DT823 Project/Report
DI008413 Project ID
Technical ID of the project
DI041520 Project
Functional ID of the project
DI008414 Parent project ID
Technical ID of the parent project
DI008416 Report
Code (ID) of the status report
DI008578 Main project ID
Technical ID of the main project
DI008586 Main project status
DI008588 Requested start
Requested start date of the project at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
DI008589 Requested end
Requested end date of the project at the time of creation of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
DI008590 Calc. start
Calculated start date of the project at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
DI008591 Calc. end
Calculated end date of the project at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
DI008592 Actual start
Actual start date of the project at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
DI008593 Actual end
Actual end date of the project at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
DI008594 Planned duration
Planned duration of the entire project at the time of creatiob/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
DI008595 Actual duration
Actual duration of the entire project at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
DI008596 Remaining duration
Remaining duration of the entire project at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
DI008597 Planned effort
From DB 39.5.0
Planned effort of the project at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the
DI of the same name in the current planning (DT461
Project).
Up to DB 39.5.0
Planned total effort for the
Internal and
External resource type at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
DI008598 Actual effort
From DB 39.5.0
Actual effort of the project at the time of creation/update of the selected status report. The value is transferred from the
DI of the same name in the current planning (DT461
Project) when creating/updating the status report.
Up to DB 39.5.0
Actual total effort for the
Internal and
External resource type at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
DI008599 Remaining effort
From DB 39.5.0
Remaining effort of the project at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the
DI of the same name in the current planning (DT461
Project).
Up to DB 39.5.0
Remaining total effort for the
Internal and
External resource type at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
DI008602 Number of tasks
Number of tasks of the project
From DB 39.5.12
DI008604 Manager ID
Code (ID) of the person who was project manager at the time of creation/update of the selected status report
Up to DB 39.5.12
DI008604 Manager
Code (ID) of the person who was project manager at the time of creation/update of the selected status report
DI008605 Cost budget
From DB 39.5.0
Sum of all costs from all
cost type groups at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the
DI of the same name in the sum line of the cost report table (DT284
Project/Report/CTGr).
Up to DB 39.5.0
Sum of all costs from all
cost type groups at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
DI008609 Total costs
From DB 39.5.0
Actual costs of the project at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the
DI of the same name in the sum line of the cost report table (DT284
Project/Report/CTGr).
Up to DB 39.5.0
Actual total costs for the
Internal and
External resource type at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
DI008606 Planned costs
From DB 39.5.0
Planned costs of the project at the time of creation/update of the selected status report. The value is transferred from the
DI of the same name in the current planning (DT461
Project) when creating/updating the status report.
Up to DB 39.5.0
Planned total costs for the
Internal and
External resource type at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
DI008607 Actual costs
From DB 39.5.0
Actual costs of the project at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the
DI of the same name in the current planning (DT461
Project).
Up to DB 39.5.0
Actual total costs for the
Internal and
External resource type at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
DI008608 Rem. costs
From DB 39.5.0
Remaining costs of the project at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the
DI of the same name in the current planning (DT461
Project).
Up to DB 39.5.0
Remaining total costs for the
Internal and
External resource type at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
.
DI008610 Total effort
From DB 39.5.0
Sum of all effort of the project at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the
DI of the same name in the current planning (DT461
Project).
Up to DB 39.5.0
Sum of all total effort for the
Internal and
External resource type at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
DI008611 Project name
Name of the project
From DB 39.5.7
DI008612 Entire project estimate
Estimate of the status of the entire project (program) by the manager after capacity scheduling at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the
DI of the same name in the current planning (DT461
Project).
From DB 39.5.7
DI008612 Manager estimate
Estimate of the status of the entire project by the manager at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the
DI of the same name in the current planning (DT461
Project).
DI008613 Estimate date entire project
Date of the estimate of the status of the entire project by the manager at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the
DI of the same name in the current planning (DT461
Project).
DI008615 Effort budget
Budget details for effort
DI008616 Cost center
Cost center (organizational unit) of the project at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the
DI of the same name in the current planning (DT461
Project).
DI008668 Customer
Customer of the project at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the
DI of the same name in the current planning (DT461
Project).
DI008670 Main project name
Name of the main project
DI008702 Report name
Name of the report
Note
From DB 39.5.6
* The name can only be changed in unreleased status reports and unreleased project applications. In released status reports as well as in released and unreleased NEW project applications, changing is not possible.
Up to DB 39.5.6
The name can only be changed in unreleased status reports and in unreleased project applications. Released status reports and project applications cannot be changed.
DI008706 Date
Date on which the
report status was allocated to the respective report
From DB 39.5.7
DI008708 Deviation project end dates: calc. end - requested end
Absolute deviation (n days) of the project end dates (calc. end of requested end) at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the
DI of the same name in the current planning (DT461
Project).
Up to DB 39.5.7
DI008708 Date deviation
Absolute deviation (n days) of the project end dates (calc. end of requested end) at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the
DI of the same name in the current planning (DT461
Project).
From DB 39.5.7
DI008709 Deviation MMS end dates: calc. end - requested end
Absolute deviation of the master milestone end dates (calc. end of requested end) at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the
DI of the same name in the current planning (DT461
Project). The highest value from all master milestones is visualized.
