The documentation from version 39.5.17 of PLANTA project can be found in the new PLANTA Online Help.

Legends

This topic is a collection of all legends used in the entire PLANTA Wiki and serves as an including source.

Required Dates

Up to DB 14 Wunsch.png Requested dates   Requested start and Requested end are defined in the Key dates area in the corresponding core data sheet (Project Core Data, Idea Core Data, Program Core Data).
From DB 14 WunschDB14.png Requested dates   Requested start and Requested end are defined in the Key dates area in the corresponding core data sheet (Project Core Data, Idea Core Data, Proposal Core Data, Program Core Data).

Calc. Dates

Up to DB 12 Kalk.png Calculated dates The bar color is defined by the code of the planning object.
A.png Code A
B.png Code B
C.png Code C
D.png Code D
E.png Code E
Calc. start and Calc. end of a planning object are determined in the calculation of the schedule of the respective planning object.
In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.
From DB 12 KalkPRDB12.PNG Calculated dates The color of the bar is determined by the code of the planning object.
CodeADB12.PNG Code A
CodeBDB12.PNG Code B
CodeCDB12.PNG Code C
CodeDDB12.PNG Code D
CodeEDB12.PNG Code E
Calc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item.
In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.
From DB 14 KalkPRDB14.png Calculated dates The color of the bar is determined by the code of the planning object.
CodeADB14.png Code A
CodeBDB14.png Code B
CodeCDB14.png Code C
CodeDDB14.png Code D
CodeEDB14.png Code E
Calc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item.
In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.

Actual Dates

Up to DB 12 Ist.png Actual dates   Actual start and Actual end (if there is any, otherwise Latest time recording date) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) when calculating the schedule of the respective planning object.
From DB 12 ActDB12.png Actual dates   Actual start and Actual end (if there is any, otherwise Latest time recording date) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) when calculating the schedule of the respective planning object.
From DB 14 ActDB14.png Actual dates The bar is white hatched. The background color depends on the Code of the planning object. Actual start and Actual end (if there is any, otherwise Latest time recording date) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) when calculating the schedule of the respective planning object.

Master Milestones

Up to DB 12 MS.PNG Master milestones MMS_krit.PNG with date delay
MS.PNG without date delay
Tasks are defined as master milestones in the Schedule module.
From DB 12 MMSDB12.png Master milestones MMSDB12.png without date delay
MMSredDB12.png with date delay
Tasks are defined as master milestones in the Schedule module.
From DB 14 MMSDB14.png Master milestones MMSDB14.png without date delay
MMSredDB14.png with date delay
Tasks are defined as master milestones in the Schedule module.

Gates

Up to DB 14 MMSbig.png Gates MMSbig.png Gate without date delay
MMSredbig.png Gate with date delay
HMS.png Main gate/main milestone
Gates are master milestones of planning objects.
Without date delay means: Total float 0
With date delay means: Total float < 0

Gates are only displayed in the schedule module if the Schedule with gates checkbox has been activated in the Project Core Data in the core data module of the respective planning object.
From DB 14 MMSbigDB14.png Gates MMSbigDB14.png Gate without date delay
MMSredbigDB14.png Gate with date delay
HMSDB14.png Main gate/main milestone
Gates are master milestones of planning objects.
Without date delay means: Total float 0
With date delay means: Total float < 0

Gates are only displayed in the schedule module if the Schedule with gates checkbox has been activated in the Project Core Data in the core data module of the respective planning object.
From DB 12 QG.png Quality Gates   Quality Gates are the items given from the portfolio and are only displayed in planning objects if they are assigned to this planning object in the portfolio to which the planning object belongs.

Dates from Status Reports

Up to DB 12 KalkSB.PNG Calculated dates from status report   Calc. start and Calc. end of the planning object from the selected status report.
From DB 12 KalkSBDB12.png Calculated dates from status report The color of the bar equates to that of the project code (see the legend above), however, it is slightly lighter. Calc. start and Calc. end of the planning object from the selected status report.
From DB 13 KalkSBDB13.png Calculated dates from status report   Calc. start and Calc. end of the planning object from the selected status report.

External Links

From DB 15 AOBAus.png external links AOBAus.png outgoing
AOBEin.png incoming
 

Unchanged

  Puffer.png Float   Float is available if the calculated end date (Calc. end) of the planning object is earlier than the requested end date (Requested end).
  Verzug.png Date delay   A date delay occurs if the calculated end date (Calc. end) of the planning horizon is later than the requested end date (Requested end).
The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades.
  DauerProjekt.PNG Calculated project dates   Calc. start and Calc. end of a project are calculated by clicking on the calculation button or by selecting the respective menu item.
  DauerProjekt.PNG Calculated dates of the programs   Calc. start and Calc. end of a program are calculated by clicking on the calculation button or by selecting the respective menu item.
  VGueberkrit.PNG Master milestone date delay   A master milestone date delay occurs if its Calc. end is later than its Latest end.

Project Legend (Complete)

ProjectsMOD0099G2 Projects2GroupingsMOD009ALG MyWatchlistMOD009AG3 MyWatchlistMOD009C9K (Program)

From DB 39.5.15

Symbol Meaning Color Comment
WunschDB14.png Requested dates   Requested start and Requested end are defined in the Key dates area in the corresponding core data module (Project Core Data, Idea Core Data, Proposal Core Data, Program Core Data).
KalkPRDB14.png Calculated dates The color of the bar is determined by the code of the planning object.
CodeADB14.png Code A
CodeBDB14.png Code B
CodeCDB14.png Code C
CodeDDB14.png Code D
CodeEDB14.png Code E
Calc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item.
In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.
ActDB14.png Actual dates The bar is white hatched. The background color depends on the Code of the planning object. Actual start and Actual end (if there is any, otherwise Latest time recording date) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) when calculating the schedule of the respective planning object.
Puffer.png Float   Float is available if the calculated end date (Calc. end) is earlier than the requested end date (Requested end).
Verzug.png Date delay   A date delay occurs if the calculated end date (Calc. end) is later than the requested end date (Requested end).
The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades.
MMSDB14.png Master milestones MMSDB14.png Without date delay
MMSredDB14.png With date delay
Tasks are defined as master milestones in the Schedule module.
AOBAus.png external links AOBAus.png outgoing
AOBEin.png incoming
 

From DB 39.5.14

Symbol Meaning Color Comment
WunschDB14.png Requested dates   Requested start and Requested end are defined in the Key dates area in the corresponding core data module (Project Core Data, Idea Core Data, Proposal Core Data, Program Core Data).
KalkPRDB14.png Calculated dates The color of the bar is determined by the code of the planning object.
CodeADB14.png Code A
CodeBDB14.png Code B
CodeCDB14.png Code C
CodeDDB14.png Code D
CodeEDB14.png Code E
Calc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item.
In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.
ActDB14.png Actual dates The bar is white hatched. The background color depends on the Code of the planning object. Actual start and Actual end (if there is any, otherwise Latest time recording date) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) in the calculation of the schedule of the respective planning object.
Puffer.png Float   Float is available if the calculated end date (Calc. end) is earlier than the requested end date (Requested end).
Verzug.png Date delay   A date delay occurs if the calculated end date (Calc. end) is later than the requested end date (Requested end).
The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades.
MMSDB14.png Master milestones MMSDB14.png Without date delay
MMSredDB14.png With date delay
Tasks are defined as master milestones in the Schedule module.

