Access rightsDetails
- The allocation of department manager rights is done in the Department name (default) parameter.
- The definition of resource access is done via the resource structure code and the Access to resources parameter.
- The definition of skill access is done via the skill structure code and via the Access to resources parameter
- Please make sure that the entries in all parameters coincide.
Base | Utilization for a period of four months (one month in the past up to three months in the future) is displayed |
Short term | The utilization for a period of one month (from today up to one month in the future) is displayed |
Legend: Utilization diagramFrom DB 39.5.15
Symbol Meaning Color Comment Planned load (remaining load) of the resource(s) in projects The color of the bar is determined by the code of the projects. Code A
Code B
Code C
Code D
Code EThe code is defined in the Project Core Data module of the respective project. The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns. Actually incurring load (actual load) of resource(s) The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472). Available capacity of resource(s) The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
The limiting line at the top of the bar will be visible despite of overlapping by load data.Basic load of resource(s) The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load defined for the resource in the Resource Data Sheet.
The limiting line at the top of the bar will be visible despite of overlapping by load data.Overload of resource The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned). From DB 39.5.14
Symbol Meaning Color Comment Planned load (remaining load) of the resource(s) in projects The color of the bar is determined by the code of the projects. Code A
Code B
Code C
Code D
Code EThe code is defined in the Project Core Data module of the respective project. The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns. Actually incurring load (actual load) of resource(s) The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472). Available capacity of resource(s) The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
The limiting line at the top of the bar will be visible despite of overlapping by load data.Basic load of resource(s) The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load defined for the resource in the Resource Data Sheet.
The limiting line at the top of the bar will be visible despite of overlapping by load data.Overload of resource The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned). From DB 39.5.12
Symbol Meaning Color Comment Planned load of the resource(s) in projects The color of the bar is determined by the code of the projects. Code A
Code B
Code C
Code D
Code EThe code is defined in the Project Core Data module of the respective project. The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns. Actual load of resource(s) The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472). Available capacity of resource(s) The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
NEWThe limiting line at the top of the bar will be visible despite of overlapping by load data.Basic load of resource(s) The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load defined for the resource in the Resource Data Sheet.
NEWThe limiting line at the top of the bar will be visible despite of overlapping by load data.Factor 4 of resource(s) The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet. Factor 5 of resource(s) The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet. Overload of resource The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned). From DB 39.5.8
Symbol Meaning Color Comment Planned load of resource(s) in the projects The bar color is determined by the project code. Code A
Code B
Code C
Code D
Code EThe code is defined in the Project Core Data module of the respective project. The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns. Actual load of resource(s) The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472). Available capacity of resource(s) The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
NEWThe limiting line at the top of the bar will be visible despite of overlapping by load data.Basic load of resource(s) The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load defined for the resource in the Resource Data Sheet.
NEWThe limiting line at the top of the bar will be visible despite of overlapping by load data.Factor 4 of resource(s) The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet. Factor 5 of resource(s) The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet. Overload of resource The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned). Up to DB 39.5.8
Symbol Meaning Color Comment Planned load of resource(s) in the projects The bar color is determined by the project code. Code A
Code B
Code C
Code D
Code EThe code is defined in the Project Core Data module of the respective project. The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns. Actual load of resource(s) The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472). Available capacity of resource(s) The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet. Basic load of resource(s) The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load value defined for the resource in the Resource Data Sheet. Factor 4 of resource(s) The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet. Factor 5 of resource(s) The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet. Overload of resource The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned).