Up to DB 14 | Requested dates | Requested start and Requested end are defined in the Key dates area in the corresponding core data sheet (Project Core Data, Idea Core Data, Program Core Data). |
||
From DB 14 | Requested dates | Requested start and Requested end are defined in the Key dates area in the corresponding core data sheet (Project Core Data, Idea Core Data, Proposal Core Data, Program Core Data). |
Up to DB 12 | Calculated dates | The bar color is defined by the code of the planning object. Code A Code B Code C Code D Code E |
Calc. start and Calc. end of a planning object are determined in the calculation of the schedule of the respective planning object. In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules. |
|
From DB 12 | Calculated dates | The color of the bar is determined by the code of the planning object. Code A Code B Code C Code D Code E |
Calc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item. In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules. |
|
From DB 14 | Calculated dates | The color of the bar is determined by the code of the planning object. Code A Code B Code C Code D Code E |
Calc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item. In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules. |
Up to DB 12 | Actual dates | Actual start and Actual end (if there is any, otherwise Latest time recording date) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) when calculating the schedule of the respective planning object. | ||
From DB 12 | Actual dates | Actual start and Actual end (if there is any, otherwise Latest time recording date) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) when calculating the schedule of the respective planning object. | ||
From DB 14 | Actual dates | The bar is white hatched. The background color depends on the Code of the planning object. | Actual start and Actual end (if there is any, otherwise Latest time recording date) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) when calculating the schedule of the respective planning object. |
Up to DB 12 | Master milestones | with date delay without date delay |
Tasks are defined as master milestones in the Schedule module. | |
From DB 12 | Master milestones | without date delay with date delay |
Tasks are defined as master milestones in the Schedule module. | |
From DB 14 | Master milestones | without date delay with date delay |
Tasks are defined as master milestones in the Schedule module. |
Up to DB 14 | Gates | Gate without date delay Gate with date delay Main gate/main milestone | Gates are master milestones of planning objects. Without date delay means: Total float 0 With date delay means: Total float < 0 Gates are only displayed in the schedule module if the Schedule with gates checkbox has been activated in the Project Core Data in the core data module of the respective planning object. | |
From DB 14 | Gates | Gate without date delay Gate with date delay Main gate/main milestone | Gates are master milestones of planning objects. Without date delay means: Total float 0 With date delay means: Total float < 0 Gates are only displayed in the schedule module if the Schedule with gates checkbox has been activated in the Project Core Data in the core data module of the respective planning object. | |
From DB 12 | Quality Gates | Quality Gates are the items given from the portfolio and are only displayed in planning objects if they are assigned to this planning object in the portfolio to which the planning object belongs. |
Up to DB 12 | Calculated dates from status report | Calc. start and Calc. end of the planning object from the selected status report. | ||
From DB 12 | Calculated dates from status report | The color of the bar equates to that of the project code (see the legend above), however, it is slightly lighter. | Calc. start and Calc. end of the planning object from the selected status report. | |
From DB 13 | Calculated dates from status report | Calc. start and Calc. end of the planning object from the selected status report. |
From DB 15 | external links | outgoing incoming |
Float | Float is available if the calculated end date (Calc. end) of the planning object is earlier than the requested end date (Requested end). |
|||
Date delay | A date delay occurs if the calculated end date (Calc. end) of the planning horizon is later than the requested end date (Requested end). The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades. |
|||
Calculated project dates | Calc. start and Calc. end of a project are calculated by clicking on the calculation button or by selecting the respective menu item. | |||
Calculated dates of the programs | Calc. start and Calc. end of a program are calculated by clicking on the calculation button or by selecting the respective menu item. | |||
Master milestone date delay | A master milestone date delay occurs if its Calc. end is later than its Latest end. |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Requested dates | Requested start and Requested end are defined in the Key dates area in the corresponding core data module (Project Core Data, Idea Core Data, Proposal Core Data, Program Core Data). |
||
Calculated dates | The color of the bar is determined by the code of the planning object. Code A Code B Code C Code D Code E |
Calc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item. In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules. |
|
Actual dates | The bar is white hatched. The background color depends on the Code of the planning object. | Actual start and Actual end (if there is any, otherwise Latest time recording date) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) when calculating the schedule of the respective planning object. | |
Float | Float is available if the calculated end date (Calc. end) is earlier than the requested end date (Requested end). |
||
Date delay | A date delay occurs if the calculated end date (Calc. end) is later than the requested end date (Requested end). The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades. |
||
Master milestones | Without date delay With date delay |
Tasks are defined as master milestones in the Schedule module. | |
external links | outgoing incoming |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Requested dates | Requested start and Requested end are defined in the Key dates area in the corresponding core data module (Project Core Data, Idea Core Data, Proposal Core Data, Program Core Data). |
||
Calculated dates | The color of the bar is determined by the code of the planning object. Code A Code B Code C Code D Code E |
Calc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item. In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules. |
|
Actual dates | The bar is white hatched. The background color depends on the Code of the planning object. | Actual start and Actual end (if there is any, otherwise Latest time recording date) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) in the calculation of the schedule of the respective planning object. | |
Float | Float is available if the calculated end date (Calc. end) is earlier than the requested end date (Requested end). |
||
Date delay | A date delay occurs if the calculated end date (Calc. end) is later than the requested end date (Requested end). The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades. |
||
Master milestones | Without date delay With date delay |
Tasks are defined as master milestones in the Schedule module. |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Requested dates | Requested start and Requested end are defined in the Key dates area in the corresponding core data module (Project Core Data, Idea Core Data, Proposal Core Data, Program Core Data). |
||
Calculated dates | The color of the bar is determined by the code of the planning object. Code A Code B Code C Code D Code E |
Calc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item. In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules. |
|
Actual dates | Actual start and Actual end (if there is any, otherwise Latest time recording date) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) when calculating the schedule of the respective planning object. | ||
Float | Float is available if the calculated end date (Calc. end) is earlier than the requested end date (Requested end). |
||
Date delay | A date delay occurs if the calculated end date (Calc. end) is later than the requested end date (Requested end). The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades. |
||
Master milestones | Without date delay With date delay |
Tasks are defined as master milestones in the Schedule module. |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Requested dates | Requested start and Requested end are defined in the Key dates area in the corresponding core data module (Project Core Data, Idea Core Data, Proposal Core Data, Program Core Data). |
||
Calculated dates | The color of the bar is determined by the code of the planning object. Code A Code B Code C Code D Code E |
Calc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item. In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules. |
|
Actual dates | Actual start and Actual end (if there is any, otherwise Latest time recording date) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) when calculating the schedule of the respective planning object. | ||
Float | Float is available if the calculated end date (Calc. end) is earlier than the requested end date (Requested end). |
||
Date delay | A date delay occurs if the calculated end date (Calc. end) is later than the requested end date (Requested end). The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades. |
||
Master milestones | With date delay Without date delay |
Tasks are defined as master milestones in the Schedule module. |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Requested dates | Requested start and Requested end are defined in the Key dates area in the corresponding core data module (Project Core Data, Idea Core Data, Proposal Core Data, Program Core Data). |
||
Calculated dates | The color of the bar is determined by the code of the planning object. Code A Code B Code C Code D Code E |
Calc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item. In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules. |
|
Actual dates | The bar is shaded in white. The background color depends on the Project Code. | Actual start and, if available Actual end, otherwise Latest time recording date of a project are calculated by clicking on the calculation button or by selecting the respective menu item. | |
Float | Float is available if the calculated end date (Calc. end) is earlier than the requested end date (Requested end). |
||
Date delay | A date delay occurs if the calculated end date (Calc. end) is later than the requested end date (Requested end). The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades. |
||
Master milestones | Without date delay With date delay |
Tasks are defined as master milestones in the Schedule module. |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Requested dates | Requested start and Requested end are defined in the Key dates area in the corresponding core data module (Project Core Data, Idea Core Data, Proposal Core Data, Program Core Data). |
||
Calculated dates | The color of the bar is determined by the code of the planning object. Code A Code B Code C Code D Code E |
Calc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item. In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules. |
|
Float | Float is available if the calculated end date (Calc. end) is earlier than the requested end date (Requested end). |
||
Date delay | A date delay occurs if the calculated end date (Calc. end) is later than the requested end date (Requested end). The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades. |
||
Master milestones | Without date delay With date delay |
Tasks are defined as master milestones in the Schedule module. |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Requested dates | Requested start and Requested end are defined in the Key dates area in the corresponding core data module (Project Core Data, Idea Core Data, Proposal Core Data, Program Core Data). |
||
Calculated dates | The color of the bar is determined by the code of the planning object. Code A Code B Code C Code D Code E |
Calc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item. In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules. |
|
Actual dates | Actual start and, if available, Actual end, in any other case the Latest time recording date of a project are calculated by clicking on the calculation button or by selecting the respective menu item. | ||
Float | Float is available if the calculated end date (Calc. end) is earlier than the requested end date (Requested end). |
||
Date delay | A date delay occurs if the calculated end date (Calc. end) is later than the requested end date (Requested end). The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades. |
||
Master milestones | With date delay Without date delay |
Tasks are defined as master milestones in the Schedule module. |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Requested dates | Requested start and Requested end of a planning object in the simulation/road map. The dates stem from the status report which was used as a source for the simulation. |
||
Simulated dates | The color of the bar is determined by the selection made in the Color in simulation field. | Changed (simulated) dates (Simulation: start and Simulation: end) of a planning object |
|
Calculated dates | Calc. start and Calc. end of a planning object in the simulation/road map. The dates stem from the status report which was used as a source for the simulation. | ||
Actual dates | The bar is shaded in white. The background color is determined by the selection made in the Color in simulation field. | Actual start and Latest time recording date of a planning object in the simulation/road map. The dates stem from the status report which was used as a source for the simulation. |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Requested dates | Requested start and Requested end of a planning object in the simulation/road map. The dates stem from the status report which was used as a source for the simulation. |
||
Simulated dates | The color of the bar is determined by the selection in the Color in simulation field | Changed (simulated) dates (Simulation: start and Simulation: end) of a planning object |
|
Calculated dates | Calc. start and Calc. end of a planning object in the simulation/road map. The dates stem from the status report which was used as a source for the simulation. | ||
Actual dates | Actual start and Latest time recording date of a planning object in the simulation/road map. The dates stem from the status report which was used as a source for the simulation. |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Requested dates | Requested start and Requested end of a planning object in the simulation/road map. The dates stem from the status report which was used as a source for the simulation. |
||
Simulated dates | The color of the bar is determined by the selection in the Color in simulation field | Changed (simulated) dates (Simulation: start and Simulation: end) of a planning object |
|
Calculated dates | Calc. start and Calc. end of a planning object in the simulation/road map. The dates stem from the status report which was used as a source for the simulation. | ||
Actual dates | Actual start and Latest time recording date of a planning object in the simulation/road map. The dates stem from the status report which was used as a source for the simulation. |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Task requested dates | Requested start and Requested end of a task can be defined in the corresponding data fields in the Schedule module or they can be entered directly and graphically in the Gantt chart. | ||
Calculated dates of the tasks | Uncritical Critical |
Calc. start and Calc. end are calculated by clicking on the calculation button or by selecting the respective menu item. Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can be critical as well. |
|
/ | Milestones/ Master milestones |
/ Without delay / With delay / With actual end |
Without delay means: Total float 0 With delay means: Total float < 0 |
Calculated dates of the summary tasks | A summary task is a task in the structured schedule which consists of subtasks and summarizes them. Information on the summary task, such as duration and dates, is determined automatically from the sub-tasks. | ||
Actual dates | The respective bars are white hatched if the Splitting parameter is deactivated, and gray hatched if the parameter is activated. | Actual start and, if available, Actual end, otherwise Latest time recording date of a task, are calculated from the respective dates of the resources assigned to the task by clicking on the calculation button or by selecting the respective menu item or by setting it manually. | |
Latest dates | Latest start and Latest end of a task are calculated by clicking on the calculation button or by selecting the respective menu item. | ||
Task date delay | A date delay occurs if the Calc. end of a task is later than its Latest end. | ||
Overlapping | Overlapping = Possible date delay of task successor when using soft links. For more information, see here. | ||
Calculated dates of the external tasks | Uncritical Critical |
Calc. start and Calc end of the external tasks are calculated by clicking on the calculation button or by selecting the respective menu item. Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can be critical as well. |
|
Calculated dates of the external summary tasks | |||
/ | Milestones/master milestones of the external summary tasks | / Without delay / With delay |
Without delay means: Total float 0 With delay means: Total float < 0 |
External link | outgoing incoming |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Task requested dates | Requested start and Requested end of a task can be defined in the corresponding data fields in the Schedule module or they can be entered directly and graphically in the Gantt chart. | ||
Calculated dates of the tasks | Uncritical Critical |
Calc. start and Calc. end are calculated by clicking on the calculation button or by selecting the respective menu item. Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical. |
|
/ | Milestones/ Master milestones |
/ Without delay / With delay / With actual end |
Without delay means: Total float 0 With delay means: Total float < 0 |
Calculated dates of the summary tasks | A summary task is a task in the structured schedule which consists of subtasks and summarizes them. Information on the summary task, such as duration and dates, is determined automatically from the sub-tasks. | ||
Actual dates | The respective bars are white hatched if the Splitting parameter is deactivated, and gray hatched if the parameter is activated. | Actual start and, if available, Actual end, otherwise Latest time recording date of a task, are calculated from the respective dates of the resources assigned to the task by clicking on the calculation button or by selecting the respective menu item or by setting it manually. | |
Latest dates | Latest start and Latest end of a task are calculated by clicking on the calculation button or by selecting the respective menu item. | ||
Task date delay | A date delay occurs if the Calc. end of a task is later than its Latest end. | ||
Overlapping | Overlapping = Possible date delay of task successor when using soft links. For more information, see here. | ||
Calculated dates of the external tasks | Uncritical Critical |
Calc. start and Calc end of the external tasks are calculated by clicking on the calculation button or by selecting the respective menu item. Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical. |
|
Calculated dates of the external summary tasks | |||
/ | Milestones/master milestones of the external summary tasks | / Without delay / With delay |
Without delay means: Total float 0 With delay means: Total float < 0 |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Task requested dates | Requested start and Requested end of a task can be defined in the corresponding data fields in the Schedule module or they can be entered directly and graphically in the Gantt chart. | ||
Calculated dates of the tasks | Uncritical Critical |
Calc. start and Calc. end are calculated by clicking on the calculation button or by selecting the respective menu item. Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical. |
|
/ | Milestones/ Master milestones |
/ Without delay / With delay / With actual end |
Without delay means: Total float 0 With delay means: Total float < 0 |
Calculated dates of the summary tasks | A summary task is a task in the structured schedule which consists of subtasks and summarizes them. Information on the summary task, such as duration and dates, is determined automatically from the sub-tasks. | ||
Actual dates | Actual start and, if available, Actual end, otherwise Latest time recording date of a task, are calculated from the respective dates of the resources assigned to the task by clicking on the calculation button or by selecting the respective menu item or it is set manually. | ||
Latest dates | Latest start and Latest end of a task are calculated by clicking on the calculation button or by selecting the respective menu item. | ||
Task date delay | A date delay occurs if the Calc. end of a task is later than its Latest end. | ||
Overlapping | Overlapping = Possible date delay of task successor when using soft links. For more information, see here. | ||
Calculated dates of the external tasks | Uncritical Critical |
Calc. start and Calc end of the external tasks are calculated by clicking on the calculation button or by selecting the respective menu item. Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical. |
|
Calculated dates of the external summary tasks | |||
/ | Milestones/master milestones of the external summary tasks | / Without delay / With delay |
Without delay means: Total float 0 With delay means: Total float < 0 |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Task requested dates | Requested start and Requested end of a task can be defined in the corresponding data fields in the Schedule module or they can be entered directly and graphically in the Gantt chart. | ||
Calculated dates of the tasks | Uncritical Critical |
Calc. start and Calc. end are calculated by clicking on the calculation button or by selecting the respective menu item. Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical. |
|
/ | Milestones/ master milestones |
/ Without delay / With delay / With actual end |
Without delay means: Total float 0 With delay means: Total float < 0 |
Calculated dates of the summary tasks | A summary task is a task in the structured schedule that consists of subtasks and summarizes them. Information on the summary task, such as duration and dates, is determined automatically from the sub-tasks. | ||
Actual dates | Actual start and, if available, Actual end, otherwise Latest time recording date of a task, are calculated from the respective dates of the resources assigned to the task by clicking on the calculation button or by selecting the respective menu item or it is set manually. | ||
Latest dates | Latest start and Latest end of a task are calculated by clicking on the calculation button or by selecting the respective menu item. | ||
Task date delay | A date delay occurs if the Calc. end of a task is later than its Latest end. | ||
Overlapping | Overlapping = Possible date delay of task successor when using soft links. For more information, see here. | ||
Calculated dates of the external tasks | Critical Uncritical |
Calc. start and Calc. end of the external tasks are calculated by clicking on the calculation button or by selecting the respective menu item. Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical. |
|
Calculated dates of the external summary tasks | |||
Milstones/master milestones of the external tasks |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Task requested dates | Requested start and Requested end of a task can be defined in the corresponding data fields in the Schedule module or they can be entered directly and graphically in the Gantt chart. | ||
Calculated dates of the tasks | Uncritical Critical |
Calc. start and Calc. end are calculated by clicking on the calculation button or by selecting the respective menu item. Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical. |
|
/ | Milestones/ Master milestones |
/ Uncritical / Critical / With actual end |
Uncritical means: Total float 0 Critical means: Total float < 0 |
Calculated dates of the summary tasks | A summary task is a task in the structured schedule that consists of subtasks and summarizes them. Information on the summary task, such as duration and dates, is determined automatically from the sub-tasks. | ||
Actual dates | Actual start and, if available, Actual end, otherwise Latest time recording date of a task, are calculated from the respective dates of the resources assigned to the task by clicking on the calculation button or by selecting the respective menu item or it is set manually. | ||
Latest dates | Latest start and Latest end of a task are calculated by clicking on the calculation button or by selecting the respective menu item. | ||
Task date delay | A date delay occurs if the Calc. end of a task is later than its Latest end. | ||
Overlapping | Overlapping = Possible date delay of task successor when using soft links. For more information, see here. | ||
Calculated dates of the external tasks | Critical Uncritical |
Calc. start and Calc. end of the external tasks are calculated by clicking on the calculation button or by selecting the respective menu item. Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical. |
|
Calculated dates of the external summary tasks | |||
Milstones/master milestones of the external tasks |
Calculated dates of the tasks from status report | Calculated dates of the tasks from status report Calc. start and Calc. end of the tasks from the selected status report. | ||
Calculated dates of the summary tasks from status report | Calc. start and Calc. end of the summary tasks from the selected status report. | ||
/ | Milestones/master milestones of the tasks from the status report |
Calculated dates of the tasks from status report | Uncritical Critical |
Calculated dates of the tasks from status report Calc. start and Calc. end of the tasks from the selected status report. | |
Calculated dates of the summary tasks from status report | Calc. start and Calc. end of the summary tasks from the selected status report. | ||
/ | Milestones/master milestones of the tasks from status report | / Without delay / With delay |
Without delay means: Total float 0 With delay means: Total float < 0 |
Calculated dates of the tasks from status report | Calc. start and Calc. end of the tasks, the milestones, and the master milestones from the selected status report. | ||
Calculated dates of summary tasks from status report | Calc. start and Calc. end of the summary tasks from the selected status report |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Planned load (remaining load) of the resource(s) in projects | The color of the bar is determined by the code of the projects. Code A Code B Code C Code D Code E |
The code is defined in the Project Core Data module of the respective project. The values for the histogram bars are each calculated from the Planned code 1 to Planned code 5 columns. | |
Actual load of the resource(s) | The values for the histogram bar are taken from the Used column from the period records of the resource(s) (DT468). The values in the period records, in turn stem from the working time recording of the resources (DT472). | ||
Available capacity of resource(s) | The values for histogram bars are calculated from the Available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet. The limiting line at the top of the bar will be visible despite of overlapping by utilization bars. |
||
Basic load of resource(s) | The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, again, comes from the general basic load defined for the resource in the Resource Data Sheet. The limiting line at the top margin of the bar will be visible despite overlapping by utilization bars. |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Planned load (remaining load) of the resource(s) in projects | The color of the bar is determined by the code of the projects. Code A Code B Code C Code D Code E |
The code is defined in the Project Core Data module of the respective project. The values for the histogram bars are each calculated from the Planned code 1 to Planned code 5 columns. | |
Actual load of the resource(s) | The values for the histogram bar are taken from the Used column from the period records of the resource(s) (DT468). The values in the period records, in turn stem from the working time recording of the resources (DT472). | ||
Available capacity of resource(s) | The values for histogram bars are calculated from the Available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet. The limiting line at the top of the bar will be visible despite of overlapping by utilization bars. |
||
Basic load of resource(s) | The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, again, comes from the general basic load defined for the resource in the Resource Data Sheet. The limiting line at the top margin of the bar will be visible despite overlapping by utilization bars. |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Planned load (remaining load) of the resource(s) in projects | The color of the bar is determined by the code of the projects. Code A Code B Code C Code D Code E |
The code is defined in the Project Core Data module of the respective project. The values for the histogram bars are each calculated from the Planned code 1 to Planned code 5 columns. | |
Actually incurring load (actual load) of the resource(s) | The values for the histogram bar are taken from the Used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472). | ||
Available capacity of the resource(s) | The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet. NEWThe limiting line at the top of the bar will be visible despite of overlapping by utilization bars. |
||
Basic load of resource(s) | The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, again, comes from the general basic load defined for the resource in the Resource Data Sheet. NEWThe limiting line at the top margin of the bar will be visible despite overlapping by utilization bars. |
||
Factor 4 of resource(s) | The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet. | ||
Factor 5 of resource(s) | The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, again, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet. |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Planned load of the resource(s) in projects | The color of the bar is determined by the code of the projects. Code A Code B Code C Code D Code E |
The code is defined in the Project Core Data module of the respective project. The values for the histogram bars are each calculated from the Planned code 1 to Planned code 5 columns. | |
Actually incurring load (actual load) of the resource(s) | The values for the histogram bar are taken from the Used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472). | ||
Available capacity of the resource(s) | The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet. NEWThe limiting line at the top of the bar will be visible despite of overlapping by utilization bars. |
||
Basic load of resource(s) | The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, again, comes from the general basic load defined for the resource in the Resource Data Sheet. NEWThe limiting line at the top margin of the bar will be visible despite overlapping by utilization bars. |
||
Factor 4 of resource(s) | The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet. | ||
Factor 5 of resource(s) | The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, again, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet. |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Planned load of the resource(s) in projects | The color of the bar is determined by the code of the projects. Code A Code B Code C Code D Code E |
The code is defined in the Project Core Data module of the respective project. The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns. | |
Actually incurring load (actual load) of the resource(s) | The values for the histogram bar are taken from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472). | ||
Available capacity of resource(s) | The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet. | ||
Basic load of resource(s) | The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load value defined for the resource in the Resource Data Sheet. | ||
Factor 4 of resource(s) | The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet. | ||
Factor 5 of resource(s) | The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, again, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet. |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Planned load (remaining load) of the resource(s) in projects | The color of the bar is determined by the code of the projects. Code A Code B Code C Code D Code E |
The code is defined in the Project Core Data module of the respective project. The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns. | |
Actually incurring load (actual load) of resource(s) | The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472). | ||
Available capacity of resource(s) | The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet. The limiting line at the top of the bar will be visible despite of overlapping by load data. |
||
Basic load of resource(s) | The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load defined for the resource in the Resource Data Sheet. The limiting line at the top of the bar will be visible despite of overlapping by load data. |
||
Overload of resource | The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned). |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Planned load (remaining load) of the resource(s) in projects | The color of the bar is determined by the code of the projects. Code A Code B Code C Code D Code E |
The code is defined in the Project Core Data module of the respective project. The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns. | |
Actually incurring load (actual load) of resource(s) | The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472). | ||
Available capacity of resource(s) | The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet. The limiting line at the top of the bar will be visible despite of overlapping by load data. |
||
Basic load of resource(s) | The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load defined for the resource in the Resource Data Sheet. The limiting line at the top of the bar will be visible despite of overlapping by load data. |
||
Overload of resource | The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned). |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Planned load of the resource(s) in projects | The color of the bar is determined by the code of the projects. Code A Code B Code C Code D Code E |
The code is defined in the Project Core Data module of the respective project. The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns. | |
Actual load of resource(s) | The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472). | ||
Available capacity of resource(s) | The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet. NEWThe limiting line at the top of the bar will be visible despite of overlapping by load data. |
||
Basic load of resource(s) | The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load defined for the resource in the Resource Data Sheet. NEWThe limiting line at the top of the bar will be visible despite of overlapping by load data. |
||
Factor 4 of resource(s) | The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet. | ||
Factor 5 of resource(s) | The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet. | ||
Overload of resource | The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned). |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Planned load of resource(s) in the projects | The bar color is determined by the project code. Code A Code B Code C Code D Code E |
The code is defined in the Project Core Data module of the respective project. The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns. | |
Actual load of resource(s) | The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472). | ||
Available capacity of resource(s) | The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet. NEWThe limiting line at the top of the bar will be visible despite of overlapping by load data. |
||
Basic load of resource(s) | The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load defined for the resource in the Resource Data Sheet. NEWThe limiting line at the top of the bar will be visible despite of overlapping by load data. |
||
Factor 4 of resource(s) | The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet. | ||
Factor 5 of resource(s) | The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet. | ||
Overload of resource | The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned). |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Planned load of resource(s) in the projects | The bar color is determined by the project code. Code A Code B Code C Code D Code E |
The code is defined in the Project Core Data module of the respective project. The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns. | |
Actual load of resource(s) | The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472). | ||
Available capacity of resource(s) | The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet. | ||
Basic load of resource(s) | The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load value defined for the resource in the Resource Data Sheet. | ||
Factor 4 of resource(s) | The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet. | ||
Factor 5 of resource(s) | The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet. | ||
Overload of resource | The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned). |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Task requested dates | Requested start and Requested end of a task are defined in the Schedule module. | ||
Calculated dates of the selected resource for the selected task in the selected project | The color of the bar is determined by the code of the respective project. For the meaning of the individual code colors, see the histogram scale. | Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. | |
Calculated dates of the selected resource for the selected task in the selected project | The bar is white hatched. | Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the reported hours worked of the corresponding resource (DT472) or are edited manually. | |
Latest task dates | Latest start and Latest end of a task are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Task requested dates | Requested start and Requested end of a task are defined in the Schedule module. | ||
Calculated dates of the selected resource for the selected task in the selected project | The color of the bar is determined by the code of the respective project. For the meaning of the individual code colors, see the histogram scale. | Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. | |
Actual dates of the selected resource for the selected task in the selected project | Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from working time recording of the corresponding resource (DT472) or are edited manually. | ||
Latest task dates | Latest start and Latest end of a task are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Task requested dates | Requested start and Requested end of a task are defined in the Schedule module. | ||
Calculated dates of the selected resource for the selected task in the selected project | The color of the bar is determined by the code of the respective project. For the meaning of the individual code colors, see the histogram scale. | Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. | |
Actual dates of the selected resource for the selected task in the selected project | Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the working time recording of the corresponding resource (DT472) or are edited manually. | ||
Latest task dates | Latest start and Latest end of a task are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Task requested dates | Requested start and Requested end of a task are defined in the Schedule module. | ||
Calculated dates of the selected resource for the selected task in the selected project | Upper bar part: The color of the bar is determined by the code of the respective project For the meaning of the individual code colors, see the histogram legend. Lower bar part: Uncritical task Critical task |
Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical. | |
Calculated dates of the selected resource for the selected task in the selected project | The bar is white hatched. | Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the working time recording of the respective resource (DT472) or edited manually. | |
Latest task dates | Latest start and Latest end of a task are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. | ||
Task date delay | A date delay occurs if Calc. end of a task is later than its Latest end. |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Task requested dates | Requested start and Requested end of a task are defined in the Schedule module. | ||
Calculated dates of the selected resource for the selected task in the selected project | Upper bar part: The color of the bar is determined by the code of the respective project For the meaning of the individual code colors, see the histogram legend. Lower bar part: Uncritical task Critical task |
Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical. | |
Actual dates of the selected resource for the selected task in the selected project | Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the reported hours worked of the corresponding resource (DT472) or are edited manually. | ||
Latest task dates | Latest start and Latest end of a task are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. | ||
Task date delay | A date delay occurs if Calc. end of a task is later than its Latest end. |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Task requested dates | Requested start and Requested end of a task are defined in the Schedule module. | ||
Calculated dates of the selected resource for the selected task in the selected project | Upper bar part: The color of the bar is determined by the code of the respective project For the meaning of the individual code colors, see the histogram legend. Lower bar part: Uncritical task Critical task |
Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical. | |
Actual dates of the selected resource for the selected task in the selected project | Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the reported hours worked of the corresponding resource (DT472) or are edited manually. | ||
Latest task dates | Latest start and Latest end of a task are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. | ||
Task date delay | A date delay occurs if Calc. end of a task is later than its Latest end. |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Task requested dates | Requested start and Requested end of a task are defined in the Schedule module. | ||
Calculated dates of the selected resource for the selected task in the selected project | Upper bar part: The color of the bar is determined by the code of the respective project For the meaning of the individual code colors, see the histogram legend. Lower bar part: Uncritical task Critical task |
Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. Uncritical means: Total float > 0 Critical means: Total float 0 Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical. | |
Actual dates of the selected resource for the selected task in the selected project | Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the reported hours worked of the corresponding resource (DT472) or are edited manually. | ||
Latest task dates | Latest start and Latest end of a task are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. | ||
Task date delay | A date delay occurs if Calc. end of a task is later than its Latest end. |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Calculated dates of the resource for the selected task in the selected project | The color of the bar is determined by the code of the corresponding project. Code A Code B Code C Code D Code E |
Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. | |
Actual dates of the selected resource for the selected task in the selected project | The bar is white hatched. | Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the reported hours worked of the corresponding resource (DT472) or are edited manually. | |
Date of tasks, risks and opportunity measures and process steps | The date value for the bar is calculated: |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Calculated dates of the resource for the selected task in the selected project | The color of the bar is determined by the code of the corresponding project. Code A Code B Code C Code D Code E |
Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. | |
Actual dates of the selected resource for the selected task in the selected project | Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the reported hours worked of the corresponding resource (DT472) or are edited manually. | ||
Date of tasks, risks and opportunity measures and process steps | The date value for the bar is calculated: |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Calculated dates of the resource for the selected task in the selected project | The color of the bar is determined by the code of the corresponding project. Code A Code B Code C Code D Code E |
Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. | |
Actual dates of the selected resource for the selected task in the selected project | Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the reported hours worked of the corresponding resource (DT472) or are edited manually. | ||
Date of tasks, risks and opportunity measures and process steps | The date value for the bar is calculated: |
Symbol | Meaning | Color | Comment |
---|---|---|---|
Calculated dates of the resource for the selected task in the selected project | The color of the bar is determined by the code of the corresponding project. Code A Code B Code C Code D Code E |
Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item. | |
Actual dates of the selected resource for the selected task in the selected project | Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the reported hours worked of the corresponding resource (DT472) or are edited manually. | ||
Date of todo items, risks and opportunity measures and process steps | The date value for the bar is calculated: |
Symbol | Meaning | Comment |
---|---|---|
Todo item date | The date value for the bar is calculated from the Date (DT804) field. |
I | Attachment | History | Size | Date | Comment |
---|---|---|---|---|---|
png | A.png | r1 | 0.3 K | 2015-06-18 - 10:46 | |
png | AOBAus.png | r1 | 0.3 K | 2020-02-21 - 10:47 | |
png | AOBEin.png | r1 | 0.3 K | 2020-02-21 - 10:47 | |
png | ActDB12.png | r3 r2 r1 | 0.2 K | 2018-10-19 - 10:34 | |
png | ActDB14.png | r3 r2 r1 | 0.3 K | 2020-02-24 - 10:45 | |
png | B.png | r1 | 0.3 K | 2015-06-18 - 10:46 | |
png | C.png | r1 | 0.3 K | 2015-06-18 - 10:46 | |
png | CalcCritDB12.PNG | r2 r1 | 0.3 K | 2018-10-09 - 09:41 | |
png | CodeADB12.PNG | r1 | 0.2 K | 2018-10-09 - 08:59 | |
png | CodeADB14.png | r2 r1 | 0.2 K | 2019-06-13 - 13:56 | |
png | CodeBDB12.PNG | r1 | 0.2 K | 2018-10-09 - 08:59 | |
png | CodeBDB14.png | r2 r1 | 0.2 K | 2019-06-13 - 13:56 | |
png | CodeCDB12.PNG | r1 | 0.2 K | 2018-10-09 - 08:59 | |
png | CodeCDB14.png | r2 r1 | 0.2 K | 2019-06-13 - 13:56 | |
png | CodeDDB12.PNG | r1 | 0.2 K | 2018-10-09 - 08:59 | |
png | CodeDDB14.png | r2 r1 | 0.2 K | 2019-06-13 - 13:56 | |
png | CodeEDB12.PNG | r5 r4 r3 r2 r1 | 0.1 K | 2018-10-09 - 09:05 | |
png | CodeEDB14.png | r2 r1 | 0.2 K | 2019-06-13 - 13:56 | |
png | CodeHisto.png | r1 | 0.4 K | 2015-07-17 - 12:09 | |
png | CriticNew.PNG | r3 r2 r1 | 0.4 K | 2018-01-18 - 11:32 | |
png | D.png | r1 | 0.3 K | 2015-06-18 - 10:47 | |
png | DauerProjekt.PNG | r1 | 0.4 K | 2015-07-23 - 13:02 | |
png | E.png | r1 | 0.3 K | 2015-06-18 - 10:47 | |
png | ExtSum.PNG | r1 | 0.3 K | 2015-09-10 - 19:09 | |
png | ExtTA.PNG | r6 r5 r4 r3 r2 | 0.3 K | 2015-09-10 - 19:14 | |
png | ExtTAUncrit.PNG | r2 r1 | 0.2 K | 2015-09-10 - 19:12 | |
png | Faktor4.png | r1 | 0.4 K | 2015-07-17 - 12:09 | |
png | Faktor5.png | r1 | 0.3 K | 2015-07-17 - 12:09 | |
png | Grundlast.png | r1 | 0.3 K | 2015-07-17 - 12:09 | |
png | GrundlastAbDb8.png | r1 | 0.2 K | 2016-08-31 - 03:30 | |
png | GrundlastLinie.png | r1 | 0.2 K | 2016-08-31 - 01:38 | |
png | GrundlastLinieDB14.png | r2 r1 | 0.2 K | 2019-06-25 - 08:47 | |
png | GrundlastLinieDB15.png | r1 | 0.2 K | 2020-02-21 - 10:40 | |
png | HMS.png | r1 | 0.5 K | 2020-03-05 - 13:19 | |
png | HMSred.png | r1 | 0.4 K | 2020-02-20 - 15:30 | |
png | Ist.png | r1 | 0.3 K | 2015-06-18 - 10:47 | |
png | IstBel.png | r1 | 1.0 K | 2015-07-17 - 12:09 | |
png | IstHisto.png | r3 r2 r1 | 0.3 K | 2018-10-19 - 10:21 | |
png | IstTermine.PNG | r2 r1 | 0.3 K | 2017-09-20 - 10:41 | |
png | Kalk.png | r1 | 0.5 K | 2015-06-18 - 10:47 | |
png | KalkDB12.PNG | r3 r2 r1 | 0.4 K | 2018-10-09 - 09:49 | |
png | KalkExtDB12.PNG | r2 r1 | 0.3 K | 2018-10-19 - 07:58 | |
png | KalkExtSammelDB12.PNG | r1 | 0.2 K | 2018-10-09 - 11:55 | |
png | KalkExtredDB12.png | r1 | 0.3 K | 2018-10-09 - 12:08 | |
png | KalkPRDB12.PNG | r2 r1 | 0.4 K | 2018-10-09 - 09:34 | |
png | KalkPRDB14.png | r2 r1 | 0.3 K | 2020-02-24 - 10:46 | |
png | KalkPRG.PNG | r2 r1 | 0.4 K | 2015-09-22 - 19:08 | |
png | KalkPRVG.PNG | r1 | 0.6 K | 2015-07-20 - 12:11 | |
png | KalkPRVGDB12.png | r1 | 0.5 K | 2018-10-19 - 11:18 | |
png | KalkPRVGDB14.png | r2 r1 | 0.5 K | 2020-02-24 - 13:21 | |
png | KalkSB.PNG | r1 | 0.3 K | 2015-07-22 - 12:02 | |
png | KalkSBDB12.png | r3 r2 r1 | 0.3 K | 2018-10-10 - 11:42 | |
png | KalkSBDB13.png | r1 | 0.3 K | 2018-12-13 - 14:25 | |
png | KalkSim.PNG | r1 | 0.3 K | 2017-09-07 - 09:06 | |
png | Kap.png | r1 | 0.3 K | 2015-07-17 - 12:08 | |
png | KapLinie.png | r1 | 0.2 K | 2016-08-31 - 03:02 | |
png | KapLinieDB14.png | r2 r1 | 0.2 K | 2019-06-13 - 14:12 | |
png | KapLinieDB15.png | r1 | 0.2 K | 2020-02-21 - 10:40 | |
png | LampeGelb.png | r1 | 0.5 K | 2015-07-23 - 12:12 | |
png | LampeGrau.png | r1 | 0.6 K | 2015-07-23 - 12:13 | |
png | LampeGruen.png | r1 | 0.5 K | 2015-07-23 - 12:13 | |
png | LampeRot.png | r1 | 0.5 K | 2015-07-23 - 12:13 | |
png | LampeWeiss.png | r1 | 0.5 K | 2015-07-23 - 12:13 | |
png | Linie.png | r1 | 0.2 K | 2016-08-31 - 03:08 | |
png | MMSCritNew.PNG | r1 | 0.4 K | 2018-01-18 - 12:47 | |
png | MMSDB12.png | r1 | 0.3 K | 2018-10-09 - 09:54 | |
png | MMSDB14.png | r1 | 0.3 K | 2019-06-13 - 13:22 | |
png | MMSExtDB12.PNG | r1 | 0.3 K | 2018-10-19 - 07:11 | |
png | MMSExtDB13.png | r1 | 0.3 K | 2018-12-14 - 10:07 | |
png | MMSGrey.PNG | r1 | 0.3 K | 2018-10-09 - 07:07 | |
png | MMS_erl.PNG | r1 | 0.5 K | 2015-09-11 - 18:33 | |
png | MMS_krit.PNG | r2 r1 | 0.5 K | 2015-09-11 - 18:09 | |
png | MMSbig.png | r1 | 0.5 K | 2020-03-05 - 13:19 | |
png | MMSdoneDB12.png | r2 r1 | 0.3 K | 2018-10-18 - 11:47 | |
png | MMSextRedDB12.png | r1 | 0.3 K | 2018-10-19 - 07:10 | |
png | MMSredDB12.png | r2 r1 | 0.3 K | 2018-10-09 - 10:18 | |
png | MMSredDB14.png | r2 r1 | 0.3 K | 2019-11-28 - 13:36 | |
png | MMSredbig.png | r1 | 0.5 K | 2020-03-05 - 13:19 | |
png | MS.PNG | r1 | 0.5 K | 2015-09-11 - 18:06 | |
png | MS.png | r1 | 0.6 K | 2015-06-18 - 10:47 | |
png | MSCritNew.png | r1 | 0.4 K | 2018-01-18 - 12:48 | |
png | MSDB12.png | r1 | 0.3 K | 2018-10-09 - 09:53 | |
png | MSDB14.png | r1 | 0.3 K | 2019-06-13 - 13:42 | |
png | MSExternal.PNG | r1 | 0.3 K | 2018-08-29 - 11:49 | |
png | MSGrey.PNG | r1 | 0.3 K | 2018-10-09 - 07:07 | |
png | MS_erl.PNG | r2 r1 | 0.5 K | 2015-09-11 - 18:34 | |
png | MSdoneDB12.png | r3 r2 r1 | 0.3 K | 2019-11-28 - 13:27 | |
png | MSextDB12.png | r1 | 0.3 K | 2018-10-19 - 07:10 | |
png | MSextDB13.png | r1 | 0.3 K | 2018-12-14 - 10:07 | |
png | MSextRedDB12.png | r1 | 0.3 K | 2018-10-19 - 07:10 | |
png | MSgreen.PNG | r2 r1 | 0.5 K | 2015-09-11 - 17:58 | |
png | MSred.PNG | r1 | 0.5 K | 2015-09-11 - 18:01 | |
png | MSredDB12.png | r2 r1 | 0.3 K | 2018-10-09 - 10:19 | |
png | MSredDB14.png | r2 r1 | 0.3 K | 2019-11-28 - 13:34 | |
png | Milestone.PNG | r1 | 0.4 K | 2015-07-17 - 17:20 | |
png | Puffer.png | r3 r2 r1 | 0.2 K | 2020-02-24 - 10:46 | |
png | QG.png | r1 | 0.4 K | 2020-02-20 - 16:02 | |
png | Sammel.PNG | r1 | 0.3 K | 2015-07-17 - 17:22 | |
png | SammelExtVGDB12.png | r1 | 0.2 K | 2018-10-19 - 07:02 | |
png | SammelExtVGDB14.png | r1 | 0.3 K | 2020-02-24 - 11:48 | |
png | SammelVGDB12.PNG | r4 r3 r2 r1 | 0.2 K | 2020-02-24 - 11:48 | |
png | SammelVGSB.PNG | r1 | 0.3 K | 2015-07-22 - 12:22 | |
png | SammelVGSBDB12.png | r2 r1 | 0.2 K | 2018-10-19 - 06:58 | |
png | Sim.PNG | r1 | 0.2 K | 2017-09-07 - 09:06 | |
png | SymbolDreieck.png | r1 | 0.6 K | 2015-07-23 - 16:00 | |
png | SymbolHaekchen.png | r1 | 0.6 K | 2015-07-23 - 16:00 | |
png | SymbolLampe.png | r1 | 0.7 K | 2015-07-23 - 16:00 | |
png | SymbolLupe.png | r1 | 0.6 K | 2015-07-23 - 16:00 | |
png | Ueberlappung.PNG | r1 | 0.3 K | 2015-07-21 - 17:06 | |
png | Ueberlast.PNG | r1 | 0.3 K | 2015-10-12 - 13:08 | |
png | Unkritisch.png | r1 | 0.4 K | 2015-07-17 - 17:19 | |
png | VGKalk.png | r1 | 0.5 K | 2015-07-17 - 17:19 | |
png | VGueberkrit.PNG | r3 r2 r1 | 0.2 K | 2020-02-24 - 10:46 | |
png | Verzug.png | r3 r2 r1 | 0.3 K | 2020-02-24 - 10:46 | |
png | Wunsch.png | r1 | 0.3 K | 2015-06-18 - 10:45 | |
png | WunschDB14.png | r1 | 0.3 K | 2019-06-13 - 12:58 | |
png | aufgabenbeschreibung.PNG | r1 | 0.4 K | 2015-07-21 - 17:05 | |
png | kritisch.png | r1 | 0.3 K | 2015-07-17 - 17:19 |