Up to DB 39.5.7
DI008709 Master milestone delay
Absolute deviation of the master milestone end dates (calc. end of requested end) at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the
DI of the same name in the current planning (DT461
Project). The highest value from all master milestones is visualized.
DI008710 % deviation costs: total - budget
Percentage deviation of the
total costs from the
cost budget of the selected status report
Details
- Deviation > 0 means: Budget overrun!
DI008711 % deviation effort: total - budget
Percentage deviation of
total costs from the
cost budget of the selected status report
Details
- Deviation > 0 means: Budget overrun!
From DB 39.5.7
DI008722 OLE entire project estimate
Symbol for the visualization of the estimate of the status of the project by the manager in the selected status report. The symbol references the value of the
Estimate entire project value of the selected status report.
Up to DB 39.5.7
DI008722 OLE manager estimate smiley
Symbol for the visualization of the estimate of the status of the project by the manager in the selected status report. The symbol references the value of the
Estimate entire project value of the selected status report.
From DB 39.5.7
DI008725 OLE deviation project end dates: calc. end - requested end
Symbol (traffic light) for the visualization of the project end dates (calc. end from requested end) in the selected status report. The symbol references the value of the
Deviation project end dates: calc. end - requested end parameter of the selected status report.
Up to DB 39.5.7
DI008725 OLE end date smiley
Symbol (traffic light) for the visualization of the project end dates (calc. end from requested end) in the selected status report. The symbol references the value of the
Deviation project end dates: calc. end - requested end parameter of the selected status report.
From DB 39.5.7
DI008728 OLE effort deviation: total - budget
Symbol (traffic light) for the visualization of the deviation of the total effort from the effort budget in the selected status report. The symbol references the value of the
% deviation effort: total - budget parameter of the selected status report.
Up to DB 39.5.7
DI008728 OLE effort smiley
Symbol (traffic light) for the visualization of the deviation of the total effort from the effort budget in the selected status report. The symbol references the value of the
% deviation effort: total - budget parameter of the selected status report.
From DB 39.5.7
DI008731 OLE deviation costs: total - budget
Symbol (traffic light) for the visualization of the deviation of the total costs from the cost budget in the selected status report. The symbol references the value of the
% deviation costs: total - budget parameter of the selected status report.
Up to DB 39.5.7
DI008731 OLE costs smiley
Symbol (traffic light) for the visualization of the deviation of the total costs from the cost budget in the selected status report. The symbol references the value of the
% deviation costs: total - budget parameter of the selected status report.
From DB 39.5.7
DI008734 OLE deviation MMS end dates: calc. end - requested end
Symbol (traffic light) for the visualization of the master milestone end dates (calc. end from requested end) in the selected status report. The symbol references the value of the
Deviation MMS end dates: calc. end - requested end parameter of the selected status report.
Up to DB 39.5.7
DI008734 OLE master milestones smiley
DI008734 OLE deviation MMS end dates: calc. end - requested end
Symbol (traffic light) for the visualization of the master milestone end dates (calc. end from requested end) in the selected status report. The symbol references the value of the
Deviation MMS end dates: calc. end - requested end parameter of the selected status report.
DI008744 HT: Dates
DI008811 HT: planned/actual costs
DI008813 Main project = project
DI008816 Cost deviation: total - budget
Absolute deviation of the
total costs from the
cost budget of the selected status report
From DB 39.5.12
DI008819 Manager
Name of the person who was project manager at the time of creation/update of the selected status report
Up to DB 39.5.12
DI008819 Manager name
Name of the person who was project manager at the time of creation/update of the selected status report
DI008821 Released on
Date on which the selected status report was released
From DB 39.5.12
DI008822 Released by: ID:
Code (ID) of the user who released the selected status report
Up to DB 39.5.12
DI008822 Released by
Code (ID) of the user who released the selected status report
From DB 39.5.12
DI008823 Released by
Name of the user who released the selected status report
Up to DB 39.5.12
DI008823 Released by: name
Name of the user who released the selected status report
From DB 39.5.12
DI008824 Created by
Name of the user who created the record
From DB 39.5.12
DI008824 Created by: name
Name of the user who created the record
DI008420 Created on
When you create a record, the creation date is automatically entered in this field.
DI008423 Created by
When you create a record, the ID (code) of the logged-on user is automatically entered in this field.
The creating user is also the
owner of a record.
DI022285 Milestone trend analysis
Via this checkbox it is controlled whether the respective status report is considered in the master milestone trend analysis or not, or whether the status report is to be compared to the current status of the project in the
Delta View module.
Values
- - the respective status report is considered in the milestone or master milestone trend analysis, or, the respective status report is compared to the current status of the project.
- - the respective status report is not considered in the milestone or master milestone trend analysis, or, the respective status report is compared to the current status of the project.
DI023333 Last scheduling date
Date on which the last
calculation of the schedule was carried out before the creation/update of the selected status report
DI028505 Baseline from
Date on which the status report was defined as a baseline
DI028506 Final report
Parameter which marks the status report as a final report
DI028538 Planned revenues
Planned revenues at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
DI028539 Actual revenues
Actual revenues at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
DI028540 Remaining revenues
Remaining revenues at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
DI028541 Total revenues
Total revenues at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
DI028547 Revenues - costs
Deviation of the
Total revenues frozen in the status report from the
Total costs
DI029162 823: OLAP 1 - txt
DI029163 Cost center name
Name for the
cost center parameter
DI034525 Active baseline
Parameter that marks a baseline as active. If several baselines have been created, the last created baseline is always marked as an
Active baseline.
