The documentation from version 39.5.17 of PLANTA project can be found in the new PLANTA Online Help.

Work Reporting MOD009ABV Up to DB 39.5.13

Description for versions DB 39.5.13


Access path

Information

Stop

  • Below the scale, the calendar preset in @G150 takes effect. It can but does not necessarily have to match with the project, proposal, or resource calendar.
    • If the calendar specified in the @G150 variable is too short, the Work Reporting module is displayed completely empty. The corresponding calendar can be adjusted in the Calendar module.

Details

From DB 39.5.12

  • Depending on whether the hours to be worked function is (de)activated, the module is divided into one or two areas.
    • Hours to be worked (only if hours to be worked are activated)
      • The hours to be worked are displayed for each day of the period defined for hours to be worked.
      • The displayed value is compared for each day against the total value of work reporting for this day. For this purpose see traffic light information in the Total area.
    • Total
      • In the Hours worked rep. only until end of current week subarea, projects are displayed for which the Time recording also in future (overh. costs) value is selected in the Posting type parameter in the Project Core Data module.
        • In this area, you can report actual hours until the last day of the current week.
      • In the Hours worked rep. also for the future (overhead costs, ...) area, projects are displayed for which the Time recording also in future (overh. costs) value is selected for the Posting type parameter in the Project Core Data module.
        • In this area, you can also report future hours
      • If the hours to be worked function is activated, a traffic light function which displays whether the hours to be worked have been exceeded (red) or fallen below (yellow) is additionally placed below the scale in this area. If the number of reported hours is the same as that defined as hours to be worked, there is no color highlighting.
        • If the hours to be worked function is activated but the hours to be worked values have not yet been defined for a resource, the traffic light for this resource is always red.

From DB 39.5.11

  • Depending on whether the hours to be worked function is (de)activated, the module is divided into one or two areas.
    • Hours to be worked (only if hours to be worked are activated)
      • The hours to be worked are displayed for each day of the period defined for hours to be worked.
      • The displayed value is compared for each day against the total value of work reporting for this day. For this purpose see traffic light information in the Total area.
    • Total
      • In the Actual postings only until today subarea, projects are displayed for which the Actual postings only until today value is selected for the Posting type parameter in the Project Core Data module.
        • In this area, you can report actual hours until the last day of the current week.
      • In the Actual postings also for the future (overhead costs, ...) area, projects are displayed for which the Act. postings also for the future (overhead costs,) value is selected for the Posting type parameter in the Project Core Data module.
        • In this area, you can also report future hours
      • If hours to be worked function is activated, a traffic light function is stored below the scale in this area, which displays whether the hours to be worked have been exceeded (red) or fallen below (yellow). If the number of reported hours is the same as that defined as hours to be worked, there is no color highlighting.
        • If the hours to be worked function is activated but the hours to be worked values have not yet been defined for a resource, the traffic light for this resource is always red.
  • From DB 39.5.0

  • Depending on whether the hours to be worked function is (de)activated, the module is divided into one or two areas.
    • Present (only if the hours to be worked function is activated) NEW
      • The hours to be worked are displayed for each day of the period defined for hours to be worked.
      • The displayed value is compared for each day against the total value of work reporting for this day. For this purpose see traffic light information in the Total area.
    • Total
      • In the Actual postings only until today subarea, projects are displayed for which the Actual postings only until today value is selected for the Posting type parameter in the Project Core Data module.
        • In this area, you can report actual hours until the last day of the current week.
      • In the Actual postings also for the future (overhead costs, ...) area, projects are displayed for which the Act. postings also for the future (overhead costs,) value is selected for the Posting type parameter in the Project Core Data module.
        • In this area, you can also report future hours
      • If hours to be worked function is activated, a traffic light function is stored below the scale in this area, which displays whether the hours to be worked have been exceeded (red) or fallen below (yellow). If the number of reported hours is the same as that defined as hours to be worked, there is no color highlighting.
        • If the hours to be worked function is activated but the hours to be worked values have not yet been defined for a resource, the traffic light for this resource is always red.
  • Up to DB 39.5.0

  • The module is divided into two areas:
    • In the Actual postings only until today area, only projects are displayed for which the Actual postings only until today value is selected in the Posting type parameter in the Project Core Data module.
      • In this area, you can report actual hours until the last day of the current week.
    • In the Actual postings also for the future (overhead costs,) area, only projects are displayed for which the Act. postings also for the future (overhead costs,) value is selected in the Posting type parameter in the Project Core Data module.
      • In this area, you can also report future hours
  • Notes

    From DB 39.5.4

    • In this module, only those projects and tasks are displayed for which the current resource is scheduled and which are not locked (e.g. via the Locked parameter in the Project Core Data or the Task locked parameter in the Schedule).
    • If you enforce the display of locked projects or tasks and try to report hours worked, one of the following messages is displayed: Project/Task locked or Invalid work reporting period.
    • NEW The tasks that were finished in the current week are displayed in the Completed tasks of current week section.

