Cost Types MOD009AWF Up to DB 39.5.0

Description for versions DB 39.5.0


Access path

Information

  • Cost types are used to break down, summarize, and calculate costs. You can define a structure for cost types.
  • Cost types correspond to cost or activity types which are otherwise customary.
  • By specifying a parent (higher level) cost type, the structure can be defined for a summarized representation of costs.
  • Before creating the cost types, you have to make the following decisions:
    • How deep is the cost recording supposed to go?
    • Are conversion factors to be assigned to the cost types as well?
      • Cost types that have no conversion factor are used exclusively for summarizing costs.
      • Cost types with conversion factor take effect upon cost calculation.
        • The P/A/R loads are multiplied by the conversion factor. If a conversion factor has been entered on the resource as well, the factors have an additive effect.
  • A cost type can be specified for the resource assignment and in each individual load record.
  • Cost types can be grouped (cost type groups). In user modules, costs and effort (e.g. the Budget module) are displayed summarized to the cost type groups.

Create Cost Types

Procedure

  • Insert a blank record:
    • If no cost types are available, click on the Insert button.
    • If some cost types already exist, activate the required cost type and click on the Insert button or right.click to select the Insert Cost type context menu command.
  • Allocate the cost type in the Cost type field.
  • Enter the name in the Cost type name field.
  • Fill further data fields.
  • Save.

Note

  • When selecting revenue cost types, no cost type group is assigned in the Cost type group name because
    • all resource type data is summarized in column 0-4 (cost type group column).
    • the revenue resource data (resource type = 8) is not summarized in this group, but treated as an independent one.
    • in the Column field, the value 0 is automatically entered so that revenue resource data can be summarized in this independent group.

Assign Cost Type To The Resource

Procedure

  • In the Resource Data Sheet module, select the required resource and in the Default cost type field select the cost type which will be automatically applied when the resource is planned.
  • Save.

Change Cost Type per Load Record

Procedure

  • Upon resource assignment, the default cost type can be changed for each separate load record:
    • Open the Schedule module with the Base variant for the respective project.
    • Select the resource to which a cost type is to be assigned.
    • Display the Cost type field in the load record (expand the tree structure of the resource) and select the required cost type from the listbox.
    • Save and recalculate the schedule by clicking on the calculation button in the toolbar.

Notes

  • Cost types of existing load records are not overwritten in recalculation.
  • If the cost type on the resource assignment is changed, the schedule must be
Topic attachments
I Attachment History Size Date Comment
Pngpng ButtonTR.png r1 1.5 K 2010-12-21 - 09:28  
Pngpng calculate_schedule.png r1 0.6 K 2018-10-04 - 08:50  

         PLANTA project









 
  • Suche in Topic-Namen

  • Suche in Topic-Inhalten
This site is powered by the TWiki collaboration platform Powered by Perl