Values
- : The status report is an active baseline
- : The status report is no active baseline
Note
- The checkbox is always activated for one status report only.
DI029177 Previous baseline
Parameter that marks, which status reports have been baselines before the latest baseline was created. The new baseline is marked with the
Active baseline parameter.
Values
- : The status report is a previous baseline
- : The status report is no previous baseline
Note
- The checkbox is activated for all existing baselines except the Active baseline.
DI029178 Previous status report
Parameter which marks a status report that was active before the currently active status report.
The active status report is the last released status report.
Values
- : The status report is a previous status report
- : The status report is no previous status report
Note
- The checkbox is always activated for one status report only.
DI029179 Active status report
Parameter that marks a baseline as an active status report.
The active status report is the last released status report.
Values
- : The status report is an active status report
- : The status report is no active status report
Note
- The checkbox is always activated for one status report only.
DI029180 Estimate project end date
Numeric estimate value for the end date of the project/program, according to which the display of the respective
estimate symbol is done. The value is transferred from the
DI of the same name in the current planning (DT461
Project) and is invisible in the user modules.
DI029181 Cost estimate
Numeric estimate value for the costs of the project/program, according to which the display of the respective
estimate symbol is done. The value is transferred from the
DI of the same name in the current planning (DT461
Project) and is invisible in the user modules.
DI029182 Effort estimate
Numeric estimate value for the effort of the project/program, according to which the display of the respective
estimate symbol is done. The value is transferred from the
DI of the same name in the current planning (DT461
Project) and is invisible in the user modules.
DI029183 Estimate project/MMS end date
Numeric estimate value for the end dates of the project/program, according to which the display of the respective
estimate symbol is done. The value is transferred from the
DI of the same name in the current planning (DT461
Project) and is invisible in the user modules.
DI029184 Quality estimate
Numeric estimate value for the end dates of the project/program, according to which the display of the respective
estimate symbol is done. The value is transferred from the
DI of the same name in the current planning (DT461
Project) and is invisible in the user modules.
DI029185 Estimate date project end date
Date on which the estimate of the project/program end date was done. The value is transferred from the
DI of the same name in the current planning (DT461
Project) and is invisible in the user modules.
DI029186 Cost estimate date
Date on which the estimate of the costs of the project/program was done. The value is transferred from the
DI of the same name in the current planning (DT461
Project) and is invisible in the user modules.
DI029187 Effort estimate date
Date on which the estimate of the project/program effort was done. The value is transferred from the
DI of the same name in the current planning (DT461
Project) and is invisible in the user modules.
From DB 39.5.7
DI029188 Estimate date project/MMS end dates
The date on which the estimate of the end dates of the project/program and the master milestones was done. The value is transferred from the
DI of the same name in the current planning (DT461
Project) and is invisible in the user modules.
Up to DB 39.5.7
DI029188 Milestones estimate date
Date on which the estimate of the costs of the master milestones was done. The value is transferred from the
DI of the same name in the current planning (DT461
Project) and is invisible in the user modules.
DI029189 Estimate date for quality
The date on which the estimate of the costs of the project/program was done. The value is transferred from the
DI of the same name in the current planning (DT461
Project) and is invisible in the user modules.
DI029196 Comment entire project
Comment on the quality of the project/program at the time of creation/update of the selected status report. The value is transferred from the
DI of the same name in the current planning (DT461
Project).
DI029197 Comment project end date
Comment on the end date of the project/program at the time of creation/update of the selected status report. The value is transferred from the
DI of the same name in the current planning (DT461
Project).
DI029198 Comment costs
Comment on the costs of the project/program at the time of creation/update of the selected status report. The value is transferred from the
DI of the same name in the current planning (DT461
Project).
DI029199 Comment effort
Comment on the effort of the project/program at the time of creation/update of the selected status report. The value is transferred from the
DI of the same name in the current planning (DT461
Project).
From DB 39.5.7
DI029200 Comment project/MMS end dates
Comment on the end dates of the project/program and the master milestones at the time of creation/update of the selected status report. The value is transferred from the
DI of the same name in the current planning (DT461
Project).
Up to DB 39.5.7
DI029200 Comment milestones
Comment on the master milestone dates of the project at the time of creation/update of the selected status report. The value is transferred from the
DI of the same name in the current planning (DT461
Project).
DI029201 Comment quality
Comment on the total status of the project/program at the time of creation/update of the selected status report. The value is transferred from the
DI of the same name in the current planning (DT461
Project).
DI061349 Comment risks/opportunities
Comment on the risks/opportunities of the project/program at the time of creation/update of the selected status report. The value is transferred from the
DI of the same name in the current planning (DT461
Project).
DI029208 OLE cost estimate
Symbol visualizing the estimate of the project/program costs by the project/program manager at the time of creation/update of the selected status report. The symbol references the value of the
Cost estimate parameter.
DI029209 OLE effort estimate
Symbol visualizing the estimate of the project/program effort by the project/program manager at the time of creation/update of the selected status report. The symbol references the value of the
Effort estimate parameter.
DI029210 OLE estimate project end date
Symbol visualizing the estimate of the project/program end date by the project/program manager at the time of creation/update of the selected status report. The symbol references the value of the
Project end date estimate parameter.
