation of this report (% deviation effort: total - budget (active SR))

Meaning

  • Arrow up: negative trend
  • Arrow down: positive trend
  • Arrow to the right: no change to the values

Up to DB 39.5.7

DI029844 OLE effort comparison

Symbol for the visualization of the trend of the effort deviation values (Total effort vs. Effort budget) of the selected status report (% deviation total effort budget) compared to the status report that was active at the time of creation of this report (Active SR: % budget-total effort deviation)

Meaning

  • Arrow up: negative trend
  • Arrow down: positive trend.

From DB 39.5.7

DI029845 OLE trend deviation MMS end dates (SR vs. active SR)

Symbol for the visualization of the trend of the deviation values of the master milestone end dates of the selected status report (Deviation MMS end dates: calc. end - requested end) compared to the deviation value from the status report that was active at the time of creation of the selected status report (Deviation MMS end dates: calc. end - requested end (active SR)).

Meaning

  • Arrow up: negative trend
  • Arrow down: positive trend
  • Arrow to the right: no change to the values

Up to DB 39.5.7

DI029845 OLE master milestones comparison

Symbol for the visualization of the deviation values of the master milestones (master milestone trend) between the selected status report and the status report that was active at the time of creation of this report

Meaning

  • Arrow up: negative trend
  • Arrow down: positive trend

From DB 39.5.7

DI029851 OLE trend cost deviation (SR vs. active SR)

Symbol for the visualization of the trend of the cost deviation values of the selected status report (% deviation costs: total - budget) compared to the deviation value of the status report that was active at the time of creation of this status report (% deviation costs: total - budget (active SR))

Meaning

  • Arrow up: negative trend
  • Arrow down: positive trend
  • Arrow to the right: no change to the values

Up to DB 39.5.7

DI029851 OLE costs comparison

Symbol for the visualization of the trend of the cost deviation values of the selected status report (% deviation costs: total - budget) compared to the deviation value of the status report that was active at the time of creation of this status report (% deviation costs: total - budget (active SR))

Meaning

  • Arrow up: negative trend
  • Arrow down: positive trend
  • Arrow to the right: no change to the values

From DB 39.5.7

DI029866 % deviation costs: total - budget (baseline)

Percentage deviation of the total costs from the cost budget from the status report that was active at the time of creation of this status report. Upon creation/update of the status report, the value is copied from the % deviation costs: total - budget parameter of the baseline that was active at that time.

Up to DB 39.5.7

DI029866 Baseline: cost deviation

Percentage deviation of the total costs from the cost budget from the status report that was active at the time of creation of this status report. Upon creation/update of the status report, the value is copied from the % deviation costs: total - budget parameter of the baseline that was active at that time.

From DB 39.5.7

DI029882 % deviation effort: total - budget (baseline)

Percentage deviation of the total effort from the effort budget from the status report that was active at the time of creation of this status report. Upon creation/update of the status report, the value is copied from the % deviation effort: total - budget parameter of the baseline that was active at that time.

Up to DB 39.5.7

DI029882 Baseline: effort deviation

Percentage deviation of the total effort from the effort budget from the status report that was active at the time of creation of this status report. Upon creation/update of the status report, the value is copied from the % deviation effort: total - budget parameter of the baseline that was active at that time.

From DB 39.5.7

DI029883 Deviation project end dates: calc. end - requested end (baseline)

Deviation of the calculated end date from the requested end date of the project (program) from the status report that was active at the time of creation of the selected status report. Upon creation/update of the status report, the value is copied from the Deviation project end dates: calc. end - requested end parameter of the baseline that was active at that time.

Up to DB 39.5.7

DI029883 Baseline: end deviation

Deviation of the calculated end date from the requested end date of the project (program) from the status report that was active at the time of creation of the selected status report. Upon creation/update of the status report, the value is copied from the Deviation project end dates: calc. end - requested end parameter of the baseline that was active at that time.

