Status MOD009C97 New from DB 39.5.0

Access path

Information

  • In this module, you can view existing status reports and create new ones.
    • Only reports for the respective program are created, not for the projects assigned to it.
  • In order to create a program status report, you have to assign status reports to the projects assigned to the program. For this purpose, see the Project Status Reports section.

Note

  • If the module described here is opened in the program and at the same time you make changes to another module of the project panel which have an influence on the data in the module described here and save them (or if another user has done so), the Refresh button will be displayed in the lower left corner of this module. Click on this button in order to refresh the displayed data.

Current Status

Information

  • The Current status area of the module shows current planning data of the project divided into several subareas (Costs, Effort, Dates, etc.). In the Costs and Dates subareas, summed-up (summarized) values of the projects assigned to the program are displayed.
    • When you create a new program status report, current program data is included. However, the current data of the assigned projects will not be included. The selected project status reports are the source of the project data in the program status report. This may cause the displayed (summarized) project effort/cost values in the Current status area in the Status module to deviate from those in the Program Status Report.

Header data of the subareas

From DB 39.5.7

  • In the header area of each subarea, you can
    • submit the manager’s estimate on the respective factor of the program
      • The estimate is visualized by a thumb symbol and can be changed via mouse-click in the » field.
        • For planning objects for which no estimate has been entered yet, no thumb symbol is displayed here.
    • insert Comments
  • In the Costs, Effort, and Dates subareas, the following data is displayed additionally:
    • The current calculated status of the deviation values of the respective factor: Total vs. budget for costs and effort, and requested vs. calculated for dates
      • This is visualized by traffic light triangles with a specification of the percentage deviation of costs and effort, and the deviation of dates in days.
        • red: costs/effort overrun by more than 5%, date delay of more than 5 days
        • yellow: costs/effort overrun by up to 5%, date delay of up to 5 days
        • green: costs/effort not overrun, no delay
        • NEW For dates, both the program end date deviation value and the master milestone end date deviation value are specified. The respective traffic light, however, refers to the worst of both values.
    • The program trend is visualized in comparison to the status frozen in the active (last released) report.
      • This is visualized by trend arrows with a specification of the percentage deviation of costs and effort and date deviation in days.
        • Arrow up = negative trend, arrow down = positive trend.

Up to DB 39.5.7

  • In the header area of each subarea, you can
    • submit the manager’s estimate on the respective factor of the program
      • The estimate is visualized by a thumb symbol and can be changed via mouse-click in the » field.
        • For planning objects for which no estimate has been entered yet, no thumb symbol is displayed here.
    • insert Comments
  • In the Costs, Effort, and Dates subareas, the following data is displayed additionally:
    • The current calculated status of the deviation values of the respective factor: Total vs. budget for costs and effort, and requested vs. calculated for dates
      • This is visualized by traffic light triangles with a specification of the percentage deviation of costs and effort, and the deviation of dates in days.
        • red: costs/effort overrun by more than 5%, date delay of more than 5 days
        • yellow: costs/effort overrun by up to 5%, date delay of up to 5 days
        • green: costs/effort not overrun, no delay
    • The program trend is visualized in comparison to the status frozen in the active (last released) report.
      • This is visualized by trend arrows with a specification of the percentage deviation of costs and effort and date deviation in days.
        • Arrow up = negative trend, arrow down = positive trend.
  • Detailed information of the subareas (after expanding)