From DB 39.5.7
DI029211 OLE estimate project/MMS end dates
Symbol visualizing the estimate of the project/program end dates and master milestones by the project/program manager at the time of creation/update of the selected status report. The symbol references the value of the
Project/MMS end date estimate parameter.
Up to DB 39.5.7
DI029211 OLE milestones estimate
Symbol visualizing the estimate of the master milestones by the project manager at the time of creation/update of the selected status report. The symbol references the value of the
Milestone estimate parameter.
DI029212 OLE quality estimate
Symbol visualizing the estimate of the quality of the project/program costs by the project/program manager at the time of creation/update of the selected status report. The symbol references the value of the
Estimate quality parameter.
DI061352 OLE risks/opportunities estimate
Symbol visualizing the estimate of the risks/opportunities of the project/program by the project/program manager at the time of creation/update of the selected status report. The symbol references the value of the
Estimate risks/opportunities parameter.
From DB 39.5.7
DI029828 Deviation project end dates: calc. end - requested end (active SR)
Deviation of the calculated end date from the requested end date of the project (program) from the status report that was active at the time of creation of the selected status report. Upon creation/update of the status report, the value is copied from the
Deviation project end dates: calc. end - requested end parameter of the status report active at that time.
Up to DB 39.5.7
DI029828 End deviation (previous report)
Deviation of the calculated end date from the requested end date of the project (program) from the status report that was active at the time of creation of the selected status report. Upon creation/update of the status report, the value is copied from the
008711 parameter of the status report active at that time.
From DB 39.5.7
DI029829 Deviation MMS end dates: calc. end - requested end (active SR)
Deviation of the calculated end date from the requested end date of the master milestones (the highest value from all master milestones) from the status report that was active at the time of creation of the selected status report. Upon creation/update of the status report, the value is copied from the
Deviation MMS end dates: calc. end - requested end parameter of the status report active at that time.
Up to DB 39.5.7
DI029829 Milestones deviation (previous report)
Deviation of the calculated end date from the requested end date of the master milestones (the highest value from all master milestones) from the status report that was active at the time of creation of the selected status report. Upon creation/update of the status report, the value is copied from the
Deviation MMS end dates: calc. end - requested end parameter of the status report that was active at that time.
From DB 39.5.7
DI029830 % deviation effort: total - budget (active SR)
Percentage deviation of the total effort from the effort budget from the status report that was active at the time of creation of this status report. Upon creation/update of the status report, the value is copied from the
% deviation effort: total - budget parameter of the status report that was active at that time.
Up to DB 39.5.7
DI029830 Effort deviation (previous report)
Percentage deviation of the total effort from the effort budget from the status report that was active at the time of creation of this status report. Upon creation/update of the status report, the value is copied from the
% deviation effort: total - budget parameter of the status report that was active at that time.
From DB 39.5.7
DI029836 % deviation costs: total - budget (active SR)
Percentage deviation of the total costs from the cost budget from the status report that was active at the time of creation of this status report. Upon creation/update of the status report, the value is copied from the
% deviation costs: total - budget parameter of the status report that was active at that time.
Up to DB 39.5.7
DI029836 Total costs deviation (previous report)
Percentage deviation of the total costs from the cost budget from the status report that was active at the time of creation of this status report. Upon creation/update of the status report, the value is copied from the
% deviation costs: total - budget parameter of the status report that was active at that time.
From DB 39.5.7
DI029844 OLE trend effort deviation (SR vs. active SR)
Symbol for the visualization of the trend of the effort deviation values (
Total effort from
Effort budget) of the selected status report (
% deviation total effort budget) compared to the status report that was active at the time of creation of this report (
% deviation effort: total - budget (active SR))
Meaning
- Arrow up: negative trend
- Arrow down: positive trend
- Arrow to the right: no change to the values
Up to DB 39.5.7
DI029844 OLE effort comparison
Symbol for the visualization of the trend of the effort deviation values (
Total effort vs.
Effort budget) of the selected status report (
% deviation total effort budget) compared to the status report that was active at the time of creation of this report (
Active SR: % budget-total effort deviation)
Meaning
- Arrow up: negative trend
- Arrow down: positive trend.
Up to DB 39.5.7
DI029845 OLE master milestones comparison
Symbol for the visualization of the deviation values of the master milestones (master milestone trend) between the selected status report
and the status report that was active at the time of creation of this report
Meaning
- Arrow up: negative trend
- Arrow down: positive trend
From DB 39.5.7
DI029851 OLE trend cost deviation (SR vs. active SR)
Symbol for the visualization of the trend of the cost deviation values of the selected status report (
% deviation costs: total - budget) compared to the deviation value of the status report that was active at the time of creation of this status report (
% deviation costs: total - budget (active SR))
Meaning
- Arrow up: negative trend
- Arrow down: positive trend
- Arrow to the right: no change to the values
Up to DB 39.5.7
DI029851 OLE costs comparison
Symbol for the visualization of the trend of the cost deviation values of the selected status report (
% deviation costs: total - budget) compared to the deviation value of the status report that was active at the time of creation of this status report (
% deviation costs: total - budget (active SR))
Meaning
- Arrow up: negative trend
- Arrow down: positive trend
- Arrow to the right: no change to the values
From DB 39.5.7
DI029866 % deviation costs: total - budget (baseline)
Percentage deviation of the total costs from the cost budget from the status report that was active at the time of creation of this status report. Upon creation/update of the status report, the value is copied from the
% deviation costs: total - budget parameter of the
baseline that was active at that time.
