Working with the Process Model (Tutorial) DB 39.5.14

Please note

  • The description in this topic applies to PLANTA project version DB 39.5.14.
  • The following table contains links to the other versions:

DB 39.5.15 go to the tutorial
DB 39.5.14 go to the tutorial
DB 39.5.13 go to the tutorial
DB 39.5.7 - DB 39.5.12 go to the tutorial
DB 39.5.0 - DB 39.5.6 go to the tutorial
< DB 39.5.0 but S 39.5.13 go to the tutorial
< DB 39.5.0 and < S 39.5.13 go to the tutorial
  go to further tutorials

Introduction

Information
  • Beside the conventional way of project planning, PLANTA project enables you to plan and control projects in a process-oriented way.

Objective

  • This workflow is supposed to teach users how to work with process models in the PLANTA software.

Notes

  • All exercises are based on the PLANTA demo data. This data must be installed beforehand.
  • Master data such as process models, resources, users, etc. has already been set up in the demo data. This tutorial does not cover how the master data is defined. (For this, see Master Data Entry). It is merely about describing procedures like the planning procedure or the creation of a new project according to one of the models available.
    • The current demo data does not include an English process model. You will be working with a German model, but translations will be given within brackets after each process step.
  • A technical guide about how to create and control projects with the PLANTA software can be found in the Project Workflow as well as in the description of individual user modules in case of planning objects such as ideas, plans or requests.
  • It is recommendable to have carried out the Project Workflow before the process model workflow.
  • The screenshots used are merely examples of functions. The screenshot layout may deviate from the program.

Activate Process Models (R41)

Task

  • The multi-project manager, Mr. Hart, has just created the new project PR-01 and he has appointed Ronja Koch (R8) as the project manager.
  • To plan and control the new project, Mr. Hart would like to apply the DIN69901/1-5 process model.

Procedure

  • Start the client.
  • Log on with user R41.
  • Create a new project.
  • Enter PR-01 for the project name.
  • Appoint Ronja Koch as a project manager (manager).
  • Deactivate the Locked checkbox in the Attributes/Parameters area.
  • Save.
  • The message Would you like to delete the current stakeholder assignment of the manager or would you like to assign the new manager additionally? appears.
  • Select No in order to keep Georg Hart as stakeholder.
  • Click on the Process status tab at the bottom of the panel in order to open the module of the same name.
  • From the Process model listbox select the DIN69901/1-5 process model.
  • Activate the Activate model button.
    • All phases of the model are loaded along with the process steps belonging to it.
      • the first phase is opened under the In process category; the individual process steps are immediately visible.
      • All other phases are displayed under the Future phases category, the individual process steps are invisible.
    • The process bar at the bottom of the module is loaded.
prozessworkflow1EN.png

Edit Phase (R41)

Create Process Steps Manually

Task

  • For the phase Initialisierung ("Initialization") Mr. Hart wants to create the additional steps Define consequences of non-realization and Clarify external commission.

Information

  • New process steps can be inserted manually in the existing model.
    • Project specific process steps: right-click on the process phase names Insert process step
    • Approval steps: via the context menu Create subordinated approval step
    • Process steps of the Submission class cannot be inserted manually.

Procedure

  • Right-click on the Initialisierung ("Initialization") process phase in the Process Status module and select the Insert process step context menu command. ( Project-specific process steps that were inserted manually are marked with "I").
  • Enter the name for the new process step in the line inserted in the Process step name field.
  • Use SHIFT and drag to move the new step below the step PM-Prozesse auswählen ("Select PM Processes").
  • Create the second individual process step.
prozessworkflow2EN.png

  • Save.

Delete Process Steps

Task

  • After consideration, Mr. Hart does not deem the process step Clarify external commission necessary anymore. He now wants to delete it.

