Description |
Adher. to schedule |
Adh. to total float |
Adher. to capacity |
Target |
How much overload arises for the employees if the dates are to be adhered to? How much buffer is available? |
How much overload arises for employees if the dates are adhered to? How long to tasks last taking account of capacity and requested dates? |
How long does a project last with predefined effort and limited capacity (no overload)? |
Description of the planning method |
Task duration and dates are adhered to. If the task durations are longer than the remaining time horizon, the end date is shifted. Overloads are shown |
The project receives a requested end date. The remaining duration of the task is calculated according to the resource effort. Floats are exploited. The overloads are smoothed. End dates are adhered to as far as the remaining time horizon is sufficient for the planned duration of the task. |
The duration of a task is determined from- Effort
- Available capacity
- CAPload profile
- Option: Planning with max. load/day
|
Planning |
Usually, Planned duration or alternatively Req. start - Req. end are entered (Req. start - Req. end dominates the Planned duration).If no Planned duration has been entered, it is calculated by Req. start - Req. end. Planning without load curves: When inputting the Planned duration of the task, the planned effort of the resource is allocated to the duration evenly. If NO Planned duration of the task is entered, the system calculates the Remaining duration of the task by means of resource effort, CAP load profile and Max. load/day. |
Usually, planned duration, or alternatively Requested start - Req. end.If no Planned duration has been entered, it is calculated with Req. start - Req. end.When you enter the Planned duration of the task, the Planned effort of the resource is allocated evenly to the duration.If NO Planned duration of the task is entered, the system calculated the Remaining duration of the task by means of the resource effort, CAP load profile, and Max. load/dayRegardless of whether Planned duration has been entered or not, the Remaining duration is extended, as far as the Planned effort cannot be accomplished within the predefined time, or within the available float.The requested date is overrun in consideration of the links if the duration of the tasks is too long. |
No input of task duration or TA Req. start/Req. end required. Only input of effort in h for allocated resources. For the parameters, see above. |
For tasks with resource assignments:.Extend tasks before MA has reported hours. |
In order to extend the task duration in days before hours have been reported, the Planned duration of the task is extended. Alternatively the effort can also be increased if the CAP load profile has been selected.In order to increase the effort, the Planned effort is increased. |
Increase of Planned duration, or Planned effort on employee level, provided that the CAP load profile has been selected. |
The Planned effort is increased on resource level, provided that the CAP load profile has been selected. |
For tasks without resource assignment:Extend tasks without actual start date. |
Increase Planned duration on task level. |
Increase Planned duration on task level. |
Increase Planned duration on task level. |
For tasks without resource assignment:Extend tasks with actual start date. |
Extend Remaining duration on task level or extend Requested end.New: Remaining duration is calculated depending on the actual date. Remaining duration = Planned duration – Actual duration , whereas: Actual duration = today - Actual start date.As before, open tasks remain with 1 remaining day as a reminder. |
Extend Remaining duration on task level or extend Requested end.New: Remaining duration is calculated regardless of the actual date. Remaining duration = Planned duration – Actual duration , whereas: Actual duration = today - Actual date.As before, open tasks remain with 1 remaining day as a reminder. |
|
Application case |
Procedure |
Result |
Plan resource without dates |
- Assign resource to task
- Enter effort
- Calculate project
|
|
Plan resource with Requested start |
|
Note- The planning time of the resource is possibly shorter than the length of the task.
|
Plan resource with Requested end |
|
Note- The planning time of the resource is possibly shorter than the length of the task.
|
Plan resource with TAR Requested end |
|
Note- The planning time of the resource is possibly shorter than the length of the task.
|
Plan resource from .... to .... |
- Assign resource to task and enter effort
- Enter start or end date in resources (TAR Requested start/Requested end)
- Consider task date limits
- Calculate project
|
Note- The planning time of the resource is possibly shorter than the length of the task.
|
Application case |
Procedure |
Result |
Plan resource without dates |
- Assign resource to task
- Enter effort
- Calculate project
|
|
Plan resource with Requested start |
- Assign resource to task and enter effort
- Enter start date in resources (TAR Requested start
- Calculate project
|
Note - The planning time of the resource is possibly shorter than the length of the task.
- If float is required, the task duration or the resource load can be extended backward.
|
Plan resource with TAR Requested end |
- Assign resource to task and enter effort
- Enter end date in resources (TAR Requested end)
- Calculate project
|
Note - The planning time of the resource is possibly shorter than the length of the task.
- If float is required, the task duration or the resource load can be extended forward.
|
Plan resource from .... to .... |
- Assign resource to task and enter effort
- Enter start or end date in resources (TAR Requested start/Requested end)
- Consider task date limits
- Calculate project
|
Note - The planning time of the resource is possibly shorter than the length of the task.
- no float exploitation by the resource within the task period.
|
No. |
Application case |
Result |
1 |
Planning with adherence to schedule with several resources- Task with several task resources
- The Planned duration of the task is preset.
- Planning type = adherent to schedule
|
- The planning is carried out by the scheduling along the duration of the task.
- Overload is not prevented by scheduling.
- Overloads are not displayed.
|
2 |
Planning with adherence to total float with several resources- Task with several task resources
- The Planned duration of the task is preset.
- Planning type = adherent to total float
|
- Scheduling carries out the planning along the duration of the task.
- Scheduling does not prevent overload.
- The float of overloaded resources is used to prevent possible overloads. If there is not sufficient float, resources will be overloaded
- Resource 1 with overload: Float is used
- Resource 2 without overload: Starts at the earliest start date.
|
3 |
Planning with adherence to capacity- Task with several task resources
- The Planned duration of the task is preset.
