  • In this module, the current utilization of resources sorted by skills is displayed.
  • Details

    • If the department resource itself has overload, it will be indicated in red color below the utilization diagram of these resources.
    • The overloads of the individual resources of the department are not identified as long as they are compensated by other resources. If, however, the sum of the overloads of individual resources causes overload for the department, the overload of the department will be identified as well.
      • The overload numbers below the diagram are specified in days.
      • By expanding the tree structure on the Overload text (in red color as well) or by double-clicking on an overload number in the diagram, you can open the subarea of the same name in which the causes (projects) of the overload are displayed. Here, overloads are displayed in hours. This may possibly lead to rounding differences in the displayed overload values. It may also occur that no overload value in days is displayed below the diagram, although an overload record is available, as is the case, e.g., for overload values of less than one day.

    Note

    • PLANTA recommends to carry out a replanning of all projects before viewing the utilization diagram, especially if changes have been made to the resource structure.

    Legend: Histogram

    From DB 39.5.15

    Symbol Meaning Color Comment
    CodeADB14.png Planned load (remaining load) of the resource(s) in projects The color of the bar is determined by the code of the projects.
    CodeADB14.png Code A
    CodeBDB14.png Code B
    CodeCDB14.png Code C
    CodeDDB14.png Code D
    CodeEDB14.png Code E
    The code is defined in the Project Core Data module of the respective project.
    The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns.
    ActDB12.png Actually incurring load (actual load) of resource(s)   The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472).
    KapLinieDB15.png Available capacity of resource(s)   The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
    The limiting line at the top of the bar will be visible despite of overlapping by load data.
    GrundlastLinieDB15.png Basic load of resource(s)   The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load defined for the resource in the Resource Data Sheet.
    The limiting line at the top of the bar will be visible despite of overlapping by load data.
    Ueberlast.PNG Overload of resource   The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned).

    From DB 39.5.14

    Symbol Meaning Color Comment
    CodeADB14.png Planned load (remaining load) of the resource(s) in projects The color of the bar is determined by the code of the projects.
    CodeADB14.png Code A
    CodeBDB14.png Code B
    CodeCDB14.png Code C
    CodeDDB14.png Code D
    CodeEDB14.png Code E
    The code is defined in the Project Core Data module of the respective project.
    The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns.
    ActDB12.png Actually incurring load (actual load) of resource(s)   The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472).
    KapLinieDB14.png Available capacity of resource(s)   The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
    The limiting line at the top of the bar will be visible despite of overlapping by load data.
    GrundlastLinieDB14.png Basic load of resource(s)   The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load defined for the resource in the Resource Data Sheet.
    The limiting line at the top of the bar will be visible despite of overlapping by load data.
    Ueberlast.PNG Overload of resource   The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned).

    From DB 39.5.12

    Symbol Meaning Color Comment
    CodeADB12.PNG Planned load of the resource(s) in projects The color of the bar is determined by the code of the projects.
    CodeADB12.PNG Code A
    CodeBDB12.PNG Code B
    CodeCDB12.PNG Code C
    CodeDDB12.PNG Code D
    CodeEDB12.PNG Code E
    The code is defined in the Project Core Data module of the respective project.
    The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns.
    IstHisto.png Actual load of resource(s)   The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472).
    KapLinie.png Available capacity of resource(s)   The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
    NEWThe limiting line at the top of the bar will be visible despite of overlapping by load data.
    GrundlastLinie.png Basic load of resource(s)   The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load defined for the resource in the Resource Data Sheet.
    NEWThe limiting line at the top of the bar will be visible despite of overlapping by load data.
    Faktor4.png Factor 4 of resource(s)   The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet.
    Faktor5.png Factor 5 of resource(s)   The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet.
    Ueberlast.PNG Overload of resource   The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned).

    From DB 39.5.8

    Symbol Meaning Color Comment
    CodeHisto.png Planned load of resource(s) in the projects The bar color is determined by the project code.
    A.png Code A
    B.png Code B
    C.png Code C
    D.png Code D
    E.png Code E
    The code is defined in the Project Core Data module of the respective project.
    The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns.
    IstHisto.png Actual load of resource(s)   The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472).
    KapLinie.png Available capacity of resource(s)   The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
    NEWThe limiting line at the top of the bar will be visible despite of overlapping by load data.
    GrundlastLinie.png Basic load of resource(s)   The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load defined for the resource in the Resource Data Sheet.
    NEWThe limiting line at the top of the bar will be visible despite of overlapping by load data.
    Faktor4.png Factor 4 of resource(s)   The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet.
    Faktor5.png Factor 5 of resource(s)   The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet.
    Ueberlast.PNG Overload of resource   The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned).

    Up to DB 39.5.8

    Symbol Meaning Color Comment
    CodeHisto.png Planned load of resource(s) in the projects The bar color is determined by the project code.
    A.png Code A
    B.png Code B
    C.png Code C
    D.png Code D
    E.png Code E
    The code is defined in the Project Core Data module of the respective project.
    The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns.
    IstHisto.png Actual load of resource(s)   The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472).
    Kap.png Available capacity of resource(s)   The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
    GrundlastAbDb8.png Basic load of resource(s)   The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load value defined for the resource in the Resource Data Sheet.
    Faktor4.png Factor 4 of resource(s)   The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet.
    Faktor5.png Factor 5 of resource(s)   The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet.
    Ueberlast.PNG Overload of resource   The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned).

    Legend: Bar diagram (project/proposal/resource)

    From DB 39.5.14

    Symbol Meaning Color Comment
    WunschDB14.png Task requested dates   Requested start and Requested end of a task are defined in the Schedule module.
    KalkPRDB14.png Calculated dates of the selected resource for the selected task in the selected project The color of the bar is determined by the code of the respective project. For the meaning of the individual code colors, see the histogram scale. Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.
    ActDB12.png Calculated dates of the selected resource for the selected task in the selected project The bar is white hatched. Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the reported hours worked of the corresponding resource (DT472) or are edited manually.
    Puffer.png Latest task dates   Latest start and Latest end of a task are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.

    From DB 39.5.12

    Symbol Meaning Color Comment
    Wunsch.png Task requested dates   Requested start and Requested end of a task are defined in the Schedule module.
    KalkPRDB12.PNG Calculated dates of the selected resource for the selected task in the selected project The color of the bar is determined by the code of the respective project. For the meaning of the individual code colors, see the histogram scale. Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.
    ActDB12.png Actual dates of the selected resource for the selected task in the selected project   Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from working time recording of the corresponding resource (DT472) or are edited manually.
    Puffer.png Latest task dates   Latest start and Latest end of a task are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.

    Up to DB 39.5.12

    Symbol Meaning Color Comment
    Wunsch.png Task requested dates   Requested start and Requested end of a task are defined in the Schedule module.
    Kalk.png Calculated dates of the selected resource for the selected task in the selected project The color of the bar is determined by the code of the respective project. For the meaning of the individual code colors, see the histogram scale. Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.
    Ist.png Actual dates of the selected resource for the selected task in the selected project   Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the working time recording of the corresponding resource (DT472) or are edited manually.
    Puffer.png Latest task dates   Latest start and Latest end of a task are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.