Up to DB 39.5.7
DI029866 Baseline: cost deviation
Percentage deviation of the total costs from the cost budget from the status report that was active at the time of creation of this status report. Upon creation/update of the status report, the value is copied from the
% deviation costs: total - budget parameter of the
baseline that was active at that time.
From DB 39.5.7
DI029882 % deviation effort: total - budget (baseline)
Percentage deviation of the total effort from the effort budget from the status report that was active at the time of creation of this status report. Upon creation/update of the status report, the value is copied from the
% deviation effort: total - budget parameter of the
baseline that was active at that time.
Up to DB 39.5.7
DI029882 Baseline: effort deviation
Percentage deviation of the total effort from the effort budget from the status report that was active at the time of creation of this status report. Upon creation/update of the status report, the value is copied from the
% deviation effort: total - budget parameter of the
baseline that was active at that time.
From DB 39.5.7
DI029883 Deviation project end dates: calc. end - requested end (baseline)
Deviation of the calculated end date from the requested end date of the project (program) from the status report that was active at the time of creation of the selected status report. Upon creation/update of the status report, the value is copied from the
Deviation project end dates: calc. end - requested end parameter of the
baseline that was active at that time.
Up to DB 39.5.7
DI029883 Baseline: end deviation
Deviation of the calculated end date from the requested end date of the project (program) from the status report that was active at the time of creation of the selected status report. Upon creation/update of the status report, the value is copied from the
Deviation project end dates: calc. end - requested end parameter of the
baseline that was active at that time.
From DB 39.5.7
DI029884 Deviation MMS end dates: calc. end - requested end (baseline)
Deviation of the calculated end date from the requested end date of the master milestones (the highest value from all master milestones) from the status report that was active at the time of creation of the selected status report. Upon creation/update of the status report, the value is copied from the
Deviation MMS end dates: calc. end - requested end parameter of the
baseline that was active at that time.
Up to DB 39.5.7
DI029884 Baseline: milestone delay
Deviation of the calculated end date from the requested end date of the master milestones (the highest value from all master milestones) from the status report that was active at the time of creation of the selected status report. Upon creation/update of the status report, the value is copied from the
Deviation MMS end dates: calc. end - requested end parameter of the
baseline that was active at that time.
DI034409 Main project/report
DI040775 Measures
Measures of the project (program) at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the
DI of the same name in the current planning (DT461
Project).
DI040776 Decisions
Measures referring to the project (program) at the time of creation/update of the selected status report. The value is transferred when creating/updating the status report from the
DI of the same name in the current planning (DT461
Project).
DI040830 Main project
ID of the main project
DI040997 HDI: baseline, active, previous
Help DI for selecting the data from the active baseline from the active status report and the status report that was active before the currently active status report
DI056898 Total duration
Total duration of the project (program) at the time of creation/update of the selected status report. The value is calculated as a sum of the values frozen in the selected status report
Actual duration and
Remaining duration.
DI056971 Status Month (period)
Time period (month) to which the status report applies
DI056972 % actual costs to planned costs
Percentage relation of
Actual costs to
Planned costs of the project (program) in the selected status report
DI056973 % actual costs to the cost budget
Percentage relation of
Actual costs to
Cost budget of the project (program) in the selected status report
DI056974 % actual costs to total costs
Percentage relation of
Actual costs to
Total costs of the project (program) in the selected status report
DI056977 Report status
Current status of the report
DI056997 % actual effort to planned effort
Percentage relation of
Actual effort to
Planned effort of the project (program) in the selected status report
DI056998 % actual effort to effort budget
Percentage relation of
Actual effort to
Effort budget of the project (program) in the selected status report
DI056999 % actual effort to total effort
Percentage relation of
Actual effort to
Total effort of the project (program) in the selected status report
DI057531 Project
Functional ID of the project. It is generated automatically (copied from the
technical project ID). Unlike the technical
Project ID, the functional ID can be changed manually afterwards if necessary.
DI057563 TDI: 1 (Number)
From DB 39.5.7
DI057723 Total costs (current)
Total costs (actual+remaining) from the current planning. The value is transferred from the
Total costs from the current planning (DT461
Project).
Up to DB 39.5.7
DI057723 Total costs complete
Total costs (actual+remaining) from the current planning. The value is transferred from the
Total costs from the current planning (DT461
Project).
From DB 39.5.7
DI057724 Total revenues (current)
Total revenues (actual+remaining) from the current planning. The value is transferred from the
Total revenues parameter from the current planning (DT461
Project).
Up to DB 39.5.7
DI057724 Total revenues complete
Total revenues (actual+remaining) from the current planning
DI057725 Cost budget (current)
Cost budget from the current planning. The value is transferred from the
Cost budget parameter from the current planning (DT461
Project).
