The documentation from version 39.5.17 of PLANTA project can be found in the new PLANTA Online Help.

Resource Planning MOD009BHJ

Access path

Information

  • In this module, resource planning is displayed and resource effort can be distributed.

Details

  • When opening the module, the planning of the department (department resource) for which the current user has been defined as a department manager, and that of individual resources is loaded automatically.
  • The utilization diagrams show the utilization of the resources by project code. On department resource level, the accumulated utilization of all resources subordinate to the department resource is displayed. In the utilization diagram, the resource utilization is compared with the resource availability (see legend).
  • The number range below the diagram shows
    • Line 1: Utilization in %
    • Line 2: Utilization in absolute numbers
    • Line 3: Available capacity
      • All number specifications are summarized specifications (selected resource + all of its child resources), just like the diagram itself.
      • There is a traffic light implemented on the field with the percentage utilization which switches to red as soon as the overload has been detected (utilization over 100%). See also the legend.
  • You can switch to the Dashboard or Task modules by clicking on the link in the Project or Task fields.

From DB 39.5.14

Period
  • When changing the period to be displayed via the from/to fields, the display of the scale is automatically adjusted exactly to the period specifications.

Up to DB 39.5.14

Period
  • When changing the period to be displayed via the from/to fields, the display of the scale is automatically adjusted exactly to the period specifications.
  • The period filter entered in this module is automatically applied to all other modules of the session which contain the period filter and is inverted

Note

  • Since the predetermined period filter in the from and to fields also influences the display of the utilization diagram, it may occur that the utilization display in the first bar of the diagram does not correspond to the display in the respective bar in the My Departments module.

New from DB 39.5.3

Module Variants
Base Here, only the resources are displayed which at the same time
  • belong to the department of the current user and
  • the current user is allowed to see according to his/her access rights
  • are planned in all projects (possess Remaining effort) and
  • have loads in the specified period
All resources Here, all resources (planned and unplanned) are displayed, which at the same time
  • belong to the department of the current user and
  • the current user is allowed to see according to his/her access rights and
  • have loads in the specified period
All Here, all resources are displayed which the current user is allowed to view, regardless of his/her department or the planning of the respective resources.
Please consider that using this module variant may cause performance impairment.
Revenues Here, all revenue resources (resources with Resource type = 8) are displayed which at the same time the current user is allowed to see
  • according to his/her access rights and
  • have loads in the specified period
Costs Here, all cost resources (resources with Resource type = 9) are displayed which at the same time the current user is allowed to see
  • according to his/her access rights and
  • have loads in the specified period
Skills Here, all skill resources (resources with resource type = 5) are displayed which at the same time the current user is allowed to see
  • according to his/her access rights and
  • have loads in the specified period
With comment This variant corresponds to the basic variant with the difference that the Comment field is displayed additionally.

From DB 39.5.12

Distribute resource planning
  • Select the source resource (the resource the effort of which is to be reduced) and expand the tree structure.
  • All projects and tasks for which this resource is scheduled are displayed.
    • The tasks are displayed sorted by their calculated end dates (Calc. end).
  • For the required project, add a new resource to which the effort from the source resource is to be distributed. To do so,
    • right-click on the project and select the Insert New resource context menu command. or
    • click on the plus button.
      • Select the target resource from the listbox in the inserted line in the Resource name field.
        • If you are authorized to access the resources of other departments (controlled via the Resource access parameter), these resources are also available as target resources in the current resource listbox.
  • Enter the effort value to be distributed in the To be distributed field.
  • Click on the Distribute effort button (the button is located at the bottom of the module).
  • Confirm the Distribute resource effort? message with Yes.
  • The effort values of the source and target resource are changed.

Up to DB 39.5.12

Distribute resource planning
  • Select the source resource (the resource the effort of which is to be reduced) and expand the tree structure.
  • All projects and tasks for which this resource is scheduled are displayed.
    • The tasks are displayed sorted by their calculated end dates (Calc. end).
  • For the required project, add a new resource to which the effort from the source resource is to be distributed. To do so,
    • right-click on the project and select the Insert New resource context menu command. or
    • click on the arrow button Pfeile.PNG. (The arrow button is located next to the task name).
      • Select the target resource from the listbox in the inserted line in the Resource name field.
        • If you are authorized to access the resources of other departments (controlled via the Resource access parameter), these resources are also available as target resources in the current resource listbox.
  • Enter the effort value to be distributed in the To be distributed field.
  • Click on the Distribute effort button (the button is located at the bottom of the module).
  • Confirm the Distribute resource effort? message with Yes.
  • The effort values of the source and target resource are changed.

