DT468 Period
DI001326 Resource
ID of the resource
DI001327 Period
In PLANTA
project, one period equates to one day. On this day, a resource can be planned, or vacation or absence can be specified for him or her.
From DB 39.5.8
DI001337 Available capacity (without child resources)
Actually available capacity of the selected resource and of all of its possibly existing child resources (summarized) in the selected period
Do not confuse this with general availability per period (
Unit/period)! Due to different influence factors, the actually available capacity can be lower or higher than the defined availability.
Details
- When creating period records, the initial value is consistently copied from the Available capacity for periods field (Resource Data Sheet module) to all periods but if necessary, it can be changed for each period by changing the influence factor values (manual changing not possible since calculated).
Calculation
- Available capacity (without child resources) = Unit/Period * Factor amount/period +/- values of the influence factor 1-5 (vacation, absence, period factor 3, 4, or 5) calculated successively.
Up to DB 39.5.8
DI001337 Available capacity
Actually available capacity of the selected resource particularly in the selected period
Do not confuse this with general availability per period (
Unit/period)! Due to different influence factors, the actually available capacity can be lower or higher than the generally defined availability.
Details
- When creating period records, the initial value is consistently copied from the Available capacity for periods field (Resource Data Sheet module) to all periods but it can be changed for each period by changing the influence factor values if necessary (manual changing not possible since calculated).
Calculation
- Available capacity = Unit/period * Factor amount/period +/- values of the influence factor 1-5 (vacation, absence, period factor 3, 4, or 5) (calculated successively).
From DB 39.5.8
DI002454 Available capacity
Actually available capacity of the selected resource and of all of its possibly existing child resources (summarized) in the selected period
Calculation (summarization)
Note
- If the resource availability of the child resources is altered, the available capacity for each period will be summarized upwards along the resource structure when saving. It is saved in the Available capacity field on each parent resource per period.
Up to DB 39.5.8
DI002454 Summarized available capacity
Summarized available capacity of the selected resource in the selected period.
Details
- Summarized available capacity = sum of the Available capacity values of the selected resource and of all of its child resources per period, provided that the Summarize periods checkbox has been activated.
Note
- If the resource availability of the child resources is altered, the available capacity for each period will be summarized upwards along the resource structure when saving. It is saved in the Summarized available capacity field on each parent resource per period.
From DB 39.5.7
DI001338 Factor amount/period
Amount available from the production factor particularly for the selected period. When creating the periods, the general, initial value is consistently copied from the
Factor amount field (
Resource Data Sheet module) to all period records but can be changed in individual period records afterwards.
Details
The parameter can be edited by users with modification rights in the following module:
Up to DB 39.5.7
DI001338 Factor amount/day
Amount available from the production factor in the selected period. When creating periods from the
Factor amount field in the
Resource Data Sheet, the initial value will be applied consistently to all period records but can be changed for individual periods afterwards.
Details
- Can be used to influence the Available capacity.
- A value less than 1 reduces the available capacity, an entry greater than 1 increases it.
The parameter can be edited by users with modification rights in the following module:
DI001339 Unit/period
The number of units (
the unit itself is defined in the
Base unit parameter), which are available for the planning of the selected resource in the selected period. When creating the periods, the initial value is consistently copied from the
Unit/day field (
Resource Data Sheet module) to all period records but can be changed in individual period records afterwards.
The parameter can be edited by users with modification rights in the following module:
From DB 39.5.7
DI001340 Vacation (factor value 1)
Value of the period influence factor 1 that serves to change the
Available capacity of the resource per period. Since influence factor 1 is reserved by PLANTA for vacation, the vacation of the resource is defined for each period in the
Vacation (factor value 1) field.
NEW The field cannot be edited manually but is filled automatically depending on the entry in the
Absence type field. Possible values are 1 or 0,5, also depending on the value selected in
Absence type.
Details
- In the calculation of the Available capacity, the 5 period influence factors are considered successively.
Up to DB 39.5.7
DI001340 Vacation
Value of the period influence factor 1 that serves to change the
Available capacity of the resource per period. Since influence factor 1 is reserved by PLANTA for vacation, the vacation of the resource is defined for each period in the
Vacation field.
Details
- For the calculation of the Available capacity, the 5 period influence factors are considered successively.
The parameter can be edited by users with modification rights in the following module:
From DB 39.5.7
DI001341 Absence (factor value 2)
Value of the period influence factor 2 that serves to change the
Available capacity (without child resources) of the resource per period. Since influence factor 2 is reserved by PLANTA for absence, the absence of the resource is defined for each period in the
Absence (factor value 2) field.
NEW The field cannot be edited manually but is filled automatically depending on the entry in the
Absence type field. Possible values are 1 or 0,5, also depending on the value selected in
Absence type.
Details
Up to DB 39.5.7
DI001341 Absence
Value of the period influence factor 2 that serves to change the
Available capacity of the resource per period. Since influence factor 2 is reserved by PLANTA for absence, the absence of the resource is defined for each period in the
Absence field.
Details
- For the calculation of the Available capacity, the 5 period influence factors are considered successively.
The parameter can be edited by users with modification rights in the following module:
From DB 39.5.8
DI001342 Basic load (factor value 3)
Value of the period influence factor 3 that serves to change the
Available capacity (without child resources) of the resource per period. Since influence factor 3 is reserved by PLANTA for basic load, the basic load of the resource is defined for each period in the
Basic load (factor value 3) field. The initial value is copied from the
Value 3 field in the
Resource Data Sheet module but can be changed in the selected period.
Details
- In the calculation of the Available capacity, the 5 period influence factors are considered successively.
The parameter can be edited by users with modification rights in the following module:
From DB 39.5.7
DI001342 Factor value 3
Value of the period influence factor 3 that serves to change the
Available capacity of the resource per period. The initial value is copied from the
Value 3 field in the
Resource Data Sheet module but can be changed for each period.
Details
- In PLANTA, Period factor 3 = Basic load.
- For the calculation of the Available capacity, the 5 period influence factors are considered successively.
The parameter can be edited by users with modification rights in the following module:
Up to DB 39.5.7
DI001342 Period factor 3
Value of the period influence factor 3 that serves to change the
Available capacity of the resource per period. The initial value is copied from the
Value 3 field in the
Resource Data Sheet module but can be changed for each period.
Details
- In PLANTA, Period factor 3 = Basic load.
- For the calculation of the Available capacity, the 5 period influence factors are considered successively.
The parameter can be edited by users with modification rights in the following module:
Up to DB 39.5.7
DI001343 Period factor 4
Influence factor that serves to modify the
Available capacity of the resource in the selected period. The initial value is copied from the
Value 4 field in the
Resource Data Sheet module but can be changed in the selected period.
Details
- In PLANTA Standard, Period factor 4 = additional work.
- For the calculation of the available capacity, the 5 period factors are considered successively.
From DB 39.5.7
DI001344 Factor value 5
Value of the period influence factor 5 that serves to change the
Available capacity (without child resources) of the resource in the selected period. The initial value is copied from the
Value 5 field in the
Resource Data Sheet module but can be changed in the selected period.
Details
The parameter can be edited by users with modification rights in the following module:
Up to DB 39.5.7
DI001344 Period factor 5
Value of the period influence factor that serves to change the
Available capacity of the resource in the selected period. The initial value is copied from the
Value 5 field in the
Resource Data Sheet module but can be changed in the selected period.
Details
- In PLANTA Standard, Period factor 5 = Miscellaneous.
- For the calculation of the Available capacity, the 5 period influence factors are considered successively.
The parameter can be edited by users with modification rights in the following module:
From DB 39.5.8
DI001346 Used (without child resources)
Actually incurring load (actual load) of the selected resource without its possibly existing child resources in the selected period (day)
Calculation
- The Used (without child resources) value is determined from Actual load values of the resource from all projects in which it is planned.