From DB 39.5.7
DI057726 Cost budget deviation: SR - current
Deviation between the cost budget value frozen in the selected status report and the cost budget value from the current planning
Calculation
Up to DB 39.5.7
DI057726 Delta cost budget
Deviation between the cost budget value frozen in the selected status report and the cost budget value from the current planning
Calculation
From DB 39.5.7
DI057727 Deviation total costs: SR - current
Deviation between the total costs value frozen in the selected status report and the total costs value from the current planning
Calculation
Up to DB 39.5.7
DI057727 Delta total costs
Deviation between the total costs value frozen in the selected status report and the total costs value from the current planning
Calculation
From DB 39.5.7
DI057728 Deviation total revenues: SR - current
Deviation between the total revenues value frozen in the selected status report and the total revenues value from the current planning
Calculation
Up to DB 39.5.7
DI057728 Delta total revenues
Deviation between the total revenues value frozen in the selected status report and the total revenues value from the current planning
Calculation
From DB 39.5.7
DI057977 Possible gross profit
Possible gross profit of the selected project and all of its subprojects at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
Up to DB 39.5.7
DI057977 Possible gross profit summarized
Possible gross profit of the selected project and all of its subprojects at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
From DB 39.5.7
DI029620 Probable gross profit
Probable gross profit of the project and all of its subprojects at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
Up to DB 39.5.7
DI029620 Probable gross profit summarized
At the time of creation/update of the selected status report, the probable gross profit is summarized from all project opportunities for which the
Active checkbox is activated in the
Risks/Opportunities module. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
From DB 39.5.7
DI029621 Actual gross profit summarized
Actual gross profit of the project and all of its subprojects at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
Up to DB 39.5.7
DI029621 Actual gross profit summarized
At the time of creation/update of the selected status report, the actual gross profit from all opportunities of the project for which the
Active checkbox in the
Risks/Opportunities module was activated is summarized in the respective modules. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
From DB 39.5.7
DI057975 Possible damage
Possible damage of the selected project and all of its subprojects at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
Up to DB 39.5.7
DI057975 Possible damage summarized
Summarized possible damage. The damage is summarized from all project risks for which the
Active checkbox is activated in the
Risks/Opportunities module. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
From DB 39.5.7
DI028291 Probable damage
Probable damage of the selected project and all of its subprojects at the time of creation/update of the status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
Up to DB 39.5.7
DI028291 Probable damage summarized
At the time of creation/update of the selected status report, the probable damage from all risks of the project for which the
Active checkbox in the
Risks/Opportunities module was activated is summarized in the respective modules. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
From DB 39.5.7
DI028292 Actual damage
Actual damage of the selected project and all of its subprojects at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
Up to DB 39.5.7
DI028292 Actual damage summarized
At the time of creation/update of the selected status report, the actual damage from all risks of the project for which the
Active checkbox in the
Risks/Opportunities module was activated is summarized in the respective modules. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
New from DB 39.5.7
DI063803 Possible damage (without subprojects)
Possible damage of the project without considering its possibly existing subprojects at the time of status report creation/update. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
DI063804 Probable damage (without subprojects)
Probable damage of the project without considering its possibly existing subprojects at the time of status report creation/update. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
DI063805 Actual damage (without Subprojects)
Actual damage of the project without considering its possibly existing subprojects at the time of status report creation/update. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
DI063806 Possible gross profit (without subprojects)
Possible gross profit of the project without considering its possibly existing subprojects at the time of status report creation/update. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
DI063807 Probable gross profit (without subprojects)
Probable gross profit of the project without considering its possibly existing subprojects at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
DI063808 Actual gross profit (without subprojects)
Actual gross profit of the project without considering its possibly existing subprojects at the time of status report creation/update. Upon creation/update of the status report, the value is copied from the
DI of the same name in the current planning (DT461
Project).
DI058030 Deviation project end dates: requested end - calc. end (text)
Absolute deviation of the calculated end date from the requested end date of the project (program) with text specification (delay/float) at the time of creation/update of the selected status report. The value is copied from the
Deviation project end date requested end - calc. end.
DI058031 Deviation MMS end dates: requested end - calc. end (text)
Deviation of the calculated end date from the requested end date of the master milestones (the highest value from all master milestones) with text specification (delay/float) at the time of creation of the selected status report. The value is copied from the
Deviation MMS end dates requested end - calc. end.
DI059238 Objectives
Objectives of the project (program) at the time of creation/update of the selected status report. The value is copied from the
DI of the same name in the current planning (DT461
Project).
DI059239 Scope and limit
Scope and limit of the project (program) at the time of creation/update of the selected status report. The value is copied from the
DI of the same name in the current planning (DT461
Project).
DI059240 Conseq. non-realization
Consequences in case of a non realization of the project (program) defined at the time of creation/update of the status report The value is copied from the
DI of the same name in the current planning (DT461
Project).
DI059241 Areas involved
The departments, persons, etc. involved in the project (program) at the time of creation/update of the status report Upon creation/update of the status report, the value is copied from the
DI of the same name from the current planning (DT461
Project).
DI059242 Mandatory
Parameter with the help of which a project (program) is marked as a mandatory project (mandatory program). Upon creation/update of the status report, the value is copied from the
DI of the same name from the current planning (DT461
Project).
Notes
- The parameter is meant to be a selection help for the portfolio manager for the creation of the portfolio. Mandatory projects must be realized, even if other projects appear to be more worthwhile, e.g. projects for complying with statutory requirements.
- The parameter has no technical influence on the system.
DI059243 Mandatory: reason
Reason for the activation of the checkbox in the
Mandatory field at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name from the current planning (DT461
Project).
DI059245 ROI
Return on investment value of the project (program) at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name from the current planning (DT461
Project).