Notes

From S 39.5.23

  • NEW Currently, the distribution of the effort from a resource with a PM_Load profile can only be carried out manually in the Schedule module.
  • If the value to be distributed is too high, the following message appears: The initial value to be distributed has been exceeded.
  • After distribution, the module is refreshed and the current values are displayed.
  • If you mark one or several tasks, only the effort of the resources of the marked tasks is distributed.
  • In the task line in the Remaining effort, Actual effort, Calc. start, and Calc. end, the efforts and dates of the resource assignment are displayed.

Up to S 39.5.23

  • If the value to be distributed is too high, the following message appears: The initial value to be distributed has been exceeded.
  • After distribution, the module is refreshed and the current values are displayed.
  • If you mark one or several tasks, only the effort of the resources of the marked tasks is distributed.
  • In the task line in the Remaining effort, Actual effort, Calc. start, and Calc. end, the efforts and dates of the resource assignment are displayed.
  • Legend: Histogram

    From DB 39.5.15

    Symbol Meaning Color Comment
    CodeADB14.png Planned load (remaining load) of the resource(s) in projects The color of the bar is determined by the code of the projects.
    CodeADB14.png Code A
    CodeBDB14.png Code B
    CodeCDB14.png Code C
    CodeDDB14.png Code D
    CodeEDB14.png Code E
    The code is defined in the Project Core Data module of the respective project.
    The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns.
    ActDB12.png Actually incurring load (actual load) of resource(s)   The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472).
    KapLinieDB15.png Available capacity of resource(s)   The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
    The limiting line at the top of the bar will be visible despite of overlapping by load data.
    GrundlastLinieDB15.png Basic load of resource(s)   The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load defined for the resource in the Resource Data Sheet.
    The limiting line at the top of the bar will be visible despite of overlapping by load data.
    Ueberlast.PNG Overload of resource   The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned).

    From DB 39.5.14

    Symbol Meaning Color Comment
    CodeADB14.png Planned load (remaining load) of the resource(s) in projects The color of the bar is determined by the code of the projects.
    CodeADB14.png Code A
    CodeBDB14.png Code B
    CodeCDB14.png Code C
    CodeDDB14.png Code D
    CodeEDB14.png Code E
    The code is defined in the Project Core Data module of the respective project.
    The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns.
    ActDB12.png Actually incurring load (actual load) of resource(s)   The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472).
    KapLinieDB14.png Available capacity of resource(s)   The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
    The limiting line at the top of the bar will be visible despite of overlapping by load data.
    GrundlastLinieDB14.png Basic load of resource(s)   The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load defined for the resource in the Resource Data Sheet.
    The limiting line at the top of the bar will be visible despite of overlapping by load data.
    Ueberlast.PNG Overload of resource   The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned).

    From DB 39.5.12

    Symbol Meaning Color Comment
    CodeADB12.PNG Planned load of the resource(s) in projects The color of the bar is determined by the code of the projects.
    CodeADB12.PNG Code A
    CodeBDB12.PNG Code B
    CodeCDB12.PNG Code C
    CodeDDB12.PNG Code D
    CodeEDB12.PNG Code E
    The code is defined in the Project Core Data module of the respective project.
    The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns.
    IstHisto.png Actual load of resource(s)   The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472).
    KapLinie.png Available capacity of resource(s)   The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
    NEWThe limiting line at the top of the bar will be visible despite of overlapping by load data.
    GrundlastLinie.png Basic load of resource(s)   The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load defined for the resource in the Resource Data Sheet.
    NEWThe limiting line at the top of the bar will be visible despite of overlapping by load data.
    Faktor4.png Factor 4 of resource(s)   The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet.
    Faktor5.png Factor 5 of resource(s)   The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet.
    Ueberlast.PNG Overload of resource   The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned).

    From DB 39.5.8

    Symbol Meaning Color Comment
    CodeHisto.png Planned load of resource(s) in the projects The bar color is determined by the project code.
    A.png Code A
    B.png Code B
    C.png Code C
    D.png Code D
    E.png Code E
    The code is defined in the Project Core Data module of the respective project.
    The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns.
    IstHisto.png Actual load of resource(s)   The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472).
    KapLinie.png Available capacity of resource(s)   The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
    NEWThe limiting line at the top of the bar will be visible despite of overlapping by load data.
    GrundlastLinie.png Basic load of resource(s)   The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load defined for the resource in the Resource Data Sheet.
    NEWThe limiting line at the top of the bar will be visible despite of overlapping by load data.
    Faktor4.png Factor 4 of resource(s)   The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet.
    Faktor5.png Factor 5 of resource(s)   The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet.
    Ueberlast.PNG Overload of resource   The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned).