From DB 39.5.12

Symbol Meaning Color Comment
Wunsch.png Requested dates   Requested start and Requested end are defined in the Key dates area in the corresponding core data module (Project Core Data, Idea Core Data, Proposal Core Data, Program Core Data).
KalkPRDB12.PNG Calculated dates The color of the bar is determined by the code of the planning object.
CodeADB12.PNG Code A
CodeBDB12.PNG Code B
CodeCDB12.PNG Code C
CodeDDB12.PNG Code D
CodeEDB12.PNG Code E
Calc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item.
In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.
ActDB12.png Actual dates   Actual start and Actual end (if there is any, otherwise Latest time recording date) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) when calculating the schedule of the respective planning object.
Puffer.png Float   Float is available if the calculated end date (Calc. end) is earlier than the requested end date (Requested end).
Verzug.png Date delay   A date delay occurs if the calculated end date (Calc. end) is later than the requested end date (Requested end).
The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades.
MMSDB12.png Master milestones MMSDB12.png Without date delay
MMSredDB12.png With date delay
Tasks are defined as master milestones in the Schedule module.

Up to DB 39.5.12

Symbol Meaning Color Comment
Wunsch.png Requested dates   Requested start and Requested end are defined in the Key dates area in the corresponding core data module (Project Core Data, Idea Core Data, Proposal Core Data, Program Core Data).
Kalk.png Calculated dates The color of the bar is determined by the code of the planning object.
A.png Code A
B.png Code B
C.png Code C
D.png Code D
E.png Code E
Calc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item.
In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.
Act.png Actual dates   Actual start and Actual end (if there is any, otherwise Latest time recording date) of a planning object. They are determined from the actual dates of the tasks (Actual start/Actual end) when calculating the schedule of the respective planning object.
Puffer.png Float   Float is available if the calculated end date (Calc. end) is earlier than the requested end date (Requested end).
Verzug.png Date delay   A date delay occurs if the calculated end date (Calc. end) is later than the requested end date (Requested end).
The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades.
MS.PNG Master milestones MMS_krit.PNG With date delay
MS.PNG Without date delay
Tasks are defined as master milestones in the Schedule module.

Project Legend (Semi Complete)

MyPlanningObjectsMOD0099RB CriticalProjectsMOD009AIR

From DB 39.5.14

Symbol Meaning Color Comment
WunschDB14.png Requested dates   Requested start and Requested end are defined in the Key dates area in the corresponding core data module (Project Core Data, Idea Core Data, Proposal Core Data, Program Core Data).
KalkPRDB14.png Calculated dates The color of the bar is determined by the code of the planning object.
CodeADB14.png Code A
CodeBDB14.png Code B
CodeCDB14.png Code C
CodeDDB14.png Code D
CodeEDB14.png Code E
Calc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item.
In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.
ActDB14.png Actual dates The bar is shaded in white. The background color depends on the Project Code. Actual start and, if available Actual end, otherwise Latest time recording date of a project are calculated by clicking on the calculation button or by selecting the respective menu item.
Puffer.png Float   Float is available if the calculated end date (Calc. end) is earlier than the requested end date (Requested end).
Verzug.png Date delay   A date delay occurs if the calculated end date (Calc. end) is later than the requested end date (Requested end).
The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades.
MMSDB14.png Master milestones MMSDB14.png Without date delay
MMSredDB14.png With date delay
Tasks are defined as master milestones in the Schedule module.

From DB 39.5.12

Symbol Meaning Color Comment
Wunsch.png Requested dates   Requested start and Requested end are defined in the Key dates area in the corresponding core data module (Project Core Data, Idea Core Data, Proposal Core Data, Program Core Data).
KalkPRDB12.PNG Calculated dates The color of the bar is determined by the code of the planning object.
CodeADB12.PNG Code A
CodeBDB12.PNG Code B
CodeCDB12.PNG Code C
CodeDDB12.PNG Code D
CodeEDB12.PNG Code E
Calc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item.
In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.
Puffer.png Float   Float is available if the calculated end date (Calc. end) is earlier than the requested end date (Requested end).
Verzug.png Date delay   A date delay occurs if the calculated end date (Calc. end) is later than the requested end date (Requested end).
The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades.
MMSDB12.png Master milestones MMSDB12.png Without date delay
MMSredDB12.png With date delay
Tasks are defined as master milestones in the Schedule module.

Up to DB 39.5.12

Symbol Meaning Color Comment
Wunsch.png Requested dates   Requested start and Requested end are defined in the Key dates area in the corresponding core data module (Project Core Data, Idea Core Data, Proposal Core Data, Program Core Data).
Kalk.png Calculated dates The color of the bar is determined by the code of the planning object.
A.png Code A
B.png Code B
C.png Code C
D.png Code D
E.png Code E
Calc. start and Calc. end of a planning object are calculated by clicking on the calculation button or by selecting the respective menu item.
In the Planning Objects (In Table Form) module, the code of planning objects is defined and can be changed; for projects and proposals this can also be done in the Project Core Data and Proposal Core Data modules.
Ist.png Actual dates   Actual start and, if available, Actual end, in any other case the Latest time recording date of a project are calculated by clicking on the calculation button or by selecting the respective menu item.
Puffer.png Float   Float is available if the calculated end date (Calc. end) is earlier than the requested end date (Requested end).
Verzug.png Date delay   A date delay occurs if the calculated end date (Calc. end) is later than the requested end date (Requested end).
The date delay bar immediately follows the bar for calculated dates and is customized with a color gradient so that the red color has various shades.
MS.PNG Master milestones MMS_krit.PNG With date delay
MS.PNG Without date delay
Tasks are defined as master milestones in the Schedule module.

Simulation Legend

From DB 39.5.14

Symbol Meaning Color Comment
WunschDB14.png Requested dates   Requested start and Requested end of a planning object in the simulation/road map. The dates stem from the status report which was used as a source for the simulation.
Sim.PNG Simulated dates The color of the bar is determined by the selection made in the Color in simulation field. Changed (simulated) dates (Simulation: start and Simulation: end) of a planning object
KalkSim.PNG Calculated dates   Calc. start and Calc. end of a planning object in the simulation/road map. The dates stem from the status report which was used as a source for the simulation.
ActDB12.png Actual dates The bar is shaded in white. The background color is determined by the selection made in the Color in simulation field. Actual start and Latest time recording date of a planning object in the simulation/road map. The dates stem from the status report which was used as a source for the simulation.

From DB 39.5.13

Symbol Meaning Color Comment
Wunsch.png Requested dates   Requested start and Requested end of a planning object in the simulation/road map. The dates stem from the status report which was used as a source for the simulation.
Sim.PNG Simulated dates The color of the bar is determined by the selection in the Color in simulation field Changed (simulated) dates (Simulation: start and Simulation: end) of a planning object
KalkSim.PNG Calculated dates   Calc. start and Calc. end of a planning object in the simulation/road map. The dates stem from the status report which was used as a source for the simulation.
IstTermine.PNG Actual dates   Actual start and Latest time recording date of a planning object in the simulation/road map. The dates stem from the status report which was used as a source for the simulation.

Up to DB 39.5.13

Symbol Meaning Color Comment
Wunsch.png Requested dates   Requested start and Requested end of a planning object in the simulation/road map. The dates stem from the status report which was used as a source for the simulation.
Sim.PNG Simulated dates The color of the bar is determined by the selection in the Color in simulation field Changed (simulated) dates (Simulation: start and Simulation: end) of a planning object
KalkSim.PNG Calculated dates   Calc. start and Calc. end of a planning object in the simulation/road map. The dates stem from the status report which was used as a source for the simulation.
IstTermine.PNG Actual dates   Actual start and Latest time recording date of a planning object in the simulation/road map. The dates stem from the status report which was used as a source for the simulation.

Task Legend

From DB 39.5.15

Symbol Meaning Color Comment
WunschDB14.png Task requested dates   Requested start and Requested end of a task can be defined in the corresponding data fields in the Schedule module or they can be entered directly and graphically in the Gantt chart.
KalkDB12.PNG Calculated dates of the tasks KalkDB12.PNG Uncritical
CalcCritDB12.PNG Critical
Calc. start and Calc. end are calculated by clicking on the calculation button or by selecting the respective menu item.
Uncritical means: Total float > 0
Critical means: Total float 0
Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can be critical as well.
MSDB14.png / MMSDB14.png Milestones/
Master milestones
MSDB14.png / MMSDB14.png Without delay
MSredDB14.png / MMSredDB14.png With delay
MSdoneDB12.png / MMSdoneDB12.png With actual end
Without delay means: Total float 0
With delay means: Total float < 0
SammelVGDB12.PNG Calculated dates of the summary tasks   A summary task is a task in the structured schedule which consists of subtasks and summarizes them. Information on the summary task, such as duration and dates, is determined automatically from the sub-tasks.
ActDB12.png Actual dates The respective bars are white hatched if the Splitting parameter is deactivated, and gray hatched if the parameter is activated. Actual start and, if available, Actual end, otherwise Latest time recording date of a task, are calculated from the respective dates of the resources assigned to the task by clicking on the calculation button or by selecting the respective menu item or by setting it manually.
Puffer.png Latest dates   Latest start and Latest end of a task are calculated by clicking on the calculation button or by selecting the respective menu item.
VGueberkrit.PNG Task date delay   A date delay occurs if the Calc. end of a task is later than its Latest end.
Ueberlappung.PNG Overlapping   Overlapping = Possible date delay of task successor when using soft links. For more information, see here.
KalkExtDB12.PNG Calculated dates of the external tasks KalkExtDB12.PNG Uncritical
KalkExtredDB12.png Critical
Calc. start and Calc end of the external tasks are calculated by clicking on the calculation button or by selecting the respective menu item.
Uncritical means: Total float > 0
Critical means: Total float 0
Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can be critical as well.
SammelExtVGDB14.png Calculated dates of the external summary tasks    
MSextDB12.png / MMSExtDB12.PNG Milestones/master milestones of the external summary tasks MSextDB12.png / MMSExtDB12.PNG Without delay
MSextRedDB12.png / MMSextRedDB12.png With delay
Without delay means: Total float 0
With delay means: Total float < 0
AOBAus.png External link AOBAus.png outgoing
AOBEin.png incoming
 

From DB 39.5.14

Symbol Meaning Color Comment
WunschDB14.png Task requested dates   Requested start and Requested end of a task can be defined in the corresponding data fields in the Schedule module or they can be entered directly and graphically in the Gantt chart.
KalkDB12.PNG Calculated dates of the tasks KalkDB12.PNG Uncritical
CalcCritDB12.PNG Critical
Calc. start and Calc. end are calculated by clicking on the calculation button or by selecting the respective menu item.
Uncritical means: Total float > 0
Critical means: Total float 0
Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical.
MSDB14.png / MMSDB14.png Milestones/
Master milestones
MSDB14.png / MMSDB14.png Without delay
MSredDB14.png / MMSredDB14.png With delay
MSdoneDB12.png / MMSdoneDB12.png With actual end
Without delay means: Total float 0
With delay means: Total float < 0
SammelVGDB12.PNG Calculated dates of the summary tasks   A summary task is a task in the structured schedule which consists of subtasks and summarizes them. Information on the summary task, such as duration and dates, is determined automatically from the sub-tasks.
ActDB12.png Actual dates The respective bars are white hatched if the Splitting parameter is deactivated, and gray hatched if the parameter is activated. Actual start and, if available, Actual end, otherwise Latest time recording date of a task, are calculated from the respective dates of the resources assigned to the task by clicking on the calculation button or by selecting the respective menu item or by setting it manually.
Puffer.png Latest dates   Latest start and Latest end of a task are calculated by clicking on the calculation button or by selecting the respective menu item.
VGueberkrit.PNG Task date delay   A date delay occurs if the Calc. end of a task is later than its Latest end.
Ueberlappung.PNG Overlapping   Overlapping = Possible date delay of task successor when using soft links. For more information, see here.
KalkExtDB12.PNG Calculated dates of the external tasks KalkExtDB12.PNG Uncritical
KalkExtredDB12.png Critical
Calc. start and Calc end of the external tasks are calculated by clicking on the calculation button or by selecting the respective menu item.
Uncritical means: Total float > 0
Critical means: Total float 0
Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical.
SammelExtVGDB14.png Calculated dates of the external summary tasks    
MSextDB12.png / MMSExtDB12.PNG Milestones/master milestones of the external summary tasks MSextDB12.png / MMSExtDB12.PNG Without delay
MSextRedDB12.png / MMSextRedDB12.png With delay
Without delay means: Total float 0
With delay means: Total float < 0

From DB 39.5.12

Symbol Meaning Color Comment
Wunsch.png Task requested dates   Requested start and Requested end of a task can be defined in the corresponding data fields in the Schedule module or they can be entered directly and graphically in the Gantt chart.
KalkDB12.PNG Calculated dates of the tasks KalkDB12.PNG Uncritical
CalcCritDB12.PNG Critical
Calc. start and Calc. end are calculated by clicking on the calculation button or by selecting the respective menu item.
Uncritical means: Total float > 0
Critical means: Total float 0
Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical.
MSDB12.png / MMSDB12.png Milestones/
Master milestones
MSDB12.png / MMSDB12.png Without delay
MSredDB12.png / MMSredDB12.png With delay
MSdoneDB12.png / MMSdoneDB12.png With actual end
Without delay means: Total float 0
With delay means: Total float < 0
SammelVGDB12.PNG Calculated dates of the summary tasks   A summary task is a task in the structured schedule which consists of subtasks and summarizes them. Information on the summary task, such as duration and dates, is determined automatically from the sub-tasks.
ActDB12.png Actual dates   Actual start and, if available, Actual end, otherwise Latest time recording date of a task, are calculated from the respective dates of the resources assigned to the task by clicking on the calculation button or by selecting the respective menu item or it is set manually.
Puffer.png Latest dates   Latest start and Latest end of a task are calculated by clicking on the calculation button or by selecting the respective menu item.
VGueberkrit.PNG Task date delay   A date delay occurs if the Calc. end of a task is later than its Latest end.
Ueberlappung.PNG Overlapping   Overlapping = Possible date delay of task successor when using soft links. For more information, see here.
KalkExtDB12.PNG Calculated dates of the external tasks KalkExtDB12.PNG Uncritical
KalkExtredDB12.png Critical
Calc. start and Calc end of the external tasks are calculated by clicking on the calculation button or by selecting the respective menu item.
Uncritical means: Total float > 0
Critical means: Total float 0
Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical.
SammelExtVGDB12.png Calculated dates of the external summary tasks    
MSextDB12.png / MMSExtDB12.PNG Milestones/master milestones of the external summary tasks MSextDB12.png / MMSExtDB12.PNG Without delay
MSextRedDB12.png / MMSextRedDB12.png With delay
Without delay means: Total float 0
With delay means: Total float < 0

From DB 39.5.11

Symbol Meaning Color Comment
Wunsch.png Task requested dates   Requested start and Requested end of a task can be defined in the corresponding data fields in the Schedule module or they can be entered directly and graphically in the Gantt chart.
VGKalk.png Calculated dates of the tasks VGKalk.png Uncritical
CriticNew.PNG Critical
Calc. start and Calc. end are calculated by clicking on the calculation button or by selecting the respective menu item.
Uncritical means: Total float > 0
Critical means: Total float 0
Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical.
MSgreen.PNG / MS.PNG Milestones/
master milestones
MSgreen.PNG / MS.PNG Without delay
MSred.PNG / MMS_krit.PNG With delay
MS_erl.PNG / MMS_erl.PNG With actual end
Without delay means: Total float 0
With delay means: Total float < 0
Sammel.PNG Calculated dates of the summary tasks   A summary task is a task in the structured schedule that consists of subtasks and summarizes them. Information on the summary task, such as duration and dates, is determined automatically from the sub-tasks.
Ist.png Actual dates   Actual start and, if available, Actual end, otherwise Latest time recording date of a task, are calculated from the respective dates of the resources assigned to the task by clicking on the calculation button or by selecting the respective menu item or it is set manually.
Puffer.png Latest dates   Latest start and Latest end of a task are calculated by clicking on the calculation button or by selecting the respective menu item.
VGueberkrit.PNG Task date delay   A date delay occurs if the Calc. end of a task is later than its Latest end.
Ueberlappung.PNG Overlapping   Overlapping = Possible date delay of task successor when using soft links. For more information, see here.
ExtTAUncrit.PNG Calculated dates of the external tasks ExtTA.PNG Critical
ExtTAUncrit.PNG Uncritical
Calc. start and Calc. end of the external tasks are calculated by clicking on the calculation button or by selecting the respective menu item.
Uncritical means: Total float > 0
Critical means: Total float 0
Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical.
ExtSum.PNG Calculated dates of the external summary tasks    
MSExternal.PNG Milstones/master milestones of the external tasks    

Up to DB 39.5.11

Symbol Meaning Color Comment
Wunsch.png Task requested dates   Requested start and Requested end of a task can be defined in the corresponding data fields in the Schedule module or they can be entered directly and graphically in the Gantt chart.
VGKalk.png Calculated dates of the tasks Unkritisch.png Uncritical
kritisch.png Critical
Calc. start and Calc. end are calculated by clicking on the calculation button or by selecting the respective menu item.
Uncritical means: Total float > 0
Critical means: Total float 0
Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical.
MSgreen.PNG / MS.PNG Milestones/
Master milestones
MSgreen.PNG / MS.PNG Uncritical
MSred.PNG / MMS_krit.PNG Critical
MS_erl.PNG / MMS_erl.PNG With actual end
Uncritical means: Total float 0
Critical means: Total float < 0
Sammel.PNG Calculated dates of the summary tasks   A summary task is a task in the structured schedule that consists of subtasks and summarizes them. Information on the summary task, such as duration and dates, is determined automatically from the sub-tasks.
Ist.png Actual dates   Actual start and, if available, Actual end, otherwise Latest time recording date of a task, are calculated from the respective dates of the resources assigned to the task by clicking on the calculation button or by selecting the respective menu item or it is set manually.
Puffer.png Latest dates   Latest start and Latest end of a task are calculated by clicking on the calculation button or by selecting the respective menu item.
VGueberkrit.PNG Task date delay   A date delay occurs if the Calc. end of a task is later than its Latest end.
Ueberlappung.PNG Overlapping   Overlapping = Possible date delay of task successor when using soft links. For more information, see here.
ExtTAUncrit.PNG Calculated dates of the external tasks ExtTA.PNG Critical
ExtTAUncrit.PNG Uncritical
Calc. start and Calc. end of the external tasks are calculated by clicking on the calculation button or by selecting the respective menu item.
Uncritical means: Total float > 0
Critical means: Total float 0
Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical.
ExtSum.PNG Calculated dates of the external summary tasks    
MSExternal.PNG Milstones/master milestones of the external tasks    

From DB 39.5.13

KalkSBDB13.png Calculated dates of the tasks from status report   Calculated dates of the tasks from status report Calc. start and Calc. end of the tasks from the selected status report.
SammelVGSBDB12.png Calculated dates of the summary tasks from status report   Calc. start and Calc. end of the summary tasks from the selected status report.
MSextDB13.png / MMSExtDB13.png Milestones/master milestones of the tasks from the status report    

From DB 39.5.12

KalkExtDB12.PNG Calculated dates of the tasks from status report KalkExtDB12.PNG Uncritical
KalkExtredDB12.png Critical
Calculated dates of the tasks from status report Calc. start and Calc. end of the tasks from the selected status report.
SammelVGSBDB12.png Calculated dates of the summary tasks from status report   Calc. start and Calc. end of the summary tasks from the selected status report.
MSextDB12.png / MMSExtDB12.PNG Milestones/master milestones of the tasks from status report MSextDB12.png / MMSExtDB12.PNG Without delay
MSextRedDB12.png / MMSextRedDB12.png With delay
Without delay means: Total float 0
With delay means: Total float < 0

Up to DB 39.5.12

KalkSB.PNG Calculated dates of the tasks from status report   Calc. start and Calc. end of the tasks, the milestones, and the master milestones from the selected status report.
SammelVGSB.PNG Calculated dates of summary tasks from status report   Calc. start and Calc. end of the summary tasks from the selected status report

Utilization Diagram Legend

Utilization Diagrams Without Overloads

From DB 39.5.15

Symbol Meaning Color Comment
CodeADB14.png Planned load (remaining load) of the resource(s) in projects The color of the bar is determined by the code of the projects.
CodeADB14.png Code A
CodeBDB14.png Code B
CodeCDB14.png Code C
CodeDDB14.png Code D
CodeEDB14.png Code E
The code is defined in the Project Core Data module of the respective project.
The values for the histogram bars are each calculated from the Planned code 1 to Planned code 5 columns.
ActDB12.png Actual load of the resource(s)   The values for the histogram bar are taken from the Used column from the period records of the resource(s) (DT468). The values in the period records, in turn stem from the working time recording of the resources (DT472).
KapLinieDB15.png Available capacity of resource(s)   The values for histogram bars are calculated from the Available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
The limiting line at the top of the bar will be visible despite of overlapping by utilization bars.
GrundlastLinieDB15.png Basic load of resource(s)   The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, again, comes from the general basic load defined for the resource in the Resource Data Sheet.
The limiting line at the top margin of the bar will be visible despite overlapping by utilization bars.

From DB 39.5.14

Symbol Meaning Color Comment
CodeADB14.png Planned load (remaining load) of the resource(s) in projects The color of the bar is determined by the code of the projects.
CodeADB14.png Code A
CodeBDB14.png Code B
CodeCDB14.png Code C
CodeDDB14.png Code D
CodeEDB14.png Code E
The code is defined in the Project Core Data module of the respective project.
The values for the histogram bars are each calculated from the Planned code 1 to Planned code 5 columns.
ActDB12.png Actual load of the resource(s)   The values for the histogram bar are taken from the Used column from the period records of the resource(s) (DT468). The values in the period records, in turn stem from the working time recording of the resources (DT472).
KapLinieDB14.png Available capacity of resource(s)   The values for histogram bars are calculated from the Available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
The limiting line at the top of the bar will be visible despite of overlapping by utilization bars.
GrundlastLinieDB14.png Basic load of resource(s)   The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, again, comes from the general basic load defined for the resource in the Resource Data Sheet.
The limiting line at the top margin of the bar will be visible despite overlapping by utilization bars.