From DB 39.5.7

DI029884 Deviation MMS end dates: calc. end - requested end (baseline)

Deviation of the calculated end date from the requested end date of the master milestones (the highest value from all master milestones) from the status report that was active at the time of creation of the selected status report. Upon creation/update of the status report, the value is copied from the Deviation MMS end dates: calc. end - requested end parameter of the baseline that was active at that time.

Up to DB 39.5.7

DI029884 Baseline: milestone delay

Deviation of the calculated end date from the requested end date of the master milestones (the highest value from all master milestones) from the status report that was active at the time of creation of the selected status report. Upon creation/update of the status report, the value is copied from the Deviation MMS end dates: calc. end - requested end parameter of the baseline that was active at that time.

DI034409 Main project/report

DI040775 Measures

Measures of the project (program) at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the DI of the same name in the current planning (DT461 Project).

DI040776 Decisions

Measures referring to the project (program) at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the DI of the same name in the current planning (DT461 Project).

DI040830 Main project

ID of the main project

DI040997 HDI: baseline, active, previous

Help DI for selecting the data from the active baseline from the active status report and the status report that was active before the currently active status report

DI056898 Total duration

Total duration of the project (program) at the time of creation/update of the selected status report. The value is calculated as a sum of the values frozen in the selected status report Actual duration and Remaining duration.

DI056971 Status Month (period)

Time period (month) to which the status report applies

DI056972 % actual costs to planned costs

Percentage relation of Actual costs to Planned costs of the project (program) in the selected status report

DI056973 % actual costs to the cost budget

Percentage relation of Actual costs to Cost budget of the project (program) in the selected status report

DI056974 % actual costs to total costs

Percentage relation of Actual costs to Total costs of the project (program) in the selected status report

DI056977 Report status

Current status of the report

DI056997 % actual effort to planned effort

Percentage relation of Actual effort to Planned effort of the project (program) in the selected status report

DI056998 % actual effort to effort budget

Percentage relation of Actual effort to Effort budget of the project (program) in the selected status report

DI056999 % actual effort to total effort

Percentage relation of Actual effort to Total effort of the project (program) in the selected status report

DI057531 Project

Functional ID of the project. It is generated automatically (copied from the technical project ID). Unlike the technical Project ID, the functional ID can be changed manually afterwards if necessary.

DI057563 TDI: 1 (Number)

From DB 39.5.7

DI057723 Total costs (current)

Total costs (actual+remaining) from the current planning. The value is transferred from the Total costs from the current planning (DT461 Project).

Up to DB 39.5.7

DI057723 Total costs complete

Total costs (actual+remaining) from the current planning. The value is transferred from the Total costs from the current planning (DT461 Project).

From DB 39.5.7

DI057724 Total revenues (current)

Total revenues (actual+remaining) from the current planning. The value is transferred from the Total revenues parameter from the current planning (DT461 Project).

Up to DB 39.5.7

DI057724 Total revenues complete

Total revenues (actual+remaining) from the current planning

DI057725 Cost budget (current)

Cost budget from the current planning. The value is transferred from the Cost budget parameter from the current planning (DT461 Project).

From DB 39.5.7

DI057726 Cost budget deviation: SR - current

Deviation between the cost budget value frozen in the selected status report and the cost budget value from the current planning

Calculation

Up to DB 39.5.7

DI057726 Delta cost budget

Deviation between the cost budget value frozen in the selected status report and the cost budget value from the current planning

Calculation

From DB 39.5.7

DI057727 Deviation total costs: SR - current

Deviation between the total costs value frozen in the selected status report and the total costs value from the current planning

Calculation

Up to DB 39.5.7

DI057727 Delta total costs

Deviation between the total costs value frozen in the selected status report and the total costs value from the current planning

Calculation

From DB 39.5.7

DI057728 Deviation total revenues: SR - current

Deviation between the total revenues value frozen in the selected status report and the total revenues value from the current planning

Calculation

Up to DB 39.5.7

DI057728 Delta total revenues

Deviation between the total revenues value frozen in the selected status report and the total revenues value from the current planning