Notes
- The respective data field is hidden in the Availability module by default and can be displayed by the user if necessary.
- In this field, only the values from the projects with status = "Active" are displayed.
- If the Work parameter = (deactivated), Used (without child resources) = 0
Up to DB 39.5.8
DI001346 Used
Actual load of the selected resource in the selected period (day)
Details
- The Used value is determined from Actual load values of the resource from all projects in which it is planned.
Notes
- The respective data field is hidden in the Availability module by default and can be displayed by the user if necessary.
- In this field, only the values from the projects with status = "Active" are displayed.
From DB 39.5.8
DI002464 Used
Actually incurring load (actual load) of the selected resource and of all of its possibly existing child resources (summarized) in the selected period (day)
Calculation (summarization)
Notes
- The respective data field is hidden in the Availability module by default and can be displayed by the user if necessary.
- In this field, only the values from the projects with status = "Active" are displayed.
Up to DB 39.5.8
DI002464 Summarized used
Actual load of the selected resource and of all of its possibly existing child resources (summarized) in the selected period (day)
Details
- Summarized used = sum of the Used values of the selected resource and of all of its child resources in the selected period, provided that the Summarize periods checkbox is activated.
Notes
- The respective data field is hidden in the Availability module by default and can be displayed by the user if necessary.
- In this field, only the values from the projects with status = "Active" are displayed.
From DB 39.5.8
DI001352 Planned (without child resources)
Planned remaining load (remaining load) of the selected resource without its possibly existing child resources in all projects in the selected period (day)
Calculation
- The Planned (without child resources) value is determined from Remaining load values of the resource from all projects in which it is planned.
Notes
- The respective data field is hidden in the Availability module by default and can be displayed by the user if necessary.
- In this field, only the values from the projects with status = "Active" are displayed.
- If the Work parameter = (deactivated), Planned (without child resources) = 0
Up to DB 39.5.8
DI001352 Planned
Planned remaining load of the selected resource without its possibly existing child resources in the selected period (day)
Details
- The Planned value is determined from Remaining load values of the resource from all projects in which it is planned.
Notes
- The respective data field is hidden in the Availability module by default and can be displayed by the user if necessary.
- In this field, only the values from the projects with status = "Active" are displayed.
From DB 39.5.8
DI001353 Planned code A (without child resources)
Planned remaining load of the selected resource without its possibly existing child resources in
active projects with
Code = A in the selected period (day)
Calculation
- The Planned code A (without child resources) value is determined from Remaining load values of the resource from all projects with Code = A in which this resource is planned.
Notes
- By adjusting the value of the Utilization code 1 model parameter, the value of another project code can also be displayed in the Planned code A field.
- If the Work parameter = (deactivated), Planned code A (without child resources) = 0
Up to DB 39.5.8
DI001353 Planned code 1
Planned remaining load of the selected resource without its possibly existing child resources in
active projects with
Code = 1 per period (day)
Calculation
- The Planned code 1 value is determined from Remaining load values of the resource from all projects with Code = 1 in which this resource is planned.
Note
- By adjusting the value of the Utilization code 1 model parameter, the value of another project code can also be displayed individually in the Planned code 1 (without child resource) field.
From DB 39.5.8
DI001354 Planned code B (without child resources)
Planned remaining load of the selected resource without its possibly existing child resources in
active projects with
Code = B in the selected period (day).
Calculation
- The Planned code B (without child resources) value is determined from Remaining load values of the resource from all projects with Code = B in which this resource is planned.
Notes
- By adjusting the value of the Utilization code 2 model parameter, the value of another project code can also be displayed in the Planned code B field.
- If the Work parameter = (deactivated), Planned code B (without child resources) = 0
Up to DB 39.5.8
DI001354 Planned code 2
Planned remaining load of the selected resources without their possibly existing child resources in
active projects with
Code = 2 per period (day)
Calculation
- The Planned code 2 (without child resources) value is determined from Remaining load values of the resource from all projects with Code = 2 in which this resource is planned.
Note
- By adjusting the value of the Utilization code 2 model parameter, the value of another project code can also be displayed individually in the Planned code 2 (without child resource) field.
From DB 39.5.8
DI001355 Planned code C (without child resources)
Planned remaining load of the selected resource without its possibly existing child resources in
active projects with
Code = C in the selected period (day)
Calculation
- The Planned code C (without child resources) value is determined from Remaining load values of the resource from all projects with Code = C in which this resource is planned.
Notes
- By adjusting the value of the Utilization code 3 model parameter, the value of another project code can also be displayed in the Planned code C field.
- If the Work parameter = (deactivated), Planned code C (without child resources) = 0
Up to DB 39.5.8
DI001355 Planned code 3
Remaining load of the selected resource without its possibly existing child resources in
active projects with
Code = C per period (day)
Note
- By adjusting the value of the Utilization code 3 model parameter, the value of another project code can also be displayed individually in the Planned code 3 (without child resource) field.
From DB 39.5.8
DI001356 Planned code D (without child resources)
Planned remaining load of the selected resource without its possibly existing child resources in
active projects with
Code = D in the selected period (day)
Calculation
- The Planned code D (without child resources) value is determined from Remaining load values of the resource from all projects with Code = D in which this resource is planned.
Notes
- By adjusting the value of the Utilization code 4 model parameter, the value of another project code can also be displayed individually in the Planned code D field.
- If the Work parameter = (deactivated), Planned code C (without child resources) = 0
Up to DB 39.5.8
DI001356 Planned code 4
Remaining load of the selected resource in
active projects with
Code = D in the selected period (day)
Note
- By adjusting the value of the Utilization code 4 model parameter, the value of another project code can also be displayed individually in the Planned code 4 (without child resource) field.
From DB 39.5.8
DI001357 Planned Code E (without child resources)
Planned remaining load of the selected resource without their possibly existing child resources in
active projects with
Code = E in the selected period (day)
Calculation
- The Planned code E (without child resources) value is determined from Remaining load values of the resource from all projects with Code = E in which the resource is planned.
Notes
- For individual adjustments you have to consider that here values from all projects are displayed, the codes of which do not correspond to any of the values of the Utilization code 1-4 model parameters. If projects with several such codes exist, their values are displayed summarized in the Planned code E (without child resources).
- If the Work parameter = (deactivated), Planned code E (without child resources) = 0
Up to DB 39.5.8
DI001357 Planned code 5
Remaining load of the selected resource without possibly existing child resources in
active projects with
Code = E per period (day)
Note
- For individual adjustments you have to consider that here values from all projects are displayed, the codes of which do not correspond to any of the values of the Utilization code 1-4 model parameters. If projects with several such codes exist, their values are displayed summarized in the Planned code 5 field.
From DB 39.5.8
DI002483 Planned
Planned remaining load (remaining load) of the selected resource and of all of its child resources (summarized) in the selected period (day)
Calculation (summarization)
Note
- The respective data field is hidden in the Availability module by default and can be displayed by the user if necessary.
Up to DB 39.5.8
DI002483 Summarized planned
Remaining load of the selected resource and all child resources (summarized) in the selected period (day)
Details
- Summarized planned = sum of the Planned values of the selected resource and of all of its child resources in the selected period (day), provided that the Summarize periods checkbox is activated for the parent resource.
Note
- The respective data field is hidden in the Availability module by default and can be displayed by the user if necessary.
From DB 39.5.8
DI002484 Planned code A
Planned remaining load (remaining load) of the selected resource and of all of its child resources (summarized) in projects the
Code of which equates to the value of the
Utilization code 1 model parameter in the selected period (day) The values for the planned load stem from the planning of the respective resource in the
Schedule.
Calculation (summarization)
Up to DB 39.5.8
DI002484 Summarized planned code 1
Remaining load of the selected resource and of all of its child resources (summarized) in projects the
Code of which equates to the value of the
Utilization code 1 model parameter per period (day)
Details
- Sum of the Planned code 1 values of the selected resource and of all of its child resources in the selected period (day), provided that the Summarize periods checkbox is activated.