DI059246 Description
Description of the project (program) at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name from the current planning (DT461
Project).
DI059247 Internal interest
The internal interest entered in the project (program) at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name from the current planning (DT461
Project).
DI059248 Area
ID of the
Area parameter of the project (program) at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name from the current planning (DT461
Project).
DI059249 Break Even
Break even code of the project (program) at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name from the current planning (DT461
Project).
DI059250 Gross profit probability
Gross profit probability of the project (program) at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name from the current planning (DT461
Project).
From DB 39.5.7
DI059251 NPV (without subprojects)
Net present value (net capital value of the project without considering its possibly existing subprojects) at the time of status report creation/update. Upon creation/update of the status report, the value is copied from the
DI of the same name from the current planning (DT461
Project). For further info on net present value, see
here.
NEW The value is automatically calculated (Python value range) taking different parameters like costs, revenues, internal interest, etc. into account.
Formula
- The calculation is done in accordance with the standard formula
- C0 Capital value with regard to t=0
- i calculation interest rate (=internal interest, e.g. 5%)
- N processing period
- CFt Cashflow (source: Wikipedia)
- In PLANTA, the cashflow is calculated per year: CFt = revenues + benefit - costs
Parameters involved (status reports)
From DB 39.5.0
DI059251 NPV (without subprojects)
Net present value (net capital value of the project without considering its possibly existing subprojects) at the time of status report creation/update. Upon creation/update of the status report, the value is copied from the
DI of the same name from the current planning (DT461
Project). For further info on net present value, see
here.
From Release 39.5.0, the field is temporarily without function.
Up to DB 39.5.0
DI059251 NPV
Net present value (net capital value of the project without considering its possibly existing subprojects) at the time of status report creation/update. Upon creation/update of the status report, the value is copied from the
DI of the same name from the current planning (DT461
Project). For further info on net present value, see
here.
The value is copied from the field of the same name from DT461.
From DB 39.5.7
DI059244 NPV
Net present value (net capital value of the project without considering its possibly existing subprojects) at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name from the current planning (DT461
Project). For further info on net present value, see
here.
NEW The value is automatically calculated (Python value range) taking different parameters like costs, revenues, internal interest, etc. into account.
For the calculation formula and the parameters involved, see
NPV (without subprojects)
From DB 39.5.0
DI059244 NPV
Net present value (net capital value of the project without considering its possibly existing subprojects) at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name from the current planning (DT461
Project). For further info on net present value, see
here.
From Release 39.5.0, the field is temporarily without function.
Up to DB 39.5.0
DI059244 NPV
Net present value (net capital value of the project without considering its possibly existing subprojects) at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name from the current planning (DT461
Project). For further info on net present value, see
here.
DI059637 Calc. start (baseline)
Calculated start date of the project (program) from the baseline report. The value is copied from the
Calc. start parameter of the baseline report.
Note
- This field is hidden by default but can be displayed by the user if necessary.
DI059636 Calc. end (baseline)
Calculated end date of the project (program) from the baseline report. The value is copied from the
Calc. end parameter of the baseline report.
Note
- This field is hidden by default but can be displayed by the user if necessary.
DI059640 Bar: actual start - work reporting date
Bar for the visualization of the interval between the actual start date and the latest work reporting date of the project (program) in the selected status report
DI059638 Bar: planned dates (calculated dates from baseline)
Bar for the visualization of the interval between the
calculated start date and
calculated end date of the project (program) from the baseline report (planned dates).
DI059627 Bars: calculated dates by code
Bar for the visualization of the interval between the
calculated start date and
calculated end date of the project (program). The color of the bar is determined by the code of the project (program).
DI059628 Bar: requested dates
Bar for the visualization of the interval between the
calculated start date and
requested end date of the project (program) in the selected status report.
DI059686 Cost trend analysis
Via this checkbox you can control whether the respective status report is considered in the cost, effort, risk, or opportunity trend analysis.
Values
- : the status report is considered.
- : the status report is not considered
From DB 39.5.7
DI063004 OLE deviation project/MMS end date: calc. end - requested end
Up to DB 39.5.7
DI063004 OLE deviation dates small traffic light
Traffic light for the visualization of the deviation of the dates at the time of creation of this status report
DI059232 Frozen risk value
Percentage value of the calculated risk value of the planning object at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name from the current planning (DT461
Project).
DI059234 Frozen objective contribution
Percentage value of the calculated objective contribution of the planning object at the time of creation/update of the selected status report. Upon creation/update of the status report, the value is copied from the
DI of the same name from the current planning (DT461
Project).
From DB 39.5.7
DI063795 Deviation project end dates: calc. end - requested end (active SR)
Deviation of the calculated end date from the requested end date of the project (program) from the status report that was active at the time of creation of the selected status report with text specification (delay/float). Upon creation/update of the status report, the value is copied from the
Deviation project end dates: calc. end - requested end parameter of the status report active at that time.
DI063796 Deviation MMS end dates: calc. end - requested end (active SR)
Deviation of the calculated end date from the requested end date of the master milestones (the highest value from all master milestones) from the status report that was active at the time of creation of the selected status report with text specification (delay/float). Upon creation/update of the status report, the value is copied from the
Deviation MMS end dates: calc. end - requested end parameter of the status report active at that time.