Calculation

From DB 39.5.7

DI057977 Possible gross profit

Possible gross profit of the selected project and all of its subprojects at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

Up to DB 39.5.7

DI057977 Possible gross profit summarized

Possible gross profit of the selected project and all of its subprojects at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

From DB 39.5.7

DI029620 Probable gross profit

Probable gross profit of the project and all of its subprojects at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

Up to DB 39.5.7

DI029620 Probable gross profit summarized

At the time of creation/update of the selected status report, the probable gross profit is summarized from all project opportunities for which the Active checkbox is activated in the Risks/Opportunities module. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

From DB 39.5.7

DI029621 Actual gross profit summarized

Actual gross profit of the project and all of its subprojects at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

Up to DB 39.5.7

DI029621 Actual gross profit summarized

At the time of creation/update of the selected status report, the actual gross profit from all opportunities of the project for which the Active checkbox in the Risks/Opportunities module was activated is summarized in the respective modules. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

From DB 39.5.7

DI057975 Possible damage

Possible damage of the selected project and all of its subprojects at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

Up to DB 39.5.7

DI057975 Possible damage summarized

Summarized possible damage. The damage is summarized from all project risks for which the Active checkbox is activated in the Risks/Opportunities module. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

From DB 39.5.7

DI028291 Probable damage

Probable damage of the selected project and all of its subprojects at the time of creation/update of the status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

Up to DB 39.5.7

DI028291 Probable damage summarized

At the time of creation/update of the selected status report, the probable damage from all risks of the project for which the Active checkbox in the Risks/Opportunities module was activated is summarized in the respective modules. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

From DB 39.5.7

DI028292 Actual damage

Actual damage of the selected project and all of its subprojects at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

Up to DB 39.5.7

DI028292 Actual damage summarized

At the time of creation/update of the selected status report, the actual damage from all risks of the project for which the Active checkbox in the Risks/Opportunities module was activated is summarized in the respective modules. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

New from DB 39.5.7

DI063803 Possible damage (without subprojects)

Possible damage of the project without considering its possibly existing subprojects at the time of status report creation/update. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

DI063804 Probable damage (without subprojects)

Probable damage of the project without considering its possibly existing subprojects at the time of status report creation/update. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

DI063805 Actual damage (without Subprojects)

Actual damage of the project without considering its possibly existing subprojects at the time of status report creation/update. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

DI063806 Possible gross profit (without subprojects)

Possible gross profit of the project without considering its possibly existing subprojects at the time of status report creation/update. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

DI063807 Probable gross profit (without subprojects)

Probable gross profit of the project without considering its possibly existing subprojects at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

DI063808 Actual gross profit (without subprojects)

Actual gross profit of the project without considering its possibly existing subprojects at the time of status report creation/update. Upon creation/update of the status report, the value is copied from the DI of the same name in the current planning (DT461 Project).

DI058030 Deviation project end dates: requested end - calc. end (text)

Absolute deviation of the calculated end date from the requested end date of the project (program) with text specification (delay/float) at the time of creation/update of the selected status report. The value is copied from the Deviation project end date requested end - calc. end.

DI058031 Deviation MMS end dates: requested end - calc. end (text)

Deviation of the calculated end date from the requested end date of the master milestones (the highest value from all master milestones) with text specification (delay/float) at the time of creation of the selected status report. The value is copied from the Deviation MMS end dates requested end - calc. end.

DI059238 Objectives

Objectives of the project (program) at the time of creation/update of the selected status report. The value is copied from the DI of the same name in the current planning (DT461 Project).

DI059239 Scope and limit

Scope and limit of the project (program) at the time of creation/update of the selected status report. The value is copied from the DI of the same name in the current planning (DT461 Project).

DI059240 Conseq. non-realization

Consequences in case of a non realization of the project (program) defined at the time of creation/update of the status report The value is copied from the DI of the same name in the current planning (DT461 Project).