From DB 39.5.8
DI002485 Planned code B
Planned remaining load (remaining load) of the selected resource and of all of its child resources (summarized) in projects the
Code of which equates to the value of the
Utilization code 2 model parameter in the selected period (day) The values for the planned load stem from the planning of the respective resource in the
Schedule.
Calculation (summarization)
Up to DB 39.5.8
DI002485 Summarized planned code 2
Remaining load of the selected resource and of all of its child resources (summarized) in projects the
Code of which equates to the value of the
Utilization code 2 model parameter in the selected period (day)
Details
- Sum of the Planned code 2 values of the selected resource and of all of its child resources in the selected period (day), provided that the Summarize periods checkbox is activated.
From DB 39.5.8
DI002486 Planned code C
Planned remaining load (remaining load) of the selected resource and of all of its child resources (summarized) in projects the
Code of which equates to the value of the
Utilization code 3 model parameter in the selected period (day) The values for the planned load stem from the planning of the respective resource in the
Schedule.
Calculation (summarization)
Up to DB 39.5.8
DI002486 Summarized planned code 3
Remaining load of the selected resource and of all of its child resources (summarized) in projects the
Code of which equates to the value of the
Utilization code 3 model parameter in the selected period (day)
Details
- Sum of the Planned code 3 values of the selected resource and of all of its child resources in the selected period (day), provided that the Summarize periods checkbox is activated.
From DB 39.5.8
DI002487 Planned code D
Planned remaining load (remaining load) of the selected resource and of all of its child resources (summarized) in projects the
Code of which equates to the value of the
Utilization code 4 model parameter in the selected period (day) The values for the planned load stem from the planning of the respective resource in the
Schedule.
Calculation (summarization)
Up to DB 39.5.8
DI002487 Summarized planned code 4
Remaining load of the selected resource and of all of its child resources (summarized) in projects the
Code of which equates to the value of the
Utilization code 4 model parameter in the selected period (day)
Details
- Sum of the Planned code 4 values of the selected resource and of all of its child resources in the selected period (day), provided that the Summarize periods checkbox is activated.
From DB 39.5.8
DI002488 Planned code E
Planned remaining load (remaining load) of the selected resource and of all of its child resources (summarized) in all planning objects the
Code of which does not correspond to any of the values in the
Utilization code 1-4 model parameters, in the selected period (day). The values for the planned load stem from the planning of the respective resource in the
Schedule.
Calculation (summarization)
Up to DB 39.5.8
DI002488 Summarized planned code 5
Remaining loads of the selected resource and of all of its child resources (summarized) in all planning objects the
Code of which does not correspond to any of the values in the
Utilization code 1-4 model parameters, per period (day)
Details
- Sum of the Planned code 5 values of the selected resource and of all of its child resources in the selected period (day), provided that the Summarize periods checkbox is activated.
From DB 39.5.8
DI001345 Utilization (without child resources)
Utilization of the selected resource without its possibly existing child resources in the selected period (day). The term utilization means the sum of planned remaining load (remaining load) and actual incurring load (actual load).
Calculation
Note
Up to DB 39.5.8
DI001345 Utilization
Utilization of the selected resource without its possibly existing child resources in the selected period (day)
Capacity scheduling
From DB 39.5.8
DI002455 Utilization
Utilization of the selected resource and of all of its child resources (summarized) in the selected period (day)
Calculation (summarization)
Up to DB 39.5.8
DI002455 Summarized utilization
Utilization of the selected resource and all of its child resources (summarized) in the selected period (day)
Details
- Sum of the Utilization values of the resource and of all of its child resources in the selected period (day), provided that the Summarize periods checkbox has been activated for the parent resource.
