The documentation from version 39.5.17 of PLANTA project can be found in the new PLANTA Online Help.

Time Recording MOD009ABV (Variant 1 without Comment, without Planned Working Time) DB 39.5.13

Information

  • In the Time Recording module
    • the logged-on user can
      • record his/her hours worked
      • record and send forecasts of remaining effort
      • delete recorded hours worked (make reverse postings)

Stop
  • Below the scale, the calendar preset in @G150 takes effect. It can but does not necessarily have to match with the project, proposal, or resource calendar.
    • If the calendar specified in the @G150 variable is too short, the Time Recording module is displayed completely empty. The corresponding calendar can be adjusted in the Calendar module.

Details sum area

  • In the top area of the module with Actual Total heading, the summarized number of recorded hours worked is displayed for each day below the scale. Next to the heading, the summed up actual weekly value is displayed.

Details project area

  • The projects listed in the module are displayed in groups:
    • Time recording only up to end of current week: Here, projects are displayed for which the Posting type parameter is set to "Actual postings until the end of the current week" in the Project Core Data module.
      • In this area you can record actual hours until the last day of the current week.
    • Time recording also in the future: Here, projects are displayed for which the Posting type parameter is set to "Actual postings also in the future" in the Project Core Data module.
      • In this group, working times can be recorded in the future.
    • My time recording favorites: Here, tasks are displayed with the respective projects which have previously been marked as favorites in one of the two groups mentioned above (Favorite checkbox activated).
      • If tasks are listed in the My time recording favorites group, they are no longer displayed in the two groups mentioned above.
      • In summary this means that the allocation to the two groups mentioned above is done in line with a fixed project criterion which is defined for each project while the third group is optional and is only displayed if the tasks have the "Favorite" property which only takes effect in this module.
    • Finished tasks of the current week
      • In this group, tasks in which one is planned and which have been finished in the current week are displayed (wit the respective projects).

Attention
  • In the module, only projects or tasks are displayed,
    • which are not locked (e.g. via the Locked parameter in the Project Core Data or the Task locked parameter in the Schedule).
    • which are not finished (actual end for project and task are not filled)
    • which are not completed (the Completed checkbox in the Time Recording module is not deactivated)
    • for which the respective project is active
  • Exceptions: locked, finished, completed tasks are displayed in the module if they already have postings in the selected week. For this purpose, see the Not postbale objects (selected week) group.

  • If you force the display of locked projects or tasks and try to record hours worked, the Project/Task locked or Invalid work recording period message is displayed.

Module Variants

Base
  • Hours worked can be recorded.
  • The recorded hours worked can be deleted or corrected.
  • NEW The forecast of remaining effort can be created and dispatched.
Without forecast The same as in the Base module variant, however without forecast fields and buttons.
With request process steps In case particular tasks have request process step assignments, they are displayed in the With Request Process Steps module variant. By clicking on the name of the required process step, you can switch to the Process Step module where you can see and edit the details.
Note: This module variant can only be used if the Request component is employed. At the moment, it is not possible to record hours worked on process steps.

Record Working Hours on Projects/Tasks in which One is Planned

Information
  • If no working hours have been recorded yet, only projects in which the employee is planned directly are displayed initially in the Time Recording module.
  • However, it is possible to add projects in which one is not planned directly to the Time Recording module via the Add other projects/tasks button. Once such projects have been added and hours have been recorded on them, these projects are displayed along with the other projects every time the Time Recording module is opened.

Procedure

  • Extend the required project and task in the left window. There are empty load records for all days of the week by default.
  • Click below the required date in the line of the required weekday in the right window below the scale.
  • Enter the required number of hours.
  • Save.
  • Enter the hours for all required days in the same way.

Browse the calendar

  • In the right window you can scroll to another week
    • via the arrow buttons or
    • by selecting the respective calendar week in the date listbox.
  • This enables you to post actual hours to tasks which are not planned for the current week but have been planned for previous weeks.
  • You can only scroll back beyond the invoicing date. However, it is not possible to record hours which lie before the invoicing date. If a user tries to report hours worked anyway, the Recording not possible: date is earlier than key date. notice is displayed.

Note

  • The Browse calendar function uses the calendar predefined in the @G150 variable. It can but does not necessarily have to match with the project, proposal, or resource calendar.

Record Hours Worked to Further Projects/Tasks

Procedure

  • Click on the ButtonZeiterfassProjVorg.png Add other projects/tasks for time recording button.
    • The Projects and Tasks for Time Recording dialog module is opened.
    • Select the required project from the required listboxes and select the required task and click on the Adopt button.
      • The selected project and the selected task are inserted in the respective group of the Time Recording module. The recording of hours worked can be done as described above.

Record Future Hours Worked (Vacation, Sickness, etc.)

Information
  • The existence of projects for which the Posting type parameter = 1 Actual postings also in the future (overhead costs, ...) is set (in practice, these are mostly overhead cost projects) and the existence of the respective tasks (e.g. vacation) are a requirement for the recording of future hours.

Procedure

  • Move to the week for which you want to record overhead costs by clicking on the arrow buttons.
  • In the Time recording also in the future group, overhead cost projects are displayed with the corresponding tasks in which the resource of the logged-on user is planned.
  • The procedure for creating hours is equal to the procedure in the "Record Hours Worked to Projects/Tasks in which One is Planned" .

Note

  • If the resource of the employee is not directly planned in an overhead project but has permission to record time in this overhead project, the project is not immediately listed in the Time recording also in the future group, but it must first be inserted in the time recording module via the Add Projects and Tasks for Time Recording module. For this purpose see the "Record Hours Worked to Further Projects/Tasks" section.

Send Remaining Effort Forecast

Information

  • In case an employee notices upon completion of a task planned for him/her that the effort is higher than planned, he/she has the option to report them to the project manager responsible in the form of a remaining effort forecast.

Procedure

  • Enter the estimated remaining effort in the Forecast field in the line of the required task in the Time Recording module and save.
  • Click on the Send forecast button in the project line (button with envelope symbol).
  • The Send Info module is opened including an automatically created message.
  • The message contains the following data: sender, actual values of the current week, remaining and forecast values as well as the expected completion date, in case it is filled.
    • The project manager of the project is automatically entered as the recipient.
  • Click on the Send button. The message is automatically sent to the recipient via e-mail.

Delete/Change Recorded Working Hours (Reverse Postings)

Procedure

  • Either correct the required hour values directly below the scale or delete them completely.

Technical details

  • Since reverse postings are saved in DT472 just like regular postings, you can filter them out in individual modules via the Canceled/Reverse posting parameter if you do not want to see them.

         PLANTA project









 
  • Suche in Topic-Namen

  • Suche in Topic-Inhalten
This site is powered by the TWiki collaboration platform Powered by Perl