    Up to DB 39.5.8

    Symbol Meaning Color Comment
    CodeHisto.png Planned load of resource(s) in the projects The bar color is determined by the project code.
    A.png Code A
    B.png Code B
    C.png Code C
    D.png Code D
    E.png Code E
    The code is defined in the Project Core Data module of the respective project.
    The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns.
    IstHisto.png Actual load of resource(s)   The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472).
    Kap.png Available capacity of resource(s)   The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
    GrundlastAbDb8.png Basic load of resource(s)   The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load value defined for the resource in the Resource Data Sheet.
    Faktor4.png Factor 4 of resource(s)   The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet.
    Faktor5.png Factor 5 of resource(s)   The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet.
    Ueberlast.PNG Overload of resource   The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned).

    Legend: Bar diagram (task)

    From DB 39.5.14

    Symbol Meaning Color Comment
    WunschDB14.png Task requested dates   Requested start and Requested end of a task are defined in the Schedule module.
    KalkPRVGDB14.png Calculated dates of the selected resource for the selected task in the selected project Upper bar part:
    The color of the bar is determined by the code of the respective project
    For the meaning of the individual code colors, see the histogram legend.

    Lower bar part:
    KalkDB12.PNG Uncritical task
    CalcCritDB12.PNG Critical task
    Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.




    Uncritical means: Total float > 0
    Critical means: Total float 0
    Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical.
    ActDB12.png Calculated dates of the selected resource for the selected task in the selected project The bar is white hatched. Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the working time recording of the respective resource (DT472) or edited manually.
    Puffer.png Latest task dates   Latest start and Latest end of a task are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.
    VGueberkrit.PNG Task date delay   A date delay occurs if Calc. end of a task is later than its Latest end.

    From DB 39.5.12

    Symbol Meaning Color Comment
    Wunsch.png Task requested dates   Requested start and Requested end of a task are defined in the Schedule module.
    KalkPRVGDB12.png Calculated dates of the selected resource for the selected task in the selected project Upper bar part:
    The color of the bar is determined by the code of the respective project
    For the meaning of the individual code colors, see the histogram legend.

    Lower bar part:
    KalkDB12.PNG Uncritical task
    CalcCritDB12.PNG Critical task
    Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.




    Uncritical means: Total float > 0
    Critical means: Total float 0
    Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical.
    ActDB12.png Actual dates of the selected resource for the selected task in the selected project   Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the reported hours worked of the corresponding resource (DT472) or are edited manually.
    Puffer.png Latest task dates   Latest start and Latest end of a task are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.
    VGueberkrit.PNG Task date delay   A date delay occurs if Calc. end of a task is later than its Latest end.

    From DB 39.5.11

    Symbol Meaning Color Comment
    Wunsch.png Task requested dates   Requested start and Requested end of a task are defined in the Schedule module.
    KalkPRVG.PNG Calculated dates of the selected resource for the selected task in the selected project Upper bar part:
    The color of the bar is determined by the code of the respective project
    For the meaning of the individual code colors, see the histogram legend.

    Lower bar part:
    VGKalk.png Uncritical task
    CriticNew.PNG Critical task
    Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.




    Uncritical means: Total float > 0
    Critical means: Total float 0
    Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical.
    Ist.png Actual dates of the selected resource for the selected task in the selected project   Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the reported hours worked of the corresponding resource (DT472) or are edited manually.
    Puffer.png Latest task dates   Latest start and Latest end of a task are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.
    VGueberkrit.PNG Task date delay   A date delay occurs if Calc. end of a task is later than its Latest end.

    Up to DB 39.5.11

    Symbol Meaning Color Comment
    Wunsch.png Task requested dates   Requested start and Requested end of a task are defined in the Schedule module.
    KalkPRVG.PNG Calculated dates of the selected resource for the selected task in the selected project Upper bar part:
    The color of the bar is determined by the code of the respective project
    For the meaning of the individual code colors, see the histogram legend.

    Lower bar part:
    Unkritisch.png Uncritical task
    kritisch.png Critical task
    Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.



    Uncritical means: Total float > 0
    Critical means: Total float 0
    Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical.
    Ist.png Actual dates of the selected resource for the selected task in the selected project   Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the reported hours worked of the corresponding resource (DT472) or are edited manually.
    Puffer.png Latest task dates   Latest start and Latest end of a task are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.
    VGueberkrit.PNG Task date delay   A date delay occurs if Calc. end of a task is later than its Latest end.

    Topic attachments
    I Attachment History Size Date Comment
    Pngpng Pfeile.PNG r2 r1 0.3 K 2015-10-12 - 13:02  

             PLANTA project









     
    • Suche in Topic-Namen

    • Suche in Topic-Inhalten
    This site is powered by the TWiki collaboration platform Powered by Perl