Base | Here, only the resources are displayed which at the same time
|
All resources | Here, all resources (planned and unplanned) are displayed, which at the same time
|
All | Here, all resources are displayed which the current user is allowed to view, regardless of his/her department or the planning of the respective resources. Please consider that using this module variant may cause performance impairment. |
Revenues | Here, all revenue resources (resources with Resource type = 8) are displayed which at the same time the current user is allowed to see
|
Costs | Here, all cost resources (resources with Resource type = 9) are displayed which at the same time the current user is allowed to see
|
Skills | Here, all skill resources (resources with resource type = 5) are displayed which at the same time the current user is allowed to see
|
With comment | This variant corresponds to the basic variant with the difference that the Comment field is displayed additionally. |
Legend: HistogramLegend: Bar diagram (task)From DB 39.5.15
Symbol Meaning Color Comment Planned load (remaining load) of the resource(s) in projects The color of the bar is determined by the code of the projects. Code A
Code B
Code C
Code D
Code EThe code is defined in the Project Core Data module of the respective project. The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns. Actually incurring load (actual load) of resource(s) The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472). Available capacity of resource(s) The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
The limiting line at the top of the bar will be visible despite of overlapping by load data.Basic load of resource(s) The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load defined for the resource in the Resource Data Sheet.
The limiting line at the top of the bar will be visible despite of overlapping by load data.Overload of resource The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned). From DB 39.5.14
Symbol Meaning Color Comment Planned load (remaining load) of the resource(s) in projects The color of the bar is determined by the code of the projects. Code A
Code B
Code C
Code D
Code EThe code is defined in the Project Core Data module of the respective project. The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns. Actually incurring load (actual load) of resource(s) The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472). Available capacity of resource(s) The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
The limiting line at the top of the bar will be visible despite of overlapping by load data.Basic load of resource(s) The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load defined for the resource in the Resource Data Sheet.
The limiting line at the top of the bar will be visible despite of overlapping by load data.Overload of resource The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned). From DB 39.5.12
Symbol Meaning Color Comment Planned load of the resource(s) in projects The color of the bar is determined by the code of the projects. Code A
Code B
Code C
Code D
Code EThe code is defined in the Project Core Data module of the respective project. The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns. Actual load of resource(s) The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472). Available capacity of resource(s) The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
NEWThe limiting line at the top of the bar will be visible despite of overlapping by load data.Basic load of resource(s) The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load defined for the resource in the Resource Data Sheet.
NEWThe limiting line at the top of the bar will be visible despite of overlapping by load data.Factor 4 of resource(s) The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet. Factor 5 of resource(s) The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet. Overload of resource The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned). From DB 39.5.8
Symbol Meaning Color Comment Planned load of resource(s) in the projects The bar color is determined by the project code. Code A
Code B
Code C
Code D
Code EThe code is defined in the Project Core Data module of the respective project. The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns. Actual load of resource(s) The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472). Available capacity of resource(s) The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
NEWThe limiting line at the top of the bar will be visible despite of overlapping by load data.Basic load of resource(s) The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load defined for the resource in the Resource Data Sheet.
NEWThe limiting line at the top of the bar will be visible despite of overlapping by load data.Factor 4 of resource(s) The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet. Factor 5 of resource(s) The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet. Overload of resource The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned). Up to DB 39.5.8
Symbol Meaning Color Comment Planned load of resource(s) in the projects The bar color is determined by the project code. Code A
Code B
Code C
Code D
Code EThe code is defined in the Project Core Data module of the respective project. The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns. Actual load of resource(s) The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472). Available capacity of resource(s) The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet. Basic load of resource(s) The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load value defined for the resource in the Resource Data Sheet. Factor 4 of resource(s) The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet. Factor 5 of resource(s) The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet. Overload of resource The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned). From DB 39.5.14
Symbol Meaning Color Comment Task requested dates Requested start and Requested end of a task are defined in the Schedule module. Calculated dates of the selected resource for the selected task in the selected project Upper bar part: The color of the bar is determined by the code of the respective project For the meaning of the individual code colors, see the histogram legend. Lower bar part: Uncritical task
Critical taskCalc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical. Calculated dates of the selected resource for the selected task in the selected project The bar is white hatched. Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the working time recording of the respective resource (DT472) or edited manually. Latest task dates Latest start and Latest end of a task are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. Task date delay A date delay occurs if Calc. end of a task is later than its Latest end. From DB 39.5.12
Symbol Meaning Color Comment Task requested dates Requested start and Requested end of a task are defined in the Schedule module. Calculated dates of the selected resource for the selected task in the selected project Upper bar part: The color of the bar is determined by the code of the respective project For the meaning of the individual code colors, see the histogram legend. Lower bar part: Uncritical task
Critical taskCalc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical. Actual dates of the selected resource for the selected task in the selected project Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the reported hours worked of the corresponding resource (DT472) or are edited manually. Latest task dates Latest start and Latest end of a task are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. Task date delay A date delay occurs if Calc. end of a task is later than its Latest end. From DB 39.5.11
Symbol Meaning Color Comment Task requested dates Requested start and Requested end of a task are defined in the Schedule module. Calculated dates of the selected resource for the selected task in the selected project Upper bar part: The color of the bar is determined by the code of the respective project For the meaning of the individual code colors, see the histogram legend. Lower bar part: Uncritical task
Critical taskCalc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical. Actual dates of the selected resource for the selected task in the selected project Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the reported hours worked of the corresponding resource (DT472) or are edited manually. Latest task dates Latest start and Latest end of a task are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. Task date delay A date delay occurs if Calc. end of a task is later than its Latest end. Up to DB 39.5.11
Symbol Meaning Color Comment Task requested dates Requested start and Requested end of a task are defined in the Schedule module. Calculated dates of the selected resource for the selected task in the selected project Upper bar part: The color of the bar is determined by the code of the respective project For the meaning of the individual code colors, see the histogram legend. Lower bar part: Uncritical task
Critical taskCalc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical. Actual dates of the selected resource for the selected task in the selected project Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the reported hours worked of the corresponding resource (DT472) or are edited manually. Latest task dates Latest start and Latest end of a task are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. Task date delay A date delay occurs if Calc. end of a task is later than its Latest end.
I | Attachment | History | Size | Date | Comment |
---|---|---|---|---|---|
png | Pfeile.PNG | r2 r1 | 0.3 K | 2015-10-12 - 13:02 |