    From DB 39.5.9

    • When expanding the respective subarea, the following data will be displayed:
      • Costs
        • current summed-up cost and cost budget values of all projects assigned to the program as well as the program cost budget
        • two program cost trend graphics which show cost values from the released status reports of the program for which the Cost trend analysis checkbox is activated in the Configure Trend Analysis module.
          • Graphic 1 shows cumulated total costs.
          • Graphic 2 shows total costs per month.
          • The two graphics only display the values up to today.
      • Effort
        • current summed-up effort and effort budget values of all projects assigned to the program as well as the program effort budget
        • two program effort trend graphics which show effort values from the released status reports of the program for which the Cost trend analysis checkbox is activated in the Configure Trend Analysis module.
          • Graphic 1 shows cumulated total effort.
          • Graphic 2 shows total effort per month.
          • The two graphics only display the values up to today.
      • Dates
        • current dates and duration of the program
        • current dates of the milestones and master milestones
        • Milestone/master milestone trend graphics which show the values from the program baseline and from all released program status reports
      • Risks/Opportunities
        • current damage and gross profit values of the program which result from risks or opportunities
        • as well as in the respective section (Risks / Opportunities)

    From DB 39.5.7

    • When expanding the respective subarea, the following data will be displayed:
      • Costs
        • current summed-up cost and cost budget values of all projects assigned to the program as well as the program cost budget from the current planning
        • two program cost trend graphics which show cost values from the released status reports of the program for which the Cost trend analysis checkbox is activated in the Configure Trend Analysis module.
          • Graphic 1 shows cumulated total costs.
          • Graphic 2 shows total costs per month.
          • The two graphics only display the values up to today.
      • Effort
        • current summed-up cost and cost budget values of all projects assigned to the program as well as the program effort budget from the current planning
        • two program effort trend graphics which show effort values from the released status reports of the program for which the Cost trend analysis checkbox is activated in the Configure Trend Analysis module.
          • Graphic 1 shows cumulated total effort.
          • Graphic 2 shows total effort per month.
          • The two graphics only display the values up to today.
      • Dates
        • current dates and duration of the program
        • current dates of the milestones and master milestones
        • Milestone/master milestone trend graphics which show the values from the program baseline and from all released program status reports
      • Risks/Opportunities
        • current damage and gross profit values of the program which result from risks or opportunities
        • as well as in the respective section (Risks / Opportunities)
          • individual risks and opportunities including their measures
          • NEW In the Risks section, a matrix diagram which shows the number of risks measured against their Damage extent and its Probability of occurrence in the high, medium and low categories is additionally visualized.

    From S 39.5.18

    • When expanding the respective subarea, the following data will be displayed:
      • Costs
        • current summed-up cost and cost budget values of all projects assigned to the program as well as the program cost budget from the current planning
        • two cost trend graphics ( provided that the Earned Value Analysis is activated), which display cost values from the released status reports of the project for which the Cost trend analysis checkbox is activated in the Configure Trend Analysis module.
          • Graphic 1 shows cumulated total costs.
          • Graphic 2 shows total costs per month.
          • The two graphics only display the values up to today.
      • Effort
        • current summed-up effort and effort budget values of all projects assigned to the program as well as the program effort budget from the current planning
        • two effort trend graphics ( provided that the Earned Value Analysis is activated), which show effort values from released status reports for which the Cost Trend Analysis checkbox is activated in the Configure Trend Analysis module.
          • Graphic 1 shows cumulated total effort.
          • Graphic 2 shows total effort per month.
          • The two graphics only display the values up to today. * Dates
        • current dates and duration of the program
        • current dates of the milestones and master milestones
        • Milestone/master milestone trend graphics which show the values from the program baseline and from all released program status reports
      • Risks/Opportunities
        • current damage and gross profit values of the program which result from risks or opportunities
        • as well as individual risks/opportunities including their measures in the respective (Risks / Opportunities) section

    From DB 39.5.5

    • When expanding the respective subarea, the following data will be displayed:
      • Costs
        • current summed-up cost and cost budget values of all projects assigned to the program as well as the program cost budget from the current planning
        • two cost trend graphics (NEW provided that the Earned Value Analysis is activated) which show cost values from the released status reports of the program for which the Cost trend analysis checkbox is activated in the Configure Trend Analysis module.
          • Graphic 1 shows cumulated total costs.
          • Graphic 2 shows total costs per month.
          • The two graphics only display the values up to today.
      • Effort
        • current summed-up effort and effort budget values of all projects assigned to the program as well as the program effort budget from the current planning
        • two effort trend graphics (NEW provided that the Earned Value Analysis is activated) which show effort values from the released status reports of the program for which the Cost trend analysis checkbox is activated in the Configure Trend Analysis module.
          • Graphic 1 shows cumulated total effort.
          • Graphic 2 shows total effort per month.
          • The two graphics only display the values up to today.
      • Dates
        • current dates and duration of the program
        • current dates of the milestones and master milestones
        • Milestone/master milestone trend graphics which show the values from the program baseline and from all released program status reports
      • Risks/Opportunities
        • current damage and gross profit values of the program which result from risks or opportunities