Procedure

  • Right-click on the subordinated approval step in the Process status module.
  • Select the Delete Process Step context menu command.
prozessworkflow3EN.png

  • Confirm the message by clicking OK.
  • The process step has been deleted.
  • Save.
prozessworkflow4EN.png

Note

  • Standard process steps can only be deleted if the respective checkboxes have been activated in the Process Model Templates module.
    • If process steps must not be deleted, the The marked records could not be deleted due to process model configurations message is displayed

Deactivate Process Steps

Task

  • As Mr. Hart has already appointed the project manager for the project the Zuständigkeit klären ("Clarify responsibility") process step is no longer necessary. The PM processes have also been selected already, which is why the step PM-Prozesse auswählen ("Select PM Processes") is no longer needed either.
  • Mr. Hart wants to deactivate these steps.

Procedure

  • Activate the Not required checkbox next to the Clarify responsibility process step in the Process Status module.
  • The status of this process step is automatically set to Completed.
  • Do the same for the PM-Prozesse auswählen ("Select PM Processes") step.
prozessworkflow5EN.png

  • Save.
  • The process steps are now deactivated.

Note

  • Process steps copied from the process model template cannot be deleted. They can only be marked as Not required.

Define Person Responsible for Process Steps

Task
  • Mr. Hart now wants to define completion dates as well as a person responsible for every project-specific, submission, and approval process step (usually this is a manager or another person with modification rights).

Procedure

  • Select a resource in the Resource name field in the process step line.
  • Select completion dates for next week in the Date field.
    • Projekt beschreiben ("Describe Project"):
      • Person responsible: Ronja Koch (PM)
      • Date: 28.08.19
    • Ziele skizzieren ("Outline objectives"):
      • Person responsible: Ronja Koch (PM)
      • Date: 28.08.19
    • Define consquences of non-realization:
      • Person responsible: Ronja Koch (PM)
      • Date: 29.08.19
    • Abgabe ("Submission"):
      • Person responsible: Ronja Koch (PM)
      • Date: 29.08.19
    • Freigabe erteilen ("Give approval"):
      • Person responsible: Georg Hart (MPM) ( The logged-on user can only define himself/herself as the person responsible for approval when he/she is multi-project manager.)
      • Date: 30.08.19
    • Save.
prozessworkflow6EN.png

Edit Process Steps (R8)

Execute Process Steps

Task
  • Project manager Ronja Koch (R8) wants to execute the process steps for which she has been defined as the person responsible.

Procedure

  • Start the client.
  • Enter R8 for the project manager.
  • Ronja Koch can now see the process steps she is supposed to edit in the My Activities module of the Employee Board panel in the Process step name area.
    • In the date scale (window 2) the completion dates of the assigned process steps can be viewed.
      • To do so, move the cursor to the green circle next to the required process step. The completion date is displayed in a tooltip.
prozessworkflow7EN.png

  • First, Ronja Koch wants to edit the Projekt beschreiben ("Describe Project") process step.
    • Here, click on the link on the ID of the project.
      • The Project panel of the PR-01 project is opened with the Dashboard module.
      • Open the Process Status module.
      • Click on the Focus task button next to the Projekt beschreiben ("Describe Project") process step. (Alternatively, the task can be focused by the Focus task context menu command.)
        • This function is only available if the corresponding process rules have been defined in the Process Model Templates module. This only makes sense for process steps that need a defined data entry in the system in order to be completed.
prozessworkflow8EN.png

  • The linked module is opened and the field that needs to be edited is focused. In this case, the field Description in the Project Core Data module.
  • Ronja Koch can now describe the project.
prozessworkflow9EN.png

  • Save.
  • Ronja Koch has completed the Projekt beschreiben ("Describe Project") process step and changes the process step status in the Status field in the Process Status module from Pending to Completed.
  • Save.
  • Ronja Koch then completes the same steps for the Ziele skizzieren ("Outline objectives") process step.
prozessworkflow10EN.png

Notes

  • The process step status can also be changed in the Status field of the Process Step module, which can be opened by clicking on the Edit process step context menu command in the My Activities module.
prozessschrittbearbeitenEN.png

  • When a process step has the Completed status it is no longer displayed in the employee board of the corresponding employee.
  • Process steps are only really completed when the Submission step is done in the Process Status module.
  • The process step status of Submission and Approval classes cannot be changed manually. This happens automatically when the process step concerned is completed.

Task

  • Complete the Define consequences of non-realization process step in the same way.