DI062316 OLE revenues/benefit estimate
New from DB 39.5.10
DI064519 Simulation report
Code which is set for status reports which
are created exclusively for simulation
DI064560 Opportunity green
Number of opportunities in the green range
DI064561 Opportunity yellow
Number of opportunities in the yellow range
DI064562 Opportunity red
Number of opportunities in the red range
DI064563 Risk red
Number of risks in the red range
DI064564 Risk yellow
Number of risks in the yellow range
DI064565 Risk green
Number of risks in the green range
DIs no longer used from DB 39.5.0
The DIs listed below are no longer used from DB version 39.5.0.
DI057979 Structure summarization: approved budget
Summarized budget values from the subprojects.
DI057985 Structure summarization: effort budget
Summarized effort from all subprojects.
DI057998 Entire structure: effort budget
Summarized effort from the parent project and the subprojects
DI057999 Entire structure: Approved budget
Summarized values from the subprojects and the cost budget.
Calculation
DI057976 Probability (damage) summarized
Probability of occurrence of the summarized damage in percent.
DI057978 Probability (gross profit) summarized
Probability of occurrence of the summarized gross profit in percent.
DI028509 Cost budget: internal personnel
Budget costs of the Internal personnel cost type group
Details
- Costs result from the multiplication of resource efforts with the conversion factors.
DI028513 Total costs: internal personnel
Total costs of the Internal personnel Cost Type Group
Details
DI028514 Cost budget: external personnel
Budget costs of the External personnel cost type group
Details
DI028518 Total costs: external personnel
Total costs of the External personnel cost type group
Details
DI028519 Cost budget: material costs
Budget costs of the Material costs Cost Type Group
Details
DI028523 Total costs: material costs
Total costs of the Material costs cost type group
Details
DI028524 Cost budget: investments
Budget costs of the Investments cost type group
Details
DI028528 Total costs: investments
Total costs of the Investments cost type group
Details
DI028529 Cost budget: miscellaneous
Budget costs of the Miscellaneous cost type group
Details
DI028533 Total costs: miscellaneous
Total costs of the Miscellaneous cost type group
Details
DI028542 % external personnel deviation
Percentage deviation of the cost budget from the total costs for the External personnel cost type group
DI028543 % material costs deviation
Percentage deviation of total costs from the cost budget for the Material costs cost type group
DI028544 % investments deviation
Percentage deviation of the cost budget from the total costs for the Investments cost type group
DI028545 % miscellaneous deviation
Absolute deviation of the cost budget from the total costs for the Miscellaneous cost type group
DI028546 % internal personnel deviation
Percentage deviation of the cost budget from the total costs for the Internal personnel cost type group
DI028548 OLE miscellaneous
OLE symbol for the Miscellaneous cost type group.
DI028549 OLE investments
OLE symbol for the Investments cost type group
DI028550 OLE material costs
OLE symbol for the Material costs cost type group
DI028551 OLE external personnel
OLE symbol for the External personnel cost type group
DI028552 OLE Personal intern
OLE symbol for the External personnel cost type group
DI057691 Planned effort: external
Planned effort for the External resource type
DI057692 Actual effort: external
Actual effort for the External resource type
DI057693 Remaining effort: external
Remaining effort for the External resource type
DI057694 Total effort: external
Total effort for the External resource type
DI057695 Total effort: internal
Total effort for the Internal resource type
DI057696 Remaining effort: internal
Remaining effort for the Internal resource type
DI057697 Actual effort: internal
Actual effort for the Internal resource type
DI057698 Planned effort: internal
Planned effort for the Internal resource type
DI057980 Structure summarization: budget miscellaneous
Summarized budget values from subprojects of the Miscellaneous cost type group
DI057981 Structure summarization: budget investments
Summarized budget values from the subprojects of the Investments cost type group
DI057982 Structure summarization: budget material costs
Summarized budget values from the subprojects of the Investments cost type group
DI057983 Structure summarization: budget external personnel
Budget values of the External personnel cost type group summarized from subprojects
DI057984 Structure summarization: budget internal personnel
Budget values of the External personnel cost type group summarized from subprojects
DI058000 Total structure: budget miscellaneous
Values summarized from parent and subprojects of the Miscellaneous cost type group
Calculation
DI058001 Total structure: budget investments
Values summarized from parent and subprojects of the Investments cost type group
Calculation
DI058002 Total structure: budget material costs
Values summarized from parent and subprojects of the Material costs cost type group
Calculation
DI058003 Total structure: budget external personnel
Values summarized from parent and subprojects of the External personnel cost type group
Calculation
DI058004 Total structure: budget internal personnel
Values summarized from parent and subprojects of the Internal personnel cost type group
Calculation
DI058954 Total costs - budget deviation: internal personnel
Absolute deviation of total costs from the cost budget in the Internal personnel cost type group
Calculation
DI058955 Total costs - budget deviation: external personnel
Absolute deviation of total costs from the cost budget in the External personnel cost type group
Calculation
DI058956 Total costs - budget deviation: investments
Absolute deviation of total costs from the cost budget in the Investments cost type group
Calculation
DI058957 Total costs - budget deviation: miscellaneous
Absolute deviation of total costs from the cost budget in the Miscellaneous cost type group
Calculation
DI058958 Total costs - budget deviation: material costs
Absolute deviation of total costs from the cost budget in the Material costs cost type group
Calculation