Base | Only tasks the deviation values of which are > 0 or NEW < 0 (indicated by red, yellow, or green traffic lights) are displayed. Tasks are displayed grouped by three criteria: end date, costs, and effort. In every grouping area, only data of the respective grouping criterion is displayed for each task. |
All end dates | All tasks of the project are displayed with end date values. |
All effort data | All tasks of the project are displayed with effort values. |
All cost data | All tasks of the project are displayed with cost values. |
Base | Only tasks the deviation values of which are > 0 (indicated by red or yellow traffic lights) are displayed. Tasks are displayed grouped by three criteria: end date, costs, and effort. In every grouping area, only data of the respective grouping criterion is displayed for each task. |
All end dates | All tasks of the project are displayed with end date values. |
All effort data | All tasks of the project are displayed with effort values. |
All cost data | All tasks of the project are displayed with cost values. |
ProjectTaskFrom DB 39.5.14
Symbol Meaning Color Comment Requested dates Requested start and Requested end are defined in the Key dates area in the corresponding core data sheet (Project Core Data, Idea Core Data, Proposal Core Data, Program Core Data).
Calculated dates The color of the bar is determined by the code of the planning object.
Code A
Code B
Code C
Code D
Code ECalc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item.
In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.Actual dates The bar is white hatched. The background color depends on the Code of the planning object. Actual start and Actual end (if there is any, otherwise Latest time recording date) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) when calculating the schedule of the respective planning object. Float Float is available if the calculated end date (Calc. end) of the planning object is earlier than the requested end date (Requested end).
Date delay A date delay occurs if the calculated end date (Calc. end) of the planning horizon is later than the requested end date (Requested end).
The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades.
Calculated dates from status report Calc. start and Calc. end of the planning object from the selected status report. From DB 39.5.13
Symbol Meaning Color Comment Requested dates Requested start and Requested end are defined in the Key dates area in the corresponding core data sheet (Project Core Data, Idea Core Data, Program Core Data).
Calculated dates The color of the bar is determined by the code of the planning object.
Code A
Code B
Code C
Code D
Code ECalc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item.
In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.Actual dates Actual start and Actual end (if there is any, otherwise Latest time recording date) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) when calculating the schedule of the respective planning object. Float Float is available if the calculated end date (Calc. end) of the planning object is earlier than the requested end date (Requested end).
Date delay A date delay occurs if the calculated end date (Calc. end) of the planning horizon is later than the requested end date (Requested end).
The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades.
Calculated dates from status report Calc. start and Calc. end of the planning object from the selected status report. From DB 39.5.12
Symbol Meaning Color Comment Requested dates Requested start and Requested end are defined in the Key dates area in the corresponding core data sheet (Project Core Data, Idea Core Data, Program Core Data).
Calculated dates The color of the bar is determined by the code of the planning object.
Code A
Code B
Code C
Code D
Code ECalc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item.
In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.Actual dates Actual start and Actual end (if there is any, otherwise Latest time recording date) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) when calculating the schedule of the respective planning object. Float Float is available if the calculated end date (Calc. end) of the planning object is earlier than the requested end date (Requested end).
Date delay A date delay occurs if the calculated end date (Calc. end) of the planning horizon is later than the requested end date (Requested end).
The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades.
Calculated dates from status report The color of the bar equates to that of the project code (see the legend above), however, it is slightly lighter. Calc. start and Calc. end of the planning object from the selected status report. From DB 39.5.7
Symbol Meaning Color Comment
Calculated dates The bar color is defined by the code of the planning object.
Code A
Code B
Code C
Code D
Code ECalc. start and Calc. end of a planning object are determined in the calculation of the schedule of the respective planning object.
In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.Actual dates Actual start and Actual end (if there is any, otherwise Latest time recording date) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) when calculating the schedule of the respective planning object. Float Float is available if the calculated end date (Calc. end) of the planning object is earlier than the requested end date (Requested end).
Date delay A date delay occurs if the calculated end date (Calc. end) of the planning horizon is later than the requested end date (Requested end).
The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades.
Calculated dates from status report Calc. start and Calc. end of the planning object from the selected status report. Up to DB 39.5.7
Symbol Meaning Color Comment
Calculated dates The bar color is defined by the code of the planning object.
Code A
Code B
Code C
Code D
Code ECalc. start and Calc. end of a planning object are determined in the calculation of the schedule of the respective planning object.
In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.Actual dates Actual start and Actual end (if there is any, otherwise Latest time recording date) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) when calculating the schedule of the respective planning object. Calculated dates from status report Calc. start and Calc. end of the planning object from the selected status report. From DB 39.5.14
Symbol Meaning Color Comment Task requested dates Requested start and Requested end of a task can be defined in the corresponding data fields in the Schedule module or they can be entered directly and graphically in the Gantt chart. Calculated dates of the tasks Uncritical
CriticalCalc. start and Calc. end are calculated by clicking on the calculation button or by selecting the respective menu item.
Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can be critical as well./ Milestones/
Master milestones/ Without delay
/ With delay
/ With actual endWithout delay means: Total float 0 With delay means: Total float < 0 Calculated dates of the summary tasks A summary task is a task in the structured schedule which consists of subtasks and summarizes them. Information on the summary task, such as duration and dates, is determined automatically from the sub-tasks. Calculated dates of the tasks from status report Calculated dates of the tasks from status report Calc. start and Calc. end of the tasks from the selected status report. / Milestones/master milestones of the tasks from the status report Calculated dates of the summary tasks from status report Calc. start and Calc. end of the summary tasks from the selected status report. From DB 39.5.13
Symbol Meaning Color Comment Task requested dates Requested start and Requested end of a task can be defined in the corresponding data fields in the Schedule module or they can be entered directly and graphically in the Gantt chart. Calculated dates of the tasks Uncritical
CriticalCalc. start and Calc. end are calculated by clicking on the calculation button or by selecting the respective menu item.
Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can be critical as well./ Milestones/
Master milestones/ Without delay
/ With delay
/ With actual endWithout delay means: Total float 0 With delay means: Total float < 0 Calculated dates of the summary tasks A summary task is a task in the structured schedule which consists of subtasks and summarizes them. Information on the summary task, such as duration and dates, is determined automatically from the sub-tasks. Calculated dates of the tasks from status report Calculated dates of the tasks from status report Calc. start and Calc. end of the tasks from the selected status report. / Milestones/master milestones of the tasks from the status report Calculated dates of the summary tasks from status report Calc. start and Calc. end of the summary tasks from the selected status report. From DB 39.5.12
Symbol Meaning Color Comment Task requested dates Requested start and Requested end of a task can be defined in the corresponding data fields in the Schedule module or they can be entered directly and graphically in the Gantt chart. Calculated dates of the tasks Uncritical
CriticalCalc. start and Calc. end are calculated by clicking on the calculation button or by selecting the respective menu item.
Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can be critical as well./ Milestones/
Master milestones/ Without delay
/ With delay
/ With actual endWithout delay means: Total float 0 With delay means: Total float < 0 Calculated dates of the summary tasks A summary task is a task in the structured schedule which consists of subtasks and summarizes them. Information on the summary task, such as duration and dates, is determined automatically from the sub-tasks. Calculated dates of the tasks from status report Uncritical
CriticalCalculated dates of the tasks from status report Calc. start and Calc. end of the tasks from the selected status report. / Milestones/master milestones of the tasks from status report / Without delay
/ With delay
Without delay means: Total float 0 With delay means: Total float < 0 Calculated dates of the summary tasks from status report Calc. start and Calc. end of the summary tasks from the selected status report. Up to DB 39.5.12
Symbol Meaning Color Comment Task requested dates Requested start and Requested end of a task can be defined in the corresponding data fields in the Schedule module or they can be entered directly and graphically in the Gantt chart. Calculated dates of the tasks Uncritical
CriticalCalc. start and Calc. end are calculated by clicking on the calculation button or by selecting the respective menu item.
Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical.Calculated dates of the summary tasks A summary task is a task in the structured schedule that consists of subtasks and summarizes them. Information on the summary task, such as duration and dates, is determined automatically from the sub-tasks. Calculated dates of the tasks from status report Calc. start and Calc. end of the tasks, the milestones, and the master milestones from the selected status report. Calculated dates of summary tasks from status report Calc. start and Calc. end of the summary tasks from the selected status report
I | Attachment | History | Size | Date | Comment |
---|---|---|---|---|---|
png | KalkSB.PNG | r2 r1 | 0.3 K | 2015-06-15 - 11:40 | |
png | MMS_krit.PNG | r1 | 0.6 K | 2015-06-12 - 16:41 | |
png | MS.png | r1 | 0.6 K | 2015-06-12 - 16:40 | |
png | MS_erl.PNG | r1 | 0.6 K | 2015-06-12 - 16:41 | |
png | Milestone.PNG | r1 | 0.4 K | 2015-06-12 - 16:40 | |
png | Sammel.PNG | r1 | 0.3 K | 2015-06-12 - 16:39 | |
png | SammelVGSB.PNG | r1 | 0.3 K | 2015-06-15 - 11:13 | |
png | Unkritisch.png | r1 | 0.4 K | 2015-06-12 - 16:42 | |
png | VGKalk.png | r1 | 0.5 K | 2015-06-12 - 16:40 | |
png | Wunsch.png | r1 | 0.3 K | 2015-06-12 - 16:40 | |
png | kritisch.png | r1 | 0.3 K | 2015-06-12 - 16:42 |