DI059241 Areas involved

The departments, persons, etc. involved in the project (program) at the time of creation/update of the status report Upon creation/update of the status report, the value is copied from the DI of the same name from the current planning (DT461 Project).

DI059242 Mandatory

Parameter with the help of which a project (program) is marked as a mandatory project (mandatory program). Upon creation/update of the status report, the value is copied from the DI of the same name from the current planning (DT461 Project).

Notes

  • The parameter is meant to be a selection help for the portfolio manager for the creation of the portfolio. Mandatory projects must be realized, even if other projects appear to be more worthwhile, e.g. projects for complying with statutory requirements.
  • The parameter has no technical influence on the system.

DI059243 Mandatory: reason

Reason for the activation of the checkbox in the Mandatory field at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name from the current planning (DT461 Project).

DI059245 ROI

Return on investment value of the project (program) at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name from the current planning (DT461 Project).

DI059246 Description

Description of the project (program) at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name from the current planning (DT461 Project).

DI059247 Internal interest

The internal interest entered in the project (program) at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name from the current planning (DT461 Project).

DI059248 Area

ID of the Area parameter of the project (program) at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name from the current planning (DT461 Project).

DI059249 Break Even

Break even code of the project (program) at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name from the current planning (DT461 Project).

DI059250 Gross profit probability

Gross profit probability of the project (program) at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name from the current planning (DT461 Project).

From DB 39.5.7

DI059251 NPV (without subprojects)

Net present value (net capital value of the project without considering its possibly existing subprojects) at the time of status report creation/update. Upon creation/update of the status report, the value is copied from the DI of the same name from the current planning (DT461 Project). For further info on net present value, see here.

NEW The value is automatically calculated (Python value range) taking different parameters like costs, revenues, internal interest, etc. into account.

Formula

  • The calculation is done in accordance with the standard formula
NPVFormel.PNG

  • C0 Capital value with regard to t=0
  • i calculation interest rate (=internal interest, e.g. 5%)
  • N processing period
  • CFt Cashflow (source: Wikipedia)
    • In PLANTA, the cashflow is calculated per year: CFt = revenues + benefit - costs

Parameters involved (status reports)

Variable from the NPV calculation DI059251 NPV (without subprojects) DI059244 NPV
Revenues DT835 Total revenues (without subprojects) DT835 Total revenues
Benefit DT835 Resulting benefit (without subprojects) DT835 Resulting benefit
Costs DT285 Total costs (without subprojects) DT285 Total costs
i Interest rate DT823 Internal interest DT823 Internal interest
N review period Years planned in the project (yearly tranches from DT835) Years planned in the project (yearly tranches from DT835)

From DB 39.5.0

DI059251 NPV (without subprojects)

Net present value (net capital value of the project without considering its possibly existing subprojects) at the time of status report creation/update. Upon creation/update of the status report, the value is copied from the DI of the same name from the current planning (DT461 Project). For further info on net present value, see here.

From Release 39.5.0, the field is temporarily without function.

Up to DB 39.5.0

DI059251 NPV

Net present value (net capital value of the project without considering its possibly existing subprojects) at the time of status report creation/update. Upon creation/update of the status report, the value is copied from the DI of the same name from the current planning (DT461 Project). For further info on net present value, see here.

The value is copied from the field of the same name from DT461.

From DB 39.5.7

DI059244 NPV

Net present value (net capital value of the project without considering its possibly existing subprojects) at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name from the current planning (DT461 Project). For further info on net present value, see here.

NEW The value is automatically calculated (Python value range) taking different parameters like costs, revenues, internal interest, etc. into account.

For the calculation formula and the parameters involved, see NPV (without subprojects)

From DB 39.5.0

DI059244 NPV

Net present value (net capital value of the project without considering its possibly existing subprojects) at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name from the current planning (DT461 Project). For further info on net present value, see here.

From Release 39.5.0, the field is temporarily without function.

Up to DB 39.5.0

DI059244 NPV

Net present value (net capital value of the project without considering its possibly existing subprojects) at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name from the current planning (DT461 Project). For further info on net present value, see here.