    Up to DB 39.5.5

    • When expanding the respective subarea, the following data will be displayed:
      • Costs
        • current summed-up cost and cost budget values of all projects assigned to the program as well as the program cost budget from the current planning
        • two effort trend graphics which show cost values from the released status reports of the program for which the Cost trend analysis checkbox is activated in the Configure Trend Analysis module.
          • Graphic 1 shows cumulated total costs.
          • Graphic 2 shows total costs per month.
          • The two graphics only display the values up to today.
      • Effort
        • current summed-up effort and effort budget values of all projects assigned to the program as well as the program effort budget from the current planning
        • two program effort trend graphics which show effort values from the released status reports of the program for which the Cost trend analysis checkbox is activated in the Configure Trend Analysis module.
          • Graphic 1 shows cumulated total effort.
          • Graphic 2 shows total effort per month.
          • The two graphics only display the values up to today.
      • Dates
        • current dates and duration of the program
        • current dates of the milestones and master milestones
        • Milestone/master milestone trend graphics which show the values from the program baseline and from all released program status reports
      • Risks/Opportunities
        • current damage and gross profit values of the program which result from risks or opportunities

    Details

    • From the Current status area, new reports (baseline, status, final report) can be created.

    Create Baseline Report

    Information
    • The baseline is a status report in which the approved and adopted planning is displayed and which is regarded as a reference or comparison report in the program progress.

    Procedure

    • If necessary, click on the Refresh button at the lower left module margin in order to refresh the data displayed in the module.
      • The Refresh button is displayed if a change has been made and was saved in another module of the project panel that might have an effect on data in the Status module.
    • Make necessary changes to the Current status area (only estimates and comments possible).
    • Click on the Create baseline button.
      • If no baseline report exists, the following message is displayed: Do you really want to create the baseline?
        • Confirm the message with Yes.
      • If a baseline report already exists,
        • the Baseline report available for project! message is displayed when you try to Baseline report available for xxx!.
        • Confirm this message with OK.
        • Confirm the Do you really want to create a baseline? message with Yes.
      • A new program baseline report is created, in which the current status of the program and the status of the projects assigned to the program from the selected project status reports are frozen. The created baseline report is displayed in the Status report area with "Baseline" report status. To open the report, click on the link on the ID of the report. This will take you to the Program Status Report module.

    Details

    From DB 39.5.5

    • NEW When you create a baseline report, an automatic recalculation of the entire program data (dates, budget, etc.) is carried out. The assigned projects are not calculated, since program status reports do not use the current project data but the data from the assigned project status reports.
    • If you want to create a baseline for a program which already has an actual end date, the This planning object already has an actual end. Create baseline anyway? prompt is displayed.
      • Yes: The baseline is created.
      • No: The task is canceled.

    Up to DB 39.5.5

  • If you want to create a baseline for a program which already has an actual end date, the This project already has an actual end. Create baseline anyway? prompt is displayed.
    • Yes: The baseline is created.
    • No: The task is canceled.
  • Note

    • If a baseline report is created and a status report is created afterwards (or the other way around) without changes having been made in the mean time, the display of the master milestones in the chart in the Dashboard is the same for all three planning statuses (current status = active report = baseline), as it is supposed to be.

