In the header area of each subarea, you can
- submit the manager’s estimate on the respective factor
- The estimate is visualized by a thumb symbol and can be changed via mouse-click in the » field. * For planning objects for which no estimate has been entered yet, no thumb symbol will be displayed here.
- insert Comments
In the
Costs,
Effort, and
Dates subareas, the following data will be displayed additionally:
- The current calculated status of the deviation values of the respective factor: Total vs. budget for costs and effort and requested vs. calculated for dates.
- This is visualized by traffic light triangles with a specification of the percentage deviation of costs and effort, and the deviation of dates in days.
- red: costs/effort overrun by more than 5%, date delay of more than 5 days
- yellow: costs/effort overrun by up to 5%, date delay of up to 5 days
- green: costs/effort not overrun, no delay
- NEW For dates, both the project/program end date deviation value and the master milestone end date deviation value are specified. The respective traffic light, however, refers to the worst of both values.
- The project trend is visualized in comparison to the status frozen in the active (last released) report.
- This is visualized by trend arrows with a specification of the percentage deviation of costs and effort and date deviation in days.
- Arrow up = negative trend, arrow down = positive trend.