- Planning type = adherent to capacity
|
- The planning of the task by the scheduling is carried out without consideration of the Planned duration of the task.
- Resources are not overloaded.
- The float of overloaded resources is used:
- Resources are not planned on non-working days.
|
4 |
Resources with vacation, planning with adherence to schedule- Resource with vacation
- Linear load
- The vacation duration is shorter than the task duration.
- Planning type = adherent to schedule
|
- The planning is carried out in a block by the date scheduling.
- The resource is not planned by the scheduling during its vacation.
- On working days, the resource is possibly planned with overloads.
|
5 |
Resources with vacation < task duration, planning with adherence to schedule- Resource with vacation
- Linear load
- The vacation duration is longer than the task duration.
- Planning type = adherent to schedule
|
- The planning is carried out by the date scheduling before or, the latest, at the beginning of vacation.
- Due to the unavailability of the resource, the load is marked as overload during vacation.
- If the entire task is during vacation, loading begins on the calculated start date of the task.
|
6 |
Planning with vacation- Vacation is entered for a resource,
- Linear load profile
- The vacation duration is shorter than the task duration.
- Planning type = adherent to total float
|
- The planning by scheduling is carried out in a block outside the vacation time.
- Available float is used. If the float s used, the resource is overloaded by the scheduling.
- The resource is not planned during vacation.
- The planning is not splitted.
|
7 |
Planning with adherence to capacity with vacation- Vacation is entered for a resource,
- Linear load profile
- The vacation duration is shorter than the task duration.
- Planning type = adherent to capacity
|
- The planning by scheduling is carried out in a block outside the vacation time.
- Available float is not planned during vacation.
|
8 |
Planning with adherence to total float with Requested end and Fix = 0- Task with several task resources.
- The Planned duration is preset.
- Requested end on a task
- Fix TA parameter = 0
- The vacation of a resource is shorter than the task.
- Planning type = adherent to total float
|
- The planning of the task is carried out by the scheduling at the Requested end.
- By setting the Fix parameter = 0, the Requested end is overrun if necessary.
- No consideration of float and possible overload since it is loaded with adherence to schedule due to the input of a Requested end.
- The task is not moved.
|
8.1 |
Planning with adherence to total float with Requested end and Fix = 1- Task with several task resources.
- The Planned duration is preset.
- Requested end on task
- Fix TA parameter = 1
- The vacation of a resource is shorter than the task.
- Planning type = adherent to total float
|
- The planning of the task is carried out by the scheduling at the Requested end.
- By setting the Fix parameter = 1, the Requested end is met and loaded with adherence to schedule.
- No consideration of float and overload.
- The task is not moved.
|
8.2 |
Planning with adherence to total float with TAR Requested start Task with several task resources |
|
9 |
Planning with adherence to total float with Requested end and Fix = 1 |
- Using the Fix = 1 parameter, the task is loaded with adher. to capacity.
- Overloads may occur.
|
10 |
Planning a task, which has a predecessor, with adherence to schedule, Requested start and Fix = 0- Vacation is entered for a resource
- Linear load profile
- The vacation duration is shorter than the task duration.
- Task with predecessor and Requested start, Fix = 0
- Planning type = adherent to schedule
|
- The task does not start at the Requested start, but after the predecessor has finished.
- The vacation of the resource is taken into consideration.
- Remaining duration = Planned duration
|
11 |
Planning with adherence to total float with effort > Availability- Task with several task resources
- The Planned duration is preset.
- The capacity required for the desired duration exceeds the available capacity
- Planning type = adherent to total float
|
- The scheduling uses available float.
- If there is no more float available, planning is carried out in a block at the latest time possible.
|
12 |
Planning with adherence to capacity with effort > availability- Task with several task resources
- The Planned duration of the task is preset.
- The capacity required for the desired duration exceeds the available capacity.
- Planning type = adherent to capacity
|
- Scheduling uses available float. Scheduling is delayed until loading in is possible in a block. Possibly the project end date is exceeded.
- The resource is not planned during vacation, the task is not splitted
|
13 |
Planning with adherence to total float of a task with predecessor, Requested end and Fix = 0- Vacation is entered for a resource
- Linear
- The vacation duration is shorter than the task duration.
- Task with predecessor and Requested start
- Fix TA parameter = 0
- Planning type = adherent to total float
|
- The task does not start at the Requested start, but after the predecessor has finished.
- The vacation of the resource is taken into consideration.
- Remaining duration = Planned duration
- Float is not used since a task with date is always loaded with adherence to schedule automatically.
|
14 |
Planning with adherence to capacity of a TA with predecessor, Requested end and Fix = 0- Vacation is entered for a resource.
- Linear
- The vacation duration is shorter than the task duration.
- Task with predecessor and Requested start
- Fix TA parameter = 0
- Planning type = adherent to capacity
|
- The task does not automatically end at the Requested end, but after the predecessor has finished.
- The vacation of the resource is taken into consideration.
- Remaining duration = Planned duration
- Float is not used since a task with date is always loaded with adherence to schedule automatically.
|
15 |
Calc. start when several task resources report- Planning of several resourcen to one task and reporting of hours:
- just as planned
- earlier than planned
- later than planned
|
- The resources are planned with their remaining effort from the TAR Actual start by the scheduling.
- If the day after the Actual start is no working day, the resource is planned on the next working day.
- The resource is possibly overloaded.
|
16 |
Reporting during vacation- several resources are assigned to a task.
- A resource is on vacation over the complete task duration, however he/she reports hours.
|
- The planning of the resources without vacation is carried out by the scheduling according to the default specifications.
- The resource which has reported during vacation is planned for the first working day after the report.
- The resource is possibly overloaded.
|