Legend barsLegend utilizationFrom DB 39.5.14
Symbol Meaning Color Comment Calculated dates of the resource for the selected task in the selected project The color of the bar is determined by the code of the corresponding project. Code A
Code B
Code C
Code D
Code ECalc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. Actual dates of the selected resource for the selected task in the selected project The bar is white hatched. Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the reported hours worked of the corresponding resource (DT472) or are edited manually. Date of tasks, risks and opportunity measures and process steps The date value for the bar is calculated: From DB 39.5.12
Symbol Meaning Color Comment Calculated dates of the resource for the selected task in the selected project The color of the bar is determined by the code of the corresponding project. Code A
Code B
Code C
Code D
Code ECalc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. Actual dates of the selected resource for the selected task in the selected project Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the reported hours worked of the corresponding resource (DT472) or are edited manually. Date of tasks, risks and opportunity measures and process steps The date value for the bar is calculated: Up to DB 39.5.12
Symbol Meaning Color Comment Calculated dates of the resource for the selected task in the selected project The color of the bar is determined by the code of the corresponding project.
Code A
Code B
Code C
Code D
Code ECalc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. Actual dates of the selected resource for the selected task in the selected project Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the reported hours worked of the corresponding resource (DT472) or are edited manually. Date of tasks, risks and opportunity measures and process steps The date value for the bar is calculated: From DB 39.5.15
Symbol Meaning Color Comment Planned load (remaining load) of the resource(s) in projects The color of the bar is determined by the code of the projects. Code A
Code B
Code C
Code D
Code EThe code is defined in the Project Core Data module of the respective project. The values for the histogram bars are each calculated from the Planned code 1 to Planned code 5 columns. Actual load of the resource(s) The values for the histogram bar are taken from the Used column from the period records of the resource(s) (DT468). The values in the period records, in turn stem from the working time recording of the resources (DT472). Available capacity of resource(s) The values for histogram bars are calculated from the Available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
The limiting line at the top of the bar will be visible despite of overlapping by utilization bars.Basic load of resource(s) The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, again, comes from the general basic load defined for the resource in the Resource Data Sheet.
The limiting line at the top margin of the bar will be visible despite overlapping by utilization bars.From DB 39.5.14
Symbol Meaning Color Comment Planned load (remaining load) of the resource(s) in projects The color of the bar is determined by the code of the projects. Code A
Code B
Code C
Code D
Code EThe code is defined in the Project Core Data module of the respective project. The values for the histogram bars are each calculated from the Planned code 1 to Planned code 5 columns. Actual load of the resource(s) The values for the histogram bar are taken from the Used column from the period records of the resource(s) (DT468). The values in the period records, in turn stem from the working time recording of the resources (DT472). Available capacity of resource(s) The values for histogram bars are calculated from the Available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
The limiting line at the top of the bar will be visible despite of overlapping by utilization bars.Basic load of resource(s) The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, again, comes from the general basic load defined for the resource in the Resource Data Sheet.
The limiting line at the top margin of the bar will be visible despite overlapping by utilization bars.From DB 39.5.12
Symbol Meaning Color Comment Planned load (remaining load) of the resource(s) in projects The color of the bar is determined by the code of the projects. Code A
Code B
Code C
Code D
Code EThe code is defined in the Project Core Data module of the respective project. The values for the histogram bars are each calculated from the Planned code 1 to Planned code 5 columns. Actually incurring load (actual load) of the resource(s) The values for the histogram bar are taken from the Used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472). Available capacity of the resource(s) The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
NEWThe limiting line at the top of the bar will be visible despite of overlapping by utilization bars.Basic load of resource(s) The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, again, comes from the general basic load defined for the resource in the Resource Data Sheet.
NEWThe limiting line at the top margin of the bar will be visible despite overlapping by utilization bars.Factor 4 of resource(s) The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet. Factor 5 of resource(s) The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, again, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet. From DB 39.5.8
Symbol Meaning Color Comment Planned load of the resource(s) in projects The color of the bar is determined by the code of the projects. Code A
Code B
Code C
Code D
Code EThe code is defined in the Project Core Data module of the respective project. The values for the histogram bars are each calculated from the Planned code 1 to Planned code 5 columns. Actually incurring load (actual load) of the resource(s) The values for the histogram bar are taken from the Used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472). Available capacity of the resource(s) The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
NEWThe limiting line at the top of the bar will be visible despite of overlapping by utilization bars.Basic load of resource(s) The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, again, comes from the general basic load defined for the resource in the Resource Data Sheet.
NEWThe limiting line at the top margin of the bar will be visible despite overlapping by utilization bars.Factor 4 of resource(s) The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet. Factor 5 of resource(s) The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, again, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet. Up to DB 39.5.8
Symbol Meaning Color Comment Planned load of the resource(s) in projects The color of the bar is determined by the code of the projects. Code A
Code B
Code C
Code D
Code EThe code is defined in the Project Core Data module of the respective project. The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns. Actually incurring load (actual load) of the resource(s) The values for the histogram bar are taken from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472). Available capacity of resource(s) The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet. Basic load of resource(s) The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load value defined for the resource in the Resource Data Sheet. Factor 4 of resource(s) The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet. Factor 5 of resource(s) The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, again, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet.