Base | Tasks are displayed with the assigned links. New program tasks and links can be created and edited for both programs and projects. |
A variant of the Schedule optimized for printing is displayed. | |
Quality Gates NEW | Displays the quality gates predefined by the portfolio manager and their todo items to be completed. |
Base | Tasks are displayed with the assigned links. New program tasks and links can be created and edited for both programs and projects. |
A variant of the Schedule optimized for printing is displayed. |
Legend: Program/ProjectLegend: TaskFrom DB 39.5.15
Gates Gate without date delay Gate with date delay Main gate/main milestone Gates are master milestones of planning objects. Without date delay means: Total float 0 With date delay means: Total float < 0 Gates are only displayed in the schedule module if the Schedule with gates checkbox has been activated in the Project Core Data in the core data module of the respective planning object. Quality Gates Quality Gates are the items given from the portfolio and are only displayed in planning objects if they are assigned to this planning object in the portfolio to which the planning object belongs. Requested dates Requested start and Requested end are defined in the Key dates area in the corresponding core data sheet (Project Core Data, Idea Core Data, Proposal Core Data, Program Core Data).
Calculated dates The color of the bar is determined by the code of the planning object.
Code A
Code B
Code C
Code D
Code ECalc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item.
In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.Actual dates The bar is white hatched. The background color depends on the Code of the planning object. Actual start and Actual end (if there is any, otherwise Latest time recording date) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) when calculating the schedule of the respective planning object. Date delay A date delay occurs if the calculated end date (Calc. end) of the planning horizon is later than the requested end date (Requested end).
The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades.
Float Float is available if the calculated end date (Calc. end) of the planning object is earlier than the requested end date (Requested end).
external links outgoing incoming From DB 39.5.14
Gates Gate without date delay Gate with date delay Main gate/main milestone Gates are master milestones of planning objects. Without date delay means: Total float 0 With date delay means: Total float < 0 Gates are only displayed in the schedule module if the Schedule with gates checkbox has been activated in the Project Core Data in the core data module of the respective planning object. Quality Gates Quality Gates are the items given from the portfolio and are only displayed in planning objects if they are assigned to this planning object in the portfolio to which the planning object belongs. Requested dates Requested start and Requested end are defined in the Key dates area in the corresponding core data sheet (Project Core Data, Idea Core Data, Proposal Core Data, Program Core Data).
Calculated dates The color of the bar is determined by the code of the planning object.
Code A
Code B
Code C
Code D
Code ECalc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item.
In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.Actual dates The bar is white hatched. The background color depends on the Code of the planning object. Actual start and Actual end (if there is any, otherwise Latest time recording date) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) when calculating the schedule of the respective planning object. Date delay A date delay occurs if the calculated end date (Calc. end) of the planning horizon is later than the requested end date (Requested end).
The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades.
Float Float is available if the calculated end date (Calc. end) of the planning object is earlier than the requested end date (Requested end).
From DB 39.5.12
Gates Gate without date delay Gate with date delay Main gate/main milestone Gates are master milestones of planning objects. Without date delay means: Total float 0 With date delay means: Total float < 0 Gates are only displayed in the schedule module if the Schedule with gates checkbox has been activated in the Project Core Data in the core data module of the respective planning object. Quality Gates Quality Gates are the items given from the portfolio and are only displayed in planning objects if they are assigned to this planning object in the portfolio to which the planning object belongs. Requested dates Requested start and Requested end are defined in the Key dates area in the corresponding core data sheet (Project Core Data, Idea Core Data, Program Core Data).
Calculated dates The color of the bar is determined by the code of the planning object.
Code A
Code B
Code C
Code D
Code ECalc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item.
In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.Actual dates Actual start and Actual end (if there is any, otherwise Latest time recording date) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) when calculating the schedule of the respective planning object. Date delay A date delay occurs if the calculated end date (Calc. end) of the planning horizon is later than the requested end date (Requested end).
The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades.
Float Float is available if the calculated end date (Calc. end) of the planning object is earlier than the requested end date (Requested end).
Up to DB 39.5.12
Gates Gate without date delay Gate with date delay Main gate/main milestone Gates are master milestones of planning objects. Without date delay means: Total float 0 With date delay means: Total float < 0 Gates are only displayed in the schedule module if the Schedule with gates checkbox has been activated in the Project Core Data in the core data module of the respective planning object. Requested dates Requested start and Requested end are defined in the Key dates area in the corresponding core data sheet (Project Core Data, Idea Core Data, Program Core Data).
Calculated dates The bar color is defined by the code of the planning object.
Code A
Code B
Code C
Code D
Code ECalc. start and Calc. end of a planning object are determined in the calculation of the schedule of the respective planning object.
In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.Actual dates Actual start and Actual end (if there is any, otherwise Latest time recording date) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) when calculating the schedule of the respective planning object. Date delay A date delay occurs if the calculated end date (Calc. end) of the planning horizon is later than the requested end date (Requested end).
The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades.
Float Float is available if the calculated end date (Calc. end) of the planning object is earlier than the requested end date (Requested end).
From DB 39.5.15
Symbol Meaning Color Comment Task requested dates Requested start and Requested end of a task can be defined in the corresponding data fields in the Schedule module or they can be entered directly and graphically in the Gantt chart. Calculated dates of the tasks Uncritical
CriticalCalc. start and Calc. end are calculated by clicking on the calculation button or by selecting the respective menu item.
Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can be critical as well./ Milestones/
Master milestones/ Without delay
/ With delay
/ With actual endWithout delay means: Total float 0 With delay means: Total float < 0 Calculated dates of the summary tasks A summary task is a task in the structured schedule which consists of subtasks and summarizes them. Information on the summary task, such as duration and dates, is determined automatically from the sub-tasks. Actual dates The respective bars are white hatched if the Splitting parameter is deactivated, and gray hatched if the parameter is activated. Actual start and, if available, Actual end, otherwise Latest time recording date of a task, are calculated from the respective dates of the resources assigned to the task by clicking on the calculation button or by selecting the respective menu item or by setting it manually. Latest dates Latest start and Latest end of a task are calculated by clicking on the calculation button or by selecting the respective menu item. Task date delay A date delay occurs if the Calc. end of a task is later than its Latest end. Overlapping Overlapping = Possible date delay of task successor when using soft links. For more information, see here. Calculated dates of the external tasks Uncritical
CriticalCalc. start and Calc end of the external tasks are calculated by clicking on the calculation button or by selecting the respective menu item.
Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can be critical as well.Calculated dates of the external summary tasks / Milestones/master milestones of the external summary tasks / Without delay
/ With delay
Without delay means: Total float 0 With delay means: Total float < 0 External link outgoing incoming From DB 39.5.14
Symbol Meaning Color Comment Task requested dates Requested start and Requested end of a task can be defined in the corresponding data fields in the Schedule module or they can be entered directly and graphically in the Gantt chart. Calculated dates of the tasks Uncritical
CriticalCalc. start and Calc. end are calculated by clicking on the calculation button or by selecting the respective menu item.
Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical./ Milestones/
Master milestones/ Without delay
/ With delay
/ With actual endWithout delay means: Total float 0 With delay means: Total float < 0 Calculated dates of the summary tasks A summary task is a task in the structured schedule which consists of subtasks and summarizes them. Information on the summary task, such as duration and dates, is determined automatically from the sub-tasks. Actual dates The respective bars are white hatched if the Splitting parameter is deactivated, and gray hatched if the parameter is activated. Actual start and, if available, Actual end, otherwise Latest time recording date of a task, are calculated from the respective dates of the resources assigned to the task by clicking on the calculation button or by selecting the respective menu item or by setting it manually. Latest dates Latest start and Latest end of a task are calculated by clicking on the calculation button or by selecting the respective menu item. Task date delay A date delay occurs if the Calc. end of a task is later than its Latest end. Overlapping Overlapping = Possible date delay of task successor when using soft links. For more information, see here. Calculated dates of the external tasks Uncritical
CriticalCalc. start and Calc end of the external tasks are calculated by clicking on the calculation button or by selecting the respective menu item.
Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical.Calculated dates of the external summary tasks / Milestones/master milestones of the external summary tasks / Without delay
/ With delay
Without delay means: Total float 0 With delay means: Total float < 0 From DB 39.5.12
Symbol Meaning Color Comment Task requested dates Requested start and Requested end of a task can be defined in the corresponding data fields in the Schedule module or they can be entered directly and graphically in the Gantt chart. Calculated dates of the tasks Uncritical
CriticalCalc. start and Calc. end are calculated by clicking on the calculation button or by selecting the respective menu item.
Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical./ Milestones/
Master milestones/ Without delay
/ With delay
/ With actual endWithout delay means: Total float 0 With delay means: Total float < 0 Calculated dates of the summary tasks A summary task is a task in the structured schedule which consists of subtasks and summarizes them. Information on the summary task, such as duration and dates, is determined automatically from the sub-tasks. Actual dates Actual start and, if available, Actual end, otherwise Latest time recording date of a task, are calculated from the respective dates of the resources assigned to the task by clicking on the calculation button or by selecting the respective menu item or it is set manually. Latest dates Latest start and Latest end of a task are calculated by clicking on the calculation button or by selecting the respective menu item. Task date delay A date delay occurs if the Calc. end of a task is later than its Latest end. Overlapping Overlapping = Possible date delay of task successor when using soft links. For more information, see here. Calculated dates of the external tasks Uncritical
CriticalCalc. start and Calc end of the external tasks are calculated by clicking on the calculation button or by selecting the respective menu item.
Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical.Calculated dates of the external summary tasks / Milestones/master milestones of the external summary tasks / Without delay
/ With delay
Without delay means: Total float 0 With delay means: Total float < 0 From DB 39.5.11
Symbol Meaning Color Comment Task requested dates Requested start and Requested end of a task can be defined in the corresponding data fields in the Schedule module or they can be entered directly and graphically in the Gantt chart. Calculated dates of the tasks Uncritical
CriticalCalc. start and Calc. end are calculated by clicking on the calculation button or by selecting the respective menu item.
Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical./ Milestones/
master milestones/ Without delay
/ With delay
/ With actual endWithout delay means: Total float 0 With delay means: Total float < 0 Calculated dates of the summary tasks A summary task is a task in the structured schedule that consists of subtasks and summarizes them. Information on the summary task, such as duration and dates, is determined automatically from the sub-tasks. Actual dates Actual start and, if available, Actual end, otherwise Latest time recording date of a task, are calculated from the respective dates of the resources assigned to the task by clicking on the calculation button or by selecting the respective menu item or it is set manually. Latest dates Latest start and Latest end of a task are calculated by clicking on the calculation button or by selecting the respective menu item. Task date delay A date delay occurs if the Calc. end of a task is later than its Latest end. Overlapping Overlapping = Possible date delay of task successor when using soft links. For more information, see here. Calculated dates of the external tasks Critical
UncriticalCalc. start and Calc. end of the external tasks are calculated by clicking on the calculation button or by selecting the respective menu item.
Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical.Calculated dates of the external summary tasks Milstones/master milestones of the external tasks Up to DB 39.5.11
Symbol Meaning Color Comment Task requested dates Requested start and Requested end of a task can be defined in the corresponding data fields in the Schedule module or they can be entered directly and graphically in the Gantt chart. Calculated dates of the tasks Uncritical
CriticalCalc. start and Calc. end are calculated by clicking on the calculation button or by selecting the respective menu item.
Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical./ Milestones/
Master milestones/ Uncritical
/ Critical
/ With actual endUncritical means: Total float 0 Critical means: Total float < 0 Calculated dates of the summary tasks A summary task is a task in the structured schedule that consists of subtasks and summarizes them. Information on the summary task, such as duration and dates, is determined automatically from the sub-tasks. Actual dates Actual start and, if available, Actual end, otherwise Latest time recording date of a task, are calculated from the respective dates of the resources assigned to the task by clicking on the calculation button or by selecting the respective menu item or it is set manually. Latest dates Latest start and Latest end of a task are calculated by clicking on the calculation button or by selecting the respective menu item. Task date delay A date delay occurs if the Calc. end of a task is later than its Latest end. Overlapping Overlapping = Possible date delay of task successor when using soft links. For more information, see here. Calculated dates of the external tasks Critical
UncriticalCalc. start and Calc. end of the external tasks are calculated by clicking on the calculation button or by selecting the respective menu item.
Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical.Calculated dates of the external summary tasks Milstones/master milestones of the external tasks
show_psp_instead_of_id
global parameter you can set which of these IDs will be used. This will then apply system wide to all user modules in which tasks are displayed.
Tip: Each task of the schedule can also be opened and edited in the form of a data sheet. To do so, click on the link on the ID of the task or right-click on the required task and select the Edit task command from the context menu. |
See also: Create, Edit, Delete Links |
See also: External Tasks |
See also: Date, Resource, and Cost Planning, Links, Work Breakdown Structure, Structuring tasks via drag&drop, Graphical Editing in Gantt Chart, insert records, External Tasks |
I | Attachment | History | Size | Date | Comment |
---|---|---|---|---|---|
png | A.png | r1 | 0.3 K | 2014-03-03 - 13:31 | |
png | B.png | r1 | 0.3 K | 2014-03-03 - 13:31 | |
png | C.png | r1 | 0.3 K | 2014-03-03 - 13:31 | |
png | D.png | r1 | 0.3 K | 2014-03-03 - 13:31 | |
png | E.png | r1 | 0.3 K | 2014-03-03 - 13:32 | |
png | Ist.png | r1 | 0.3 K | 2014-03-03 - 13:33 | |
png | Kalk.png | r1 | 0.5 K | 2014-03-03 - 13:34 | |
png | PSP.PNG | r1 | 1.3 K | 2016-12-02 - 13:36 | |
png | Puffer.png | r1 | 0.4 K | 2014-03-03 - 13:35 | |
png | Verzug.png | r1 | 0.5 K | 2014-03-03 - 13:35 | |
png | Wunsch.png | r1 | 0.3 K | 2014-03-03 - 13:35 |