DI059637 Calc. start (baseline)

Calculated start date of the project (program) from the baseline report. The value is copied from the Calc. start parameter of the baseline report.

Note

  • This field is hidden by default but can be displayed by the user if necessary.

DI059636 Calc. end (baseline)

Calculated end date of the project (program) from the baseline report. The value is copied from the Calc. end parameter of the baseline report.

Note

  • This field is hidden by default but can be displayed by the user if necessary.

DI059640 Bar: actual start - work reporting date

Bar for the visualization of the interval between the actual start date and the latest work reporting date of the project (program) in the selected status report

DI059638 Bar: planned dates (calculated dates from baseline)

Bar for the visualization of the interval between the calculated start date and calculated end date of the project (program) from the baseline report (planned dates).

DI059627 Bars: calculated dates by code

Bar for the visualization of the interval between the calculated start date and calculated end date of the project (program). The color of the bar is determined by the code of the project (program).

DI059628 Bar: requested dates

Bar for the visualization of the interval between the calculated start date and requested end date of the project (program) in the selected status report.

DI059686 Cost trend analysis

Via this checkbox you can control whether the respective status report is considered in the cost, effort, risk, or opportunity trend analysis.

Values

  • Checked : the status report is considered.
  • Unchecked : the status report is not considered

From DB 39.5.7

DI063004 OLE deviation project/MMS end date: calc. end - requested end

Up to DB 39.5.7

DI063004 OLE deviation dates small traffic light

Traffic light for the visualization of the deviation of the dates at the time of creation of this status report

DI059232 Frozen risk value

Percentage value of the calculated risk value of the planning object at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name from the current planning (DT461 Project).

DI059234 Frozen objective contribution

Percentage value of the calculated objective contribution of the planning object at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the DI of the same name from the current planning (DT461 Project).

From DB 39.5.7

DI063795 Deviation project end dates: calc. end - requested end (active SR)

Deviation of the calculated end date from the requested end date of the project (program) from the status report that was active at the time of creation of the selected status report with text specification (delay/float). Upon creation/update of the status report, the value is copied from the Deviation project end dates: calc. end - requested end parameter of the status report active at that time.

DI063796 Deviation MMS end dates: calc. end - requested end (active SR)

Deviation of the calculated end date from the requested end date of the master milestones (the highest value from all master milestones) from the status report that was active at the time of creation of the selected status report with text specification (delay/float). Upon creation/update of the status report, the value is copied from the Deviation MMS end dates: calc. end - requested end parameter of the status report active at that time.

DI062316 OLE revenues/benefit estimate

New from DB 39.5.10

DI064519 Simulation report

Code which is set for status reports which are created exclusively for simulation

DI064560 Opportunity green

Number of opportunities in the green range

DI064561 Opportunity yellow

Number of opportunities in the yellow range

DI064562 Opportunity red

Number of opportunities in the red range

DI064563 Risk red

Number of risks in the red range

DI064564 Risk yellow

Number of risks in the yellow range

DI064565 Risk green

Number of risks in the green range



DIs no longer used from DB 39.5.0

The DIs listed below are no longer used from DB version 39.5.0.

DI057979 Structure summarization: approved budget

Summarized budget values from the subprojects.

DI057985 Structure summarization: effort budget

Summarized effort from all subprojects.

DI057998 Entire structure: effort budget

Summarized effort from the parent project and the subprojects

DI057999 Entire structure: Approved budget

Summarized values from the subprojects and the cost budget.

Calculation

DI057976 Probability (damage) summarized

Probability of occurrence of the summarized damage in percent.

DI057978 Probability (gross profit) summarized

Probability of occurrence of the summarized gross profit in percent.

DI028509 Cost budget: internal personnel

Budget costs of the Internal personnel cost type group

Details

  • Costs result from the multiplication of resource efforts with the conversion factors.