    Up to DB 39.5.4

  • In this module, only those projects and tasks are displayed for which the current resource is scheduled and which are not locked (e.g. via the Locked parameter in the Project Core Data or the Task locked parameter in the Schedule).
  • If you enforce the display of locked projects or tasks in any way and try to report hours worked, one of the following messages is displayed: Project/Task locked or Invalid work reporting period.
  • Module Variants

    From DB 39.5.0

    Base
    With request process steps In case particular tasks have request process step assignments, they are displayed in the With Request Process Steps module variant. By clicking on the name of the required process step, you can switch to the Process Step module where you can see and edit the details.
    Note: This variant can only be used when the Request component is employed. At the moment, it is not possible to report hours worked to process steps.
    Without forecast NEW Since the forecast function has been moved to the Base variant, this variant is a simplified module variant without forecast fields and buttons.

    Up to DB 39.5.0

    Base
    • Working hours can be created.
    • Reverse postings can be made.
    With request process steps In case particular tasks have request process step assignments, they are displayed in the With Request Process Steps module variant. By clicking on the name of the required process step, you can switch to the Process Step module where you can see and edit the details.
    Note: This variant can only be used when the Request component is employed. At the moment, it is not possible to report hours worked to process steps.
    Forecast In this module variant, you can create forecasts of remaining effort and send them via mail.

    Report Hours

    Report to Own Tasks

    Procedure

    • In the left window, all projects and tasks for which the current employee is scheduled as a resource are displayed.
    • Open the required project.
    • Click in the field below the required date in the line of the required task in the right window.
    • Enter the required number of hours.
    • Save.
      • A load record is created below the respective task line.
    • Enter the hours for all required days in the same way.
    • Expand the tree structure of the task in question in the left window. Here, you can see the load records in tabular form.
      • In the Comment field you can write a comment on the load record.
      • If the date is changed manually in the Load date field, the load record is automatically moved under the scale as well.

    From DB 39.5.0

    Browse the calendar
    • In the right window you can scroll to another week
      • via the arrow buttons or
      • by selecting the respective calendar week in the date listbox.
    • This enables you to post actual hours to tasks which are not planned for the current week but which have been planned for previous weeks.
    • You can only scroll back beyond the invoicing date. However, it is not possible to record hours which lie before the invoicing date. If a user tries to report hours worked anyway, the Recording not possible: date is earlier than key date. notice is displayed.

    Note

    • The browse function uses the calendar predefined in the @G150 variable. It can but does not necessarily have to match with the project, proposal, or resource calendar.

    Up to DB 39.5.0

    Arrow buttons
    • You can scroll to other weeks using the arrow buttons in Window 2.
    • This enables you to post actual hours to tasks which are not planned for the current week but which have been planned for previous weeks.
    • You can only scroll back beyond the invoicing date. However, it is not possible to record hours which lie before the invoicing date. If a user tries to report hours worked which are earlier than the invoicing date anyway, the Reporting not possible: date is before invoicing date. notice is displayed.

    Report to Other Projects/Tasks

    Procedure

    From DB 39.5.7

    • Click on the NEW Post to further projects/tasks button.
      • As a result, you switch to the Reporting Hours Worked module.
      • In this module, the employee can report his/her hours worked for tasks and process steps for which he/she is scheduled, as well as for those tasks in which the resources the current employee has access to are planned (controlled by the resource structure code).

    Up to DB 39.5.7

  • Click on the Post to unplanned tasks button.
    • As a result, you switch to the Reporting Hours Worked module.
    • In this module, the employee can report his/her hours worked for tasks and process steps for which he/she is scheduled, as well as for those tasks in which the resources the current employee has access to are planned (controlled by the resource structure code).
  • Post Hours in the Future

    Information

    • The existence of projects for which the Posting type parameter = 1 Actual postings also in the future (overhead costs, ...) is set (in practice, these are mostly overhead cost projects) with the respective tasks (e.g. vacation) is a requirement for reporting future hours.