    Create Status Report

    Procedure

    • Click on the Refresh button on the bottom left module margin, so that the most current project data is displayed in the module.
      • The Refresh button is displayed if a change has been made and was saved in another module of the project panel that might have an effect on data in the Status module.
    • Make necessary changes to the Current status area (only estimates and comments possible).
    • Click on the Create status report button.
    • Confirm the Are all entries (estimates/comments) and assignments (status reports to planning objects) complete and up-to-date? message with Yes. The status report in which the current status of the program and the status of the projects assigned to the program from the selected project status reports are frozen is created. You automatically switch to the Program Status Report module in which the data of the created status report is displayed. Here, the status report can and should be released (in opposite to the baseline which is released per se).
      • After its creation, if a status report is
        • released, it is displayed in the Status reports area in the Status module with last released report status.
        • not released, it is displayed in the Status reports area in the Status module with created report status.
    • If it is a finished project (all tasks have an actual end date), a query is displayed, asking whether a final report is to be created. If the query is negated, the creation is not aborted but a normal status report (no final report) is created.

    Details

    New from DB 39.5.5

    • NEW When a final report is created, an automatic recalculation of the entire project/program data (dates, budget, etc.) is carried out. The assigned projects are not calculated, since program status reports do not use the current project data but the data from the assigned project status reports.

    Notes

    • You cannot create a status report if a final report already exists.
    • Status reports can only be created for active planning objects (Status = 1 (active)).

    Create Final Report

    Information

    • If a report is created for a programfor which an Actual end has already been set, such a report is called a final report.

    Procedure

    • Click on the Create final report button.
    • Confirm the Have you refreshed your estimates and comments? message with Yes. The status report in which the current status of the program and the status of the projects assigned to the program from the selected project status reports are frozen is created. You automatically switch to the Program Status Report module in which the data of the created status report is displayed.
      • In the Status Report module, you can and should release the status report (unlike the baseline which is a released status report per se).
      • If after its creation a status report is
        • released, it is displayed in the Status reports area in the Status module with last released report status.
        • not released, it is displayed in the Status reports area in the Status module with open final report report status.

    Details

    New from DB 39.5.5

    • NEW When a final report is created, an automatic recalculation of the entire project/program data (dates, budget, etc.) is carried out. The assigned projects are not calculated, since program status reports do not use the current project data but the data from the assigned project status reports.

    Note

    • As soon as a final report has been created, no further status report can be created.

    Status Reports

    Information
    • In this area, all projects assigned to the program are listed.
    • They must have a status report assignment in the Project status report field so that a program status report can be created.

    Procedure

    From DB 39.5.12

    • Click on the arrow button next to the Project Status Report field to assign a status report to a project.
      • A dialog module is opened in which all released status reports of the project are listed.
        • Activate the NEW Select checkbox for the required project and click on the Assign selected status report button. The status report is automatically assigned to the selected project and the dialog module is closed.

    Up to DB 39.5.12

  • Click on the arrow button next to the Project Status Report field to assign a status report to a project.
    • A dialog module is opened in which all released status reports of the project are listed.
      • Click on the link on the ID of the required report. It is automatically assigned to the selected project and the dialog module is closed.
  • Note

    • If a status report has been assigned to a project in the Project status report field, the field can no longer be emptied. You can only replace the selected report by another one.

    Program Status Reports

    Information
    • In the Program status report area, the already existing status reports of the program are listed and a basic overview of the frozen status of different factors in the respective report is provided.
    • By clicking on the report ID, you can open and view the corresponding report with detailed data in the Program Status Report module.

    Configure Trend Analysis

    Information

    • From the Status report area, you can switch to the Configure Trend Analysis module by clicking on the Configure trend analysis button. In this module, you can define the status reports that should be considered in trend analyses or the comparison of planning states.


    See also: Program Status Report

    Topic attachments
    I Attachment History Size Date Comment
    Pngpng SF_Status.PNG r1 0.4 K 2014-03-03 - 19:07  

             PLANTA project









     
    • Suche in Topic-Namen

    • Suche in Topic-Inhalten
    This site is powered by the TWiki collaboration platform Powered by Perl