DI028513 Total costs: internal personnel

Total costs of the Internal personnel Cost Type Group

Details

DI028514 Cost budget: external personnel

Budget costs of the External personnel cost type group

Details

DI028518 Total costs: external personnel

Total costs of the External personnel cost type group

Details

DI028519 Cost budget: material costs

Budget costs of the Material costs Cost Type Group

Details

DI028523 Total costs: material costs

Total costs of the Material costs cost type group

Details

DI028524 Cost budget: investments

Budget costs of the Investments cost type group

Details

DI028528 Total costs: investments

Total costs of the Investments cost type group

Details

DI028529 Cost budget: miscellaneous

Budget costs of the Miscellaneous cost type group

Details

DI028533 Total costs: miscellaneous

Total costs of the Miscellaneous cost type group

Details

DI028542 % external personnel deviation

Percentage deviation of the cost budget from the total costs for the External personnel cost type group

DI028543 % material costs deviation

Percentage deviation of total costs from the cost budget for the Material costs cost type group

DI028544 % investments deviation

Percentage deviation of the cost budget from the total costs for the Investments cost type group

DI028545 % miscellaneous deviation

Absolute deviation of the cost budget from the total costs for the Miscellaneous cost type group

DI028546 % internal personnel deviation

Percentage deviation of the cost budget from the total costs for the Internal personnel cost type group

DI028548 OLE miscellaneous

OLE symbol for the Miscellaneous cost type group.

DI028549 OLE investments

OLE symbol for the Investments cost type group

DI028550 OLE material costs

OLE symbol for the Material costs cost type group

DI028551 OLE external personnel

OLE symbol for the External personnel cost type group

DI028552 OLE Personal intern

OLE symbol for the External personnel cost type group

DI057691 Planned effort: external

Planned effort for the External resource type

DI057692 Actual effort: external

Actual effort for the External resource type

DI057693 Remaining effort: external

Remaining effort for the External resource type

DI057694 Total effort: external

Total effort for the External resource type

DI057695 Total effort: internal

Total effort for the Internal resource type

DI057696 Remaining effort: internal

Remaining effort for the Internal resource type

DI057697 Actual effort: internal

Actual effort for the Internal resource type

DI057698 Planned effort: internal

Planned effort for the Internal resource type

DI057980 Structure summarization: budget miscellaneous

Summarized budget values from subprojects of the Miscellaneous cost type group

DI057981 Structure summarization: budget investments

Summarized budget values from the subprojects of the Investments cost type group

DI057982 Structure summarization: budget material costs

Summarized budget values from the subprojects of the Investments cost type group

DI057983 Structure summarization: budget external personnel

Budget values of the External personnel cost type group summarized from subprojects

DI057984 Structure summarization: budget internal personnel

Budget values of the External personnel cost type group summarized from subprojects

DI058000 Total structure: budget miscellaneous

Values summarized from parent and subprojects of the Miscellaneous cost type group

Calculation

DI058001 Total structure: budget investments

Values summarized from parent and subprojects of the Investments cost type group

Calculation

DI058002 Total structure: budget material costs

Values summarized from parent and subprojects of the Material costs cost type group

Calculation

DI058003 Total structure: budget external personnel

Values summarized from parent and subprojects of the External personnel cost type group

Calculation

DI058004 Total structure: budget internal personnel

Values summarized from parent and subprojects of the Internal personnel cost type group

Calculation

DI058954 Total costs - budget deviation: internal personnel

Absolute deviation of total costs from the cost budget in the Internal personnel cost type group

Calculation

DI058955 Total costs - budget deviation: external personnel

Absolute deviation of total costs from the cost budget in the External personnel cost type group

Calculation

DI058956 Total costs - budget deviation: investments

Absolute deviation of total costs from the cost budget in the Investments cost type group

Calculation

DI058957 Total costs - budget deviation: miscellaneous

Absolute deviation of total costs from the cost budget in the Miscellaneous cost type group

Calculation

DI058958 Total costs - budget deviation: material costs

Absolute deviation of total costs from the cost budget in the Material costs cost type group

Calculation