From DB 39.5.8
DI001363 % utilization (without child resources)
Percentage value of the utilization of the selected resource without its possibly existing child resources in the selected period (day)
Calculation
Up to DB 39.5.8
DI001363 % utilization
The utilization of the resource per period (day) in percent
Capacity scheduling
From DB 39.5.14
DI059759 % utilization
Percentage value of the utilization of the selected resource and of all of its child resources (summarized) in the selected period (day)
Calculation
NEW
Note
From DB 39.5.8
DI059759 % utilization
Percentage value of the utilization of the selected resource and of all of its child resources (summarized) in the selected period (day)
Calculation
Note
Up to DB 39.5.8
DI059759 Summarized % utilization
Percentage value of the planned utilization of the selected resource and of all of its child resources (summarized) in the selected period (day)
Calculation
Note
DI001364 Work
With this parameter you can define whether the resource is available for planning in the selected period (day).
Values:
- = work
- = no work.
- If the Work parameter is deactivated for a particular period, all other parameters mentioned above (Available capacity (without child resources), Utilization (without child resources), Planned (without child resources), Utilization (without child resources)) = 0 for this period
Details
From DB 39.5.8
- When creating periods, this value is copied from the stored resource calendar.
- In order to define a day as a non-working day in the Availability module, you have to empty the Unit/period and Factor amount/period parameters and save these changes. If this is done, the Available capacity (without child resources) and Available capacity fields are emptied automatically if they contain values and the Work checkbox is automatically deactivated.
- And vice versa, if you want to define a non-working day as a working day in the Availability module, the Unit/period and Factor amount/period parameters must be set, and in case the basic load is defined in the Resource Data Sheet, the Basic load (factor value 3) field with the appropriat value and the changes must be saved. As a result, the Work checkbox is automatically deactivated.
- After these parameters have been changed, replanning is required in order for the changed availabilities to be taken into account in all projects for which the resource has been planned.
From DB 39.5.7
When creating periods, this value is copied from the stored resource calendar.
In order to define a day as a non-working day in the Availability module, you have to empty the Unit/period and Factor amount/period parameters and save these changes. If this is done, the Available capacity and Summarized available capacity fields are emptied automatically if they contain values.
After these parameters have been changed, replanning is required in order for the changed availabilities to be taken into account in all projects for which the resource has been planned. Up to DB 39.5.7
When creating periods, this value is copied from the stored resource calendar.
In order to define a day as a non-working day in the Availability module, you have to empty the Unit/period and Factor amount/period parameters and save these changes. If this is done, the Available capacity and Summarized available capacity fields are emptied automatically if they contain values.
After these parameters have been changed, replanning is required in order for the available capacities in all projects for which the resource has been planned to be taken into account.
DI002537 Vacation
Number of vacation days of the selected resource
Details
DI002538 Absence
Number of vacation days of the selected resource
Details
DI002544 Comment
Comment on the absence of the resource.
DI041435 Absence type name
Name of the absence type. If the respective field is an input field in the selected module, the type can be selected from the listbox.
Values
Note
- Depending on the value selected here, the Vacation and Absence fields of the respective resource are filled with 1 or 0,5.
From DB 39.5.14
DI009478 Presence
Presence or hours to be worked of the selected resource in the selected period
Details
- NEW When using the Arrival/Leaving times, the presence of the employee is saved here as soon as he/she has recorded presence in the course of working time recording.
- When using the hours to be worked function, the hours to be worked for employees can be specified here. The field is either filled automatically when setting the hours to be worked value in the Edit Hours to be Worked module or it can be edited manually in the Availability module.
New from DB 39.5.0
DI009478 Hours to be worked
Hours to be worked of the selected resource in the selected period
Details
New from DB 39.5.8
DI063981 Histo: Available capacity + planned by code
Display of the available capacity and remaining utilization as a histogram by project code
DI041387 Week (period)
Calendar week with year specification
DI041388 Month (period)
Display of month and year
DI041389 Quarter (period)
DI041390 Year (period)
DI001661 Calendar week
DI001673 Day
DI002536 Vacation, absence, work = Y
DI059484 Absence+vacation sum
Sum of all absence and vacation days per selected time period. The time period can vary in different modules.