Notes

  • The Define consequences of non-realization process step is an an individual process step which does not contain any focus to the appropriate editing module.
  • But Ronja Koch as an experienced PLANTA user knows in which module she has to edit data for this step.

Procedure

  • Ronja Koch opens the project panel of the PR-01 project,
  • activates the Project Core Data module and
  • fills the Conseq. non-realization field.
  • Then she sets the status of the process step to "Completed" like described above.

Submit Phase

Task
  • In the Process Status module Ronja Koch sees that all project-specific process steps of the Initialisierung ("Initialization") phase have the Completed status. Now she wants to submit the process steps of the Initialisierung ("Initialization") phase. To do this, she needs to complete the Abgabe ("Submit") process step.

Procedure

  • Click on the link on the Abgabe ("Submit") process step in the Process Status module.
prozessworkflow11EN.png

  • The query whether you want to write a comment is displayed.
    • Confirm the message with No.
  • If not all process steps have been completed, the Not all process steps are completed. message is output and the submission is not carried out. The status of the corresponding process step can be changed and returned to the person responsible for the process step.
  • After submission, the Send Info module is opened and an info can be sent.
    • The info text is inserted automatically.
    • Georg Hart is set as recipient by default.
    • Click on the Send button.
prozessworkflow12EN.png

  • After submission, completed process steps are listed in the Submitted phases category.
prozessworkflow13EN.png

Approve Phase (R41)

Task
  • The multi-project manager has checked the completed process steps and wants to approve the Initialisierung ("Initialization") phase.

Procedure

  • Log on with user R41.
  • Open the project and click on the approval step Freigabe erteilen ("Give approval") in the Process Status module.
  • A dialog message is displayed.
prozessworkflow14EN.png

  • Click on the Approve button.
  • By doing so, the process step status is automatically set to Accepted.
  • The Send Info module is opened and a message can be sent.
    • The info text is inserted automatically.
    • Ronja Koch is set as recipient by default.
    • Click on the Send button.
prozessworkflow15EN.png

  • The completed phase including its process steps is moved to the Completed phases category.
  • In the process bar, the name of the completed phase is marked grey and the name of the new phase is highlighted white.
  • The process steps of the next phase can be seen in the In process category.
prozessworkflow16EN.png

  • The progress from one phase to the next is thus completed.
Topic attachments
I Attachment History Size Date Comment
Pngpng prozessschrittbearbeitenEN.png r1 6.2 K 2019-08-23 - 14:01  
Pngpng prozessworkflow10EN.png r1 21.1 K 2019-08-23 - 14:01  
Pngpng prozessworkflow11EN.png r1 21.3 K 2019-08-23 - 14:01  
Pngpng prozessworkflow12EN.png r1 5.4 K 2019-08-23 - 14:00  
Pngpng prozessworkflow13EN.png r1 19.3 K 2019-08-23 - 14:00  
Pngpng prozessworkflow14EN.png r1 4.6 K 2019-08-23 - 14:00  
Pngpng prozessworkflow15EN.png r1 5.1 K 2019-08-23 - 14:00  
Pngpng prozessworkflow16EN.png r1 46.7 K 2019-08-23 - 14:00  
Pngpng prozessworkflow1EN.png r1 55.7 K 2019-08-23 - 14:02  
Pngpng prozessworkflow2EN.png r1 19.3 K 2019-08-23 - 14:01  
Pngpng prozessworkflow3EN.png r1 22.8 K 2019-08-23 - 14:01  
Pngpng prozessworkflow4EN.png r1 19.0 K 2019-08-23 - 14:01  
Pngpng prozessworkflow5EN.png r1 19.6 K 2019-08-23 - 14:01  
Pngpng prozessworkflow6EN.png r1 22.6 K 2019-08-23 - 14:01  
Pngpng prozessworkflow7EN.png r1 53.9 K 2019-08-23 - 14:01  
Pngpng prozessworkflow8EN.png r1 22.0 K 2019-08-23 - 14:01  
Pngpng prozessworkflow9EN.png r1 46.2 K 2019-08-23 - 14:01  

         PLANTA project









 
  • Suche in Topic-Namen

  • Suche in Topic-Inhalten
This site is powered by the TWiki collaboration platform Powered by Perl