From DB 39.5.12

Symbol Meaning Color Comment
CodeADB12.PNG Planned load (remaining load) of the resource(s) in projects The color of the bar is determined by the code of the projects.
CodeADB12.PNG Code A
CodeBDB12.PNG Code B
CodeCDB12.PNG Code C
CodeDDB12.PNG Code D
CodeEDB12.PNG Code E
The code is defined in the Project Core Data module of the respective project.
The values for the histogram bars are each calculated from the Planned code 1 to Planned code 5 columns.
IstHisto.png Actually incurring load (actual load) of the resource(s)   The values for the histogram bar are taken from the Used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472).
KapLinie.png Available capacity of the resource(s)   The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
NEWThe limiting line at the top of the bar will be visible despite of overlapping by utilization bars.
GrundlastLinie.png Basic load of resource(s)   The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, again, comes from the general basic load defined for the resource in the Resource Data Sheet.
NEWThe limiting line at the top margin of the bar will be visible despite overlapping by utilization bars.
Faktor4.png Factor 4 of resource(s)   The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet.
Faktor5.png Factor 5 of resource(s)   The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, again, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet.

From DB 39.5.8

Symbol Meaning Color Comment
CodeHisto.png Planned load of the resource(s) in projects The color of the bar is determined by the code of the projects.
A.png Code A
B.png Code B
C.png Code C
D.png Code D
E.png Code E
The code is defined in the Project Core Data module of the respective project.
The values for the histogram bars are each calculated from the Planned code 1 to Planned code 5 columns.
IstHisto.png Actually incurring load (actual load) of the resource(s)   The values for the histogram bar are taken from the Used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472).
KapLinie.png Available capacity of the resource(s)   The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
NEWThe limiting line at the top of the bar will be visible despite of overlapping by utilization bars.
GrundlastLinie.png Basic load of resource(s)   The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, again, comes from the general basic load defined for the resource in the Resource Data Sheet.
NEWThe limiting line at the top margin of the bar will be visible despite overlapping by utilization bars.
Faktor4.png Factor 4 of resource(s)   The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet.
Faktor5.png Factor 5 of resource(s)   The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, again, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet.

Up to DB 39.5.8

Symbol Meaning Color Comment
CodeHisto.png Planned load of the resource(s) in projects The color of the bar is determined by the code of the projects.
A.png Code A
B.png Code B
C.png Code C
D.png Code D
E.png Code E
The code is defined in the Project Core Data module of the respective project.
The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns.
IstHisto.png Actually incurring load (actual load) of the resource(s)   The values for the histogram bar are taken from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472).
Kap.png Available capacity of resource(s)   The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
GrundlastAbDb8.png Basic load of resource(s)   The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load value defined for the resource in the Resource Data Sheet.
Faktor4.png Factor 4 of resource(s)   The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet.
Faktor5.png Factor 5 of resource(s)   The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, again, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet.

Utilization Diagrams With Overloads

From DB 39.5.15

Symbol Meaning Color Comment
CodeADB14.png Planned load (remaining load) of the resource(s) in projects The color of the bar is determined by the code of the projects.
CodeADB14.png Code A
CodeBDB14.png Code B
CodeCDB14.png Code C
CodeDDB14.png Code D
CodeEDB14.png Code E
The code is defined in the Project Core Data module of the respective project.
The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns.
ActDB12.png Actually incurring load (actual load) of resource(s)   The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472).
KapLinieDB15.png Available capacity of resource(s)   The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
The limiting line at the top of the bar will be visible despite of overlapping by load data.
GrundlastLinieDB15.png Basic load of resource(s)   The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load defined for the resource in the Resource Data Sheet.
The limiting line at the top of the bar will be visible despite of overlapping by load data.
Ueberlast.PNG Overload of resource   The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned).

From DB 39.5.14

Symbol Meaning Color Comment
CodeADB14.png Planned load (remaining load) of the resource(s) in projects The color of the bar is determined by the code of the projects.
CodeADB14.png Code A
CodeBDB14.png Code B
CodeCDB14.png Code C
CodeDDB14.png Code D
CodeEDB14.png Code E
The code is defined in the Project Core Data module of the respective project.
The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns.
ActDB12.png Actually incurring load (actual load) of resource(s)   The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472).
KapLinieDB14.png Available capacity of resource(s)   The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
The limiting line at the top of the bar will be visible despite of overlapping by load data.
GrundlastLinieDB14.png Basic load of resource(s)   The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load defined for the resource in the Resource Data Sheet.
The limiting line at the top of the bar will be visible despite of overlapping by load data.
Ueberlast.PNG Overload of resource   The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned).

From DB 39.5.12

Symbol Meaning Color Comment
CodeADB12.PNG Planned load of the resource(s) in projects The color of the bar is determined by the code of the projects.
CodeADB12.PNG Code A
CodeBDB12.PNG Code B
CodeCDB12.PNG Code C
CodeDDB12.PNG Code D
CodeEDB12.PNG Code E
The code is defined in the Project Core Data module of the respective project.
The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns.
IstHisto.png Actual load of resource(s)   The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472).
KapLinie.png Available capacity of resource(s)   The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
NEWThe limiting line at the top of the bar will be visible despite of overlapping by load data.
GrundlastLinie.png Basic load of resource(s)   The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load defined for the resource in the Resource Data Sheet.
NEWThe limiting line at the top of the bar will be visible despite of overlapping by load data.
Faktor4.png Factor 4 of resource(s)   The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet.
Faktor5.png Factor 5 of resource(s)   The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet.
Ueberlast.PNG Overload of resource   The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned).

From DB 39.5.8

Symbol Meaning Color Comment
CodeHisto.png Planned load of resource(s) in the projects The bar color is determined by the project code.
A.png Code A
B.png Code B
C.png Code C
D.png Code D
E.png Code E
The code is defined in the Project Core Data module of the respective project.
The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns.
IstHisto.png Actual load of resource(s)   The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472).
KapLinie.png Available capacity of resource(s)   The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
NEWThe limiting line at the top of the bar will be visible despite of overlapping by load data.
GrundlastLinie.png Basic load of resource(s)   The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load defined for the resource in the Resource Data Sheet.
NEWThe limiting line at the top of the bar will be visible despite of overlapping by load data.
Faktor4.png Factor 4 of resource(s)   The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet.
Faktor5.png Factor 5 of resource(s)   The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet.
Ueberlast.PNG Overload of resource   The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned).

Up to DB 39.5.8

Symbol Meaning Color Comment
CodeHisto.png Planned load of resource(s) in the projects The bar color is determined by the project code.
A.png Code A
B.png Code B
C.png Code C
D.png Code D
E.png Code E
The code is defined in the Project Core Data module of the respective project.
The values for the histogram bars are each calculated from the Summarized planned code 1 to Summarized planned code 5 columns.
IstHisto.png Actual load of resource(s)   The values for the histogram bars are calculated from the Summarized used column from the period records of the resource(s) (DT468). The values in the period records, however, stem from the working time recording of the resources (DT472).
Kap.png Available capacity of resource(s)   The values for histogram bars are calculated from the Summarized available capacity column from the period records of the resource(s) (DT468). The value in DT468, however, comes from the general Available capacity defined for the resource in the Resource Data Sheet.
GrundlastAbDb8.png Basic load of resource(s)   The values for the histogram bar are calculated from the Basic load (factor value 3) column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general basic load value defined for the resource in the Resource Data Sheet.
Faktor4.png Factor 4 of resource(s)   The values for the histogram bar are calculated from the Factor value 4 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 4 defined for the resource in the Resource Data Sheet.
Faktor5.png Factor 5 of resource(s)   The values for the histogram bar are calculated from the Factor value 5 column from the period records of the resource(s)(DT468). The value in DT468, however, comes from the general value of factor 5 defined for the resource in the Resource Data Sheet.
Ueberlast.PNG Overload of resource   The overload value displayed in the red bar in percentage is calculated from the availability of the resource (Summarized available capacity) and its planned load (Summarized planned).

Resource/Task 1 Legend

From DB 39.5.14

Symbol Meaning Color Comment
WunschDB14.png Task requested dates   Requested start and Requested end of a task are defined in the Schedule module.
KalkPRDB14.png Calculated dates of the selected resource for the selected task in the selected project The color of the bar is determined by the code of the respective project. For the meaning of the individual code colors, see the histogram scale. Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.
ActDB12.png Calculated dates of the selected resource for the selected task in the selected project The bar is white hatched. Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the reported hours worked of the corresponding resource (DT472) or are edited manually.
Puffer.png Latest task dates   Latest start and Latest end of a task are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.

From DB 39.5.12

Symbol Meaning Color Comment
Wunsch.png Task requested dates   Requested start and Requested end of a task are defined in the Schedule module.
KalkPRDB12.PNG Calculated dates of the selected resource for the selected task in the selected project The color of the bar is determined by the code of the respective project. For the meaning of the individual code colors, see the histogram scale. Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.
ActDB12.png Actual dates of the selected resource for the selected task in the selected project   Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from working time recording of the corresponding resource (DT472) or are edited manually.
Puffer.png Latest task dates   Latest start and Latest end of a task are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.

Up to DB 39.5.12

Symbol Meaning Color Comment
Wunsch.png Task requested dates   Requested start and Requested end of a task are defined in the Schedule module.
Kalk.png Calculated dates of the selected resource for the selected task in the selected project The color of the bar is determined by the code of the respective project. For the meaning of the individual code colors, see the histogram scale. Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.
Ist.png Actual dates of the selected resource for the selected task in the selected project   Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the working time recording of the corresponding resource (DT472) or are edited manually.
Puffer.png Latest task dates   Latest start and Latest end of a task are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.

Resource/Task 2 Legend

From DB 39.5.14

Symbol Meaning Color Comment
WunschDB14.png Task requested dates   Requested start and Requested end of a task are defined in the Schedule module.
KalkPRVGDB14.png Calculated dates of the selected resource for the selected task in the selected project Upper bar part:
The color of the bar is determined by the code of the respective project
For the meaning of the individual code colors, see the histogram legend.

Lower bar part:
KalkDB12.PNG Uncritical task
CalcCritDB12.PNG Critical task
Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.




Uncritical means: Total float > 0
Critical means: Total float 0
Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical.
ActDB12.png Calculated dates of the selected resource for the selected task in the selected project The bar is white hatched. Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the working time recording of the respective resource (DT472) or edited manually.
Puffer.png Latest task dates   Latest start and Latest end of a task are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.
VGueberkrit.PNG Task date delay   A date delay occurs if Calc. end of a task is later than its Latest end.

From DB 39.5.12

Symbol Meaning Color Comment
Wunsch.png Task requested dates   Requested start and Requested end of a task are defined in the Schedule module.
KalkPRVGDB12.png Calculated dates of the selected resource for the selected task in the selected project Upper bar part:
The color of the bar is determined by the code of the respective project
For the meaning of the individual code colors, see the histogram legend.

Lower bar part:
KalkDB12.PNG Uncritical task
CalcCritDB12.PNG Critical task
Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.




Uncritical means: Total float > 0
Critical means: Total float 0
Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical.
ActDB12.png Actual dates of the selected resource for the selected task in the selected project   Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the reported hours worked of the corresponding resource (DT472) or are edited manually.
Puffer.png Latest task dates   Latest start and Latest end of a task are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.
VGueberkrit.PNG Task date delay   A date delay occurs if Calc. end of a task is later than its Latest end.

From DB 39.5.11

Symbol Meaning Color Comment
Wunsch.png Task requested dates   Requested start and Requested end of a task are defined in the Schedule module.
KalkPRVG.PNG Calculated dates of the selected resource for the selected task in the selected project Upper bar part:
The color of the bar is determined by the code of the respective project
For the meaning of the individual code colors, see the histogram legend.

Lower bar part:
VGKalk.png Uncritical task
CriticNew.PNG Critical task
Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.




Uncritical means: Total float > 0
Critical means: Total float 0
Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical.
Ist.png Actual dates of the selected resource for the selected task in the selected project   Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the reported hours worked of the corresponding resource (DT472) or are edited manually.
Puffer.png Latest task dates   Latest start and Latest end of a task are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.
VGueberkrit.PNG Task date delay   A date delay occurs if Calc. end of a task is later than its Latest end.

Up to DB 39.5.11

Symbol Meaning Color Comment
Wunsch.png Task requested dates   Requested start and Requested end of a task are defined in the Schedule module.
KalkPRVG.PNG Calculated dates of the selected resource for the selected task in the selected project Upper bar part:
The color of the bar is determined by the code of the respective project
For the meaning of the individual code colors, see the histogram legend.

Lower bar part:
Unkritisch.png Uncritical task
kritisch.png Critical task
Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.



Uncritical means: Total float > 0
Critical means: Total float 0
Since in PLANTA project the setting of requested dates on tasks leads to Total float = 0, tasks that do not necessarily lie on the critical path can also be critical.
Ist.png Actual dates of the selected resource for the selected task in the selected project   Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the reported hours worked of the corresponding resource (DT472) or are edited manually.
Puffer.png Latest task dates   Latest start and Latest end of a task are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.
VGueberkrit.PNG Task date delay   A date delay occurs if Calc. end of a task is later than its Latest end.

Resource/Task 3 Legend

From DB 39.5.14

Symbol Meaning Color Comment
KalkPRDB14.png Calculated dates of the resource for the selected task in the selected project The color of the bar is determined by the code of the corresponding project.
CodeADB14.png Code A
CodeBDB14.png Code B
CodeCDB14.png Code C
CodeDDB14.png Code D
CodeEDB14.png Code E
Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.
ActDB12.png Actual dates of the selected resource for the selected task in the selected project The bar is white hatched. Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the reported hours worked of the corresponding resource (DT472) or are edited manually.
aufgabenbeschreibung.PNG Date of tasks, risks and opportunity measures and process steps   The date value for the bar is calculated:
  • for the todo items from the Date (DT804) field
  • for the risks measures from the Date (DT811) field
  • for the opportunity measures from the Date (DT813) field
  • for the process steps from the Date (DT499) field.

From DB 39.5.12

Symbol Meaning Color Comment
KalkPRDB12.PNG Calculated dates of the resource for the selected task in the selected project The color of the bar is determined by the code of the corresponding project.
CodeADB12.PNG Code A
CodeBDB12.PNG Code B
CodeCDB12.PNG Code C
CodeDDB12.PNG Code D
CodeEDB12.PNG Code E
Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.
ActDB12.png Actual dates of the selected resource for the selected task in the selected project   Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the reported hours worked of the corresponding resource (DT472) or are edited manually.
aufgabenbeschreibung.PNG Date of tasks, risks and opportunity measures and process steps   The date value for the bar is calculated:
  • for the todo items from the Date (DT804) field
  • for the risks measures from the Date (DT811) field
  • for the opportunity measures from the Date (DT813) field
  • for the process steps from the Date (DT499) field.

Up to DB 39.5.12

Symbol Meaning Color Comment
Kalk.png Calculated dates of the resource for the selected task in the selected project The color of the bar is determined by the code of the corresponding project.
A.png Code A
B.png Code B
C.png Code C
D.png Code D
E.png Code E
Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.
Ist.png Actual dates of the selected resource for the selected task in the selected project   Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the reported hours worked of the corresponding resource (DT472) or are edited manually.
aufgabenbeschreibung.PNG Date of tasks, risks and opportunity measures and process steps   The date value for the bar is calculated:
  • for the todo items from the Date (DT804) field
  • for the risks measures from the Date (DT811) field
  • for the opportunity measures from the Date (DT813) field
  • for the process steps from the Date (DT499) field.

Resources/Task 4 Legend (since only in MOD My Todo Items, none from DB 12 tabs)

Symbol Meaning Color Comment
Kalk.png Calculated dates of the resource for the selected task in the selected project The color of the bar is determined by the code of the corresponding project.
A.png Code A
B.png Code B
C.png Code C
D.png Code D
E.png Code E
Calc. start, and Calc. end of a resource in a task (resource assignment) are calculated by clicking on the calculation button in the toolbar or by selecting the respective menu item.
Ist.png Actual dates of the selected resource for the selected task in the selected project   Actual start and last Latest time recording date of a resource in a task (resource assignment) are calculated from the reported hours worked of the corresponding resource (DT472) or are edited manually.
aufgabenbeschreibung.PNG Date of todo items, risks and opportunity measures and process steps   The date value for the bar is calculated:
  • for the todo items from the Date (DT804) field
  • for the risks measures from the Date (DT811) field
  • for the opportunity measures from the Date (DT813) field
  • for the process steps from the Date (DT499) field.

Todo Items Legend

Symbol Meaning Comment
aufgabenbeschreibung.PNG Todo item date The date value for the bar is calculated from the Date (DT804) field.

Migration Packets from S 39.5.17 Legend

Legend
  • LampeWeiss.png indicates that the migration packet has not been executed yet.
  • LampeGruen.png indicates that the migration packet has run successfully.
  • LampeRot.png indicates that the migration packet has failed. The failure of a migration packet may have several reasons:
    • Before they are run, many migration packets check whether the customizing on which the fix is based, has changed.
      • If this is the case, the packet will not be changed. The packet is considered failed.
        • In this case, the customizing has to be checked in order to find out whether the modification in question can be carried out.
        • If the modification has been carried out or the modification is not necessary, the packet can be set to completed manually by activating the Completed checkbox.
        • As a result, it is moved from the Failed/open packets area to the Completed Packets module.
    • Many help packets check the customizing for problems.
      • If they fail, this means that the customizer must become active.
      • As a result, the positions listed in the logfile have to be checked and modified.
      • If the cause for the failure has been eliminated, the migration packet can be run again by clicking on the Run packet button in the Overview of all Previous Runs module.
  • LampeGelb.png NEW signalizes that this migration packet is still open and waits for another migrationpacket to reach a particular status before it can be run.
  • LampeGrau.png NEW signalizes that this migration packet is not relevant for the current update type due to version dependencies.
  • SymbolDreieck.png means that this migration packet has been skipped. This status is not used at the moment.

Migration Packets up to S 39.5.17 Legend

Legend
  • SymbolLupe.png signalizes that the migration packet has not been executed yet.
  • SymbolDreieck.png means that this migration packet has been skipped.
  • SymbolLampe.png signalizes that the migration packet has failed. The failure of a migration packet may have several reasons:
    • Before they are run, many migration packets check whether the customizing on which the fix is based, has changed.
      • If this is the case, the packet will not be changed. The packet is considered failed.
        • In this case, the customizing has to be checked in order to find out whether the modification in question can be carried out.
        • If the modification has been carried out or the modification is not necessary, the packet can be set to completed manually by activating the Completed checkbox.
        • As a result, it is moved from the Failed packets area to the Completed Packets module.
    • Many help packets check the customizing for problems.
      • If they fail, this means that the customizer must become active.
      • As a result, the positions listed in the logfile have to be checked and modified.
      • If the cause for the failure has been fixed, the migration packet can be run again by clicking on the Run packet button in the Overview of all Previous Runs module.
  • SymbolHaekchen.png means that a migration packet has run successfully.

Topic attachments
I Attachment History Size Date Comment
Pngpng A.png r1 0.3 K 2015-06-18 - 10:46  
Pngpng AOBAus.png r1 0.3 K 2020-02-21 - 10:47  
Pngpng AOBEin.png r1 0.3 K 2020-02-21 - 10:47  
Pngpng ActDB12.png r3 r2 r1 0.2 K 2018-10-19 - 10:34  
Pngpng ActDB14.png r3 r2 r1 0.3 K 2020-02-24 - 10:45  
Pngpng B.png r1 0.3 K 2015-06-18 - 10:46  
Pngpng C.png r1 0.3 K 2015-06-18 - 10:46  
Pngpng CalcCritDB12.PNG r2 r1 0.3 K 2018-10-09 - 09:41  
Pngpng CodeADB12.PNG r1 0.2 K 2018-10-09 - 08:59  
Pngpng CodeADB14.png r2 r1 0.2 K 2019-06-13 - 13:56  
Pngpng CodeBDB12.PNG r1 0.2 K 2018-10-09 - 08:59  
Pngpng CodeBDB14.png r2 r1 0.2 K 2019-06-13 - 13:56  
Pngpng CodeCDB12.PNG r1 0.2 K 2018-10-09 - 08:59  
Pngpng CodeCDB14.png r2 r1 0.2 K 2019-06-13 - 13:56  
Pngpng CodeDDB12.PNG r1 0.2 K 2018-10-09 - 08:59  
Pngpng CodeDDB14.png r2 r1 0.2 K 2019-06-13 - 13:56  
Pngpng CodeEDB12.PNG r5 r4 r3 r2 r1 0.1 K 2018-10-09 - 09:05  
Pngpng CodeEDB14.png r2 r1 0.2 K 2019-06-13 - 13:56  
Pngpng CodeHisto.png r1 0.4 K 2015-07-17 - 12:09  
Pngpng CriticNew.PNG r3 r2 r1 0.4 K 2018-01-18 - 11:32  
Pngpng D.png r1 0.3 K 2015-06-18 - 10:47  
Pngpng DauerProjekt.PNG r1 0.4 K 2015-07-23 - 13:02  
Pngpng E.png r1 0.3 K 2015-06-18 - 10:47  
Pngpng ExtSum.PNG r1 0.3 K 2015-09-10 - 19:09  
Pngpng ExtTA.PNG r6 r5 r4 r3 r2 0.3 K 2015-09-10 - 19:14  
Pngpng ExtTAUncrit.PNG r2 r1 0.2 K 2015-09-10 - 19:12  
Pngpng Faktor4.png r1 0.4 K 2015-07-17 - 12:09  
Pngpng Faktor5.png r1 0.3 K 2015-07-17 - 12:09  
Pngpng Grundlast.png r1 0.3 K 2015-07-17 - 12:09  
Pngpng GrundlastAbDb8.png r1 0.2 K 2016-08-31 - 03:30  
Pngpng GrundlastLinie.png r1 0.2 K 2016-08-31 - 01:38  
Pngpng GrundlastLinieDB14.png r2 r1 0.2 K 2019-06-25 - 08:47  
Pngpng GrundlastLinieDB15.png r1 0.2 K 2020-02-21 - 10:40  
Pngpng HMS.png r1 0.5 K 2020-03-05 - 13:19  
Pngpng HMSred.png r1 0.4 K 2020-02-20 - 15:30  
Pngpng Ist.png r1 0.3 K 2015-06-18 - 10:47  
Pngpng IstBel.png r1 1.0 K 2015-07-17 - 12:09  
Pngpng IstHisto.png r3 r2 r1 0.3 K 2018-10-19 - 10:21  
Pngpng IstTermine.PNG r2 r1 0.3 K 2017-09-20 - 10:41  
Pngpng Kalk.png r1 0.5 K 2015-06-18 - 10:47  
Pngpng KalkDB12.PNG r3 r2 r1 0.4 K 2018-10-09 - 09:49  
Pngpng KalkExtDB12.PNG r2 r1 0.3 K 2018-10-19 - 07:58  
Pngpng KalkExtSammelDB12.PNG r1 0.2 K 2018-10-09 - 11:55  
Pngpng KalkExtredDB12.png r1 0.3 K 2018-10-09 - 12:08  
Pngpng KalkPRDB12.PNG r2 r1 0.4 K 2018-10-09 - 09:34  
Pngpng KalkPRDB14.png r2 r1 0.3 K 2020-02-24 - 10:46  
Pngpng KalkPRG.PNG r2 r1 0.4 K 2015-09-22 - 19:08  
Pngpng KalkPRVG.PNG r1 0.6 K 2015-07-20 - 12:11  
Pngpng KalkPRVGDB12.png r1 0.5 K 2018-10-19 - 11:18  
Pngpng KalkPRVGDB14.png r2 r1 0.5 K 2020-02-24 - 13:21  
Pngpng KalkSB.PNG r1 0.3 K 2015-07-22 - 12:02  
Pngpng KalkSBDB12.png r3 r2 r1 0.3 K 2018-10-10 - 11:42  
Pngpng KalkSBDB13.png r1 0.3 K 2018-12-13 - 14:25  
Pngpng KalkSim.PNG r1 0.3 K 2017-09-07 - 09:06  
Pngpng Kap.png r1 0.3 K 2015-07-17 - 12:08  
Pngpng KapLinie.png r1 0.2 K 2016-08-31 - 03:02  
Pngpng KapLinieDB14.png r2 r1 0.2 K 2019-06-13 - 14:12  
Pngpng KapLinieDB15.png r1 0.2 K 2020-02-21 - 10:40  
Pngpng LampeGelb.png r1 0.5 K 2015-07-23 - 12:12  
Pngpng LampeGrau.png r1 0.6 K 2015-07-23 - 12:13  
Pngpng LampeGruen.png r1 0.5 K 2015-07-23 - 12:13  
Pngpng LampeRot.png r1 0.5 K 2015-07-23 - 12:13  
Pngpng LampeWeiss.png r1 0.5 K 2015-07-23 - 12:13  
Pngpng Linie.png r1 0.2 K 2016-08-31 - 03:08  
Pngpng MMSCritNew.PNG r1 0.4 K 2018-01-18 - 12:47  
Pngpng MMSDB12.png r1 0.3 K 2018-10-09 - 09:54  
Pngpng MMSDB14.png r1 0.3 K 2019-06-13 - 13:22  
Pngpng MMSExtDB12.PNG r1 0.3 K 2018-10-19 - 07:11  
Pngpng MMSExtDB13.png r1 0.3 K 2018-12-14 - 10:07  
Pngpng MMSGrey.PNG r1 0.3 K 2018-10-09 - 07:07  
Pngpng MMS_erl.PNG r1 0.5 K 2015-09-11 - 18:33  
Pngpng MMS_krit.PNG r2 r1 0.5 K 2015-09-11 - 18:09  
Pngpng MMSbig.png r1 0.5 K 2020-03-05 - 13:19  
Pngpng MMSdoneDB12.png r2 r1 0.3 K 2018-10-18 - 11:47  
Pngpng MMSextRedDB12.png r1 0.3 K 2018-10-19 - 07:10  
Pngpng MMSredDB12.png r2 r1 0.3 K 2018-10-09 - 10:18  
Pngpng MMSredDB14.png r2 r1 0.3 K 2019-11-28 - 13:36  
Pngpng MMSredbig.png r1 0.5 K 2020-03-05 - 13:19  
Pngpng MS.PNG r1 0.5 K 2015-09-11 - 18:06  
Pngpng MS.png r1 0.6 K 2015-06-18 - 10:47  
Pngpng MSCritNew.png r1 0.4 K 2018-01-18 - 12:48  
Pngpng MSDB12.png r1 0.3 K 2018-10-09 - 09:53  
Pngpng MSDB14.png r1 0.3 K 2019-06-13 - 13:42  
Pngpng MSExternal.PNG r1 0.3 K 2018-08-29 - 11:49  
Pngpng MSGrey.PNG r1 0.3 K 2018-10-09 - 07:07  
Pngpng MS_erl.PNG r2 r1 0.5 K 2015-09-11 - 18:34  
Pngpng MSdoneDB12.png r3 r2 r1 0.3 K 2019-11-28 - 13:27  
Pngpng MSextDB12.png r1 0.3 K 2018-10-19 - 07:10  
Pngpng MSextDB13.png r1 0.3 K 2018-12-14 - 10:07  
Pngpng MSextRedDB12.png r1 0.3 K 2018-10-19 - 07:10  
Pngpng MSgreen.PNG r2 r1 0.5 K 2015-09-11 - 17:58  
Pngpng MSred.PNG r1 0.5 K 2015-09-11 - 18:01  
Pngpng MSredDB12.png r2 r1 0.3 K 2018-10-09 - 10:19  
Pngpng MSredDB14.png r2 r1 0.3 K 2019-11-28 - 13:34  
Pngpng Milestone.PNG r1 0.4 K 2015-07-17 - 17:20  
Pngpng Puffer.png r3 r2 r1 0.2 K 2020-02-24 - 10:46  
Pngpng QG.png r1 0.4 K 2020-02-20 - 16:02  
Pngpng Sammel.PNG r1 0.3 K 2015-07-17 - 17:22  
Pngpng SammelExtVGDB12.png r1 0.2 K 2018-10-19 - 07:02  
Pngpng SammelExtVGDB14.png r1 0.3 K 2020-02-24 - 11:48  
Pngpng SammelVGDB12.PNG r4 r3 r2 r1 0.2 K 2020-02-24 - 11:48  
Pngpng SammelVGSB.PNG r1 0.3 K 2015-07-22 - 12:22  
Pngpng SammelVGSBDB12.png r2 r1 0.2 K 2018-10-19 - 06:58  
Pngpng Sim.PNG r1 0.2 K 2017-09-07 - 09:06  
Pngpng SymbolDreieck.png r1 0.6 K 2015-07-23 - 16:00  
Pngpng SymbolHaekchen.png r1 0.6 K 2015-07-23 - 16:00  
Pngpng SymbolLampe.png r1 0.7 K 2015-07-23 - 16:00  
Pngpng SymbolLupe.png r1 0.6 K 2015-07-23 - 16:00  
Pngpng Ueberlappung.PNG r1 0.3 K 2015-07-21 - 17:06  
Pngpng Ueberlast.PNG r1 0.3 K 2015-10-12 - 13:08  
Pngpng Unkritisch.png r1 0.4 K 2015-07-17 - 17:19  
Pngpng VGKalk.png r1 0.5 K 2015-07-17 - 17:19  
Pngpng VGueberkrit.PNG r3 r2 r1 0.2 K 2020-02-24 - 10:46  
Pngpng Verzug.png r3 r2 r1 0.3 K 2020-02-24 - 10:46  
Pngpng Wunsch.png r1 0.3 K 2015-06-18 - 10:45  
Pngpng WunschDB14.png r1 0.3 K 2019-06-13 - 12:58  
Pngpng aufgabenbeschreibung.PNG r1 0.4 K 2015-07-21 - 17:05  
Pngpng kritisch.png r1 0.3 K 2015-07-17 - 17:19  

         PLANTA project









 
  • Suche in Topic-Namen

  • Suche in Topic-Inhalten
This site is powered by the TWiki collaboration platform Powered by Perl