Date scheduling | For description, see here |
Time scheduling | For description, see here |
Planning horizon | For description, see Planning horizon is one of the key terms of scheduling and describes the period in which resources are available for scheduling in projects. The planning horizon of a resource is defined with the Start period and End period parameters in the Resource Data Sheet module. |
Capacity scheduling | For description, see here |
Capacity adjustment | For description, see Information
Details when using the CAP load profile
Example: Planned effort of the resource assignment = 100, Max. load/day = 5 The capacity scheduling calculates the duration of the resource assignment as follows: 100/5 = 20 days. This is the base for further calculation (capacity adjustment, etc.) In the following constellations, no capacity adjustment takes place, even if the checkbox is activated.
The capacity adjustment for tasks with deactivated Planning early checkbox is done reversely, i.e. starting with the Latest start / Latest end of the task toward the Earliest start / Earliest end of the task. If the effort specified for a task is so high that it cannot be planned in any period, then the Adjustment limit parameter comes into effect. |
Planning strategies | For description, see PLANTA project distinguishes three planning strategies:
The planning strategy is set by the planning type project parameter. An important factor for capacity adjustment is the remaining capacity per day. It is calculated from the avail. capacity * Load limit % - Util. Remaining capacity is available capacity which has not yet been planned. |
Module | Action | Calculation |
---|---|---|
Schedule (Project) | Scheduling button in the menu bar or the menu item of the same name | DS + CS + BRRC |
Budget (Project) | Recalculate button | DS + BS + CoS + BRRC |
Status | Create baseline, Create status report, Create final report buttons | DS + BS + CoS + BRRC |
Portfolio | Update portfolio button | BS + CoS + BRRC |
Portfolio Period | Update portfolio button | BS + CoS + BRRC |
Portfolio Status Reports | Create status report button | Summarization project status reports |
Schedule (Program) | Scheduling button in the menu bar or the menu item of the same name | DS + CoS + BRRC |
Budget (Program) | Recalculate button | DS + BS + CoS + BRRC |
Status | Create baseline, Create status report, Create final report buttons | DS + Summarization project status reports |
Replanning | Replanning button Replanning incl. portfolios button |
DS + BS + CoS + BRRC DS + BS + CoS on portfolio yearly tranches + BRRC |
Legend:
Calculation type Variant Subvariant Calculation ![]()
BRRC Calculation benefit, revenues, risks, opportunities CoS = Cost scheduling From resource (manual = 0)
From years (manual = 1)Summarization costs from resource utilization to CTGr/year and CTGr/Project
Summarization from year/CTGr to project/CTGrBS = Budget scheduling Project
Portfolio
ProgramSummarization years to project and TPR on parent projects
Summarization project years to portfolio
Summarization: Projects to programDS = Date scheduling Manual cost planning = 0
Manual cost planning = 1CS + CP = Capacity scheduling with cost planning = 1
CS + CP = Capacity scheduling with cost planning = 0Time scheduling + Capacity scheduling + Cost scheduling + BRRC
Time scheduling + Capacity scheduling + BRRC
Time scheduling + Capacity scheduling + BRRC
I | Attachment | History | Size | Date | Comment |
---|---|---|---|---|---|
![]() |
Grundlast.png | r1 | 22.9 K | 2013-03-26 - 17:59 | |
![]() |
L0472-00002579.pdf | r1 | 5032.1 K | 2010-08-05 - 13:22 | |
![]() |
TerminRechnung.pdf | r1 | 5032.1 K | 2012-05-11 - 10:52 |