    Procedure

    From DB 39.5.12

    • Move to the week for which you want to report overhead costs by pressing the arrow buttons.
    • In the Time recording also in future (overh. costs, ...) area, overhead cost projects are displayed with their corresponding tasks.
    • Click on the line of the required overhead cost task in the scale area below the required date and enter the hours.
    • Save.
      • A load record is created and can be viewed and edited in the left window by expanding the tree structure of the respective task.
        • In the Comment field you can write a comment on the load record.
        • If the date is changed manually in the Load date field, the load record is automatically moved under the scale as well.
    • Enter the hours for all required days in the same way and save.

    Up to DB 39.5.12

  • Move to the week for which you want to report overhead costs by pressing the arrow buttons.
  • In the Act. postings also in the future (overh. costs, ...) area, overhead cost projects are displayed with their corresponding tasks.
  • Click on the line of the required overhead cost task in the scale area below the required date and enter the hours.
  • Save.
    • A load record is created and can be viewed and edited in the left window by expanding the tree structure of the respective task.
      • In the Comment field you can write a comment on the load record.
      • If the date is changed manually in the Load date field, the load record is automatically moved under the scale as well.
  • Enter the hours for all required days in the same way and save.
  • Send Remaining Effort Forecast

    Information
    • In case an employee notices upon completion of a task planned for him/her that the effort is higher than planned, he/she has the option to report them to the project manager in charge in the form of remaining effort prognoses.

    From DB 39.5.12

    Procedure
    • Select the Forecast module variant from the toolbar.
    • Enter the estimated remaining effort in the Forecast field and save.
    • Click on the Send forecast button.
    • The Send Info module is opened including an automatically created message.
    • The message contains the following data: sender, planned and NEW actual values of the current week, remaining and forecast values for effort as well as NEW the expected completion date, if it is filled.
      • The project manager of the project is automatically entered as the recipient.
    • Click on the Send button.

    From DB 39.5.0

    Procedure
    • Select the Forecast module variant from the toolbar.
    • Enter the estimated remaining effort in the Forecast field and save.
    • Click on the Send forecast button.
    • The Send Info module is opened including an automatically created message.
    • The message contains the following data: sender, planned, actual, remaining, and forecast values for the effort.
      • The project manager of the project is automatically entered as the recipient.
    • Click on the Send button.

    Up to DB 39.5.0

    Procedure
    • Select the Forecast module variant from the toolbar.
    • Enter the estimated remaining effort in the Forecast field and save.
    • Click on the Send forecast button.
    • The Send Info module is opened including an automatically created message.
    • The message contains the following data: sender, planned, actual, remaining, and forecast values for the effort.
      • The project manager of the project is automatically entered as the recipient.
    • Click on the Send button.

    Reverse Postings

    Information
    • If incorrect actual data has been recorded, you can always correct or delete them. In some cases, this is prevented by PLANTA (indicated by respective messages which are displayed when attempting to delete or correct the values).
    • PLANTA expressly advices you against the deletion of the complete load records in such a case, even if the user possesses the required rights to do so. Instead, it is recommended to make reverse postings in such cases.
      • Exception: Key date
        • If a key date has been set, you have the option to change or delete the data recorded before and on the key date or to record new data (if you forgot something).

    Detailed information and reasons for using reverse postings, see the topic of the same name.

    Procedure in the Work Reporting or Report Hours Worked module

    • Actual load value is to be deleted
      • Insert a new record below the load record to be canceled and set all values except Actual load as in the original record.
        • Enter the same value as in the original record with a minus symbol in the Actual load field.

    • Actual load value is to be change
      • Insert a new record below the load record to be canceled and set all values except Actual load as in the original record.
        • Enter the same value as in the original record with a minus symbol in the Actual load field.
      • Insert another record and set all values except Actual load as in the original record.

    • Cost type or date is to be changed
      • Insert a new record below the load record to be canceled and set all values except Actual load as in the original record.
        • Enter the same value as in the original record with a minus symbol in the Actual load field.
      • Insert another record and set Actual Load as in the original record.
      • Enter the required new cost type or date value.
        • If a new parameter is only entered for one of the two parameters, the other value remains the same as in the original record.


    See also: Overview: Working Time Recording, Reporting Hours Worked module

             PLANTA project









     
    • Suche in Topic-Namen

    • Suche in Topic-Inhalten
    This site is powered by the TWiki